Panduan Trafik Lobak 2 Seremban REV 5
Panduan Trafik Lobak 2 Seremban REV 5
DISEMBER 2012
TAMAN
PERMATA
`
PETRONAS
`
`
TAMAN
BAIDURI
TAMAN
KOOP
SK PUTERI
PIPE JACKING (1.695km)
SMK
PUTERI OPEN EXCAVATION
(2.041km)
PIPE JACKING (1.022km) SJK(C) CHAN WA
TAMAN SAGA
BIL. KRITERIA PERKARA
ZONE B:
1)PADANG MPS (HADAPAN S.J.K. TAMIL)
KERJA-KERJA YANG MELIBATKAN
DIBAHU JALAN ADALAH:
1) JALAN PERMATA 1
2) JALAN BAIDURI 5
3) LORONG JALAN PERMATA 1
4) PADANG MPS (HADAPAN S.J.K. TAMIL)
Zon A
MH A13
MH A14
MH A12
MH A12-1
MH A12-2F
JALAN BAIDURI 5
JALAN 2 LORONG 1 HALA
4m 4m
MH A12-2F
KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN BAIDURI 5
JALAN 2 LORONG 1 HALA
3.5m
12-2
MH A
7m
KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN PERMATA 1
JALAN 2 LORONG 1 HALA
MH A12
7m
3.5m
KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN PERMATA 1
JALAN 2 LORONG 2 HALA
MH A14
7m
3.5m
KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN PERMATA 1
JALAN 2 LORONG 1 HALA
MH A13
7m
3.5m
KERJA MELIBATKAN
BAHU JALAN
SAHAJA
Zon A
MH A10
MH A8
MH A9
MH A11
MH A8-1
JALAN PERMATA 1
JALAN 2 LORONG 1 HALA
MH A11
7m
3.5m
KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN PERMATA 1
JALAN 2 LORONG 1 HALA
MH A10
7m
3.5m
KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN PERMATA 1
JALAN 2 LORONG 1 HALA
MH A9
7m
3.5m
KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN PERMATA 1
JALAN 2 LORONG 1 HALA
MH A8
7m
3.5m
KERJA MELIBATKAN
BAHU JALAN
SAHAJA
LORONG JALAN PERMATA 1
JALAN 1 LORONG 1 HALA
MH A8-1
7m
4m
KERJA MELIBATKAN
BAHU JALAN
SAHAJA
Zon A
MH A1
MH A5
MH A4
MH A2
MH A6
MH A3
MH A7
JALAN PERMATA 1
JALAN 2 LORONG 1 HALA
MH A7
7m
3.5m
KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN PERMATA 1
JALAN 2 LORONG 1 HALA
MH A6
7m
3.5m
KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN PERMATA 1
JALAN 2 LORONG 1 HALA
MH A5
7m
3.5m
KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN PERMATA 1
JALAN 2 LORONG 1 HALA
MH A4
7m
3.5m
KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN PERMATA 1
JALAN 2 LORONG 1 HALA
MH A3
7m
3.5m
KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN LOBAK
JALAN 2 LORONG 2 HALA
4m
7m
MH A2
KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN LOBAK
JALAN 2 LORONG 2 HALA
4m
7m
MH A1
KERJA MELIBATKAN
BAHU JALAN
SAHAJA
KEDUDUKAN MESIN DAN PERALATAN DI
KAWASAN BAHU JALAN
JALAN 2 LORONG 1 HALA
Genset &
tools
Tank
water
Control
26m room
Jacking
BARRICAGE WIDTH = + 0.5 m pit
Excavator
Pipes
3.5m
KERJA-KERJA DIJALANKAN DIBAHU JALAN
JALAN 2 LORONG 1 HALA
Genset &
tools
Tank
water
Control
26m room
Jacking
BARRICAGE WIDTH = + 0.5 m pit
Excavator
Pipes
3.5m
KERJA-KERJA DIJALANKAN DIBAHU JALAN
JALAN 2 LORONG 2 HALA
MH B7
MH A4-1
MH A4-1
MH B6
PADANG DEPAN S.J.K TAMIL
LALUAN P
AIP JACKI
NG
MH B7 4m
PADANG DEPAN S.J.K TAMIL
MH B4-2
7m
LALUAN PAIP JACKING
4m
MH B7-1
MH B7 MH B7-1
7m
PADANG DEPAN S.J.K TAMIL
MH B4
LALUAN PAIP JACKING
MH B5
7m
4m
7m
MH B6
LALUAN PAIP JACKING
4m
PADANG DEPAN S.J.K TAMIL
To be con
nected to
MH B4 MH B4-1
7m
MH B4-1
7m
MH B4-2
4m
KEDUDUKAN MESIN DAN PERALATAN DI
KAWASAN BAHU JALAN
DI TEPI PADANG
Genset &
tools
Tank
water
Control
26m room
Jacking
BARRICAGE WIDTH = + 0.5 m pit
Excavator
Pipes
4m
KERJA-KERJA DIJALANKAN DIBAHU JALAN
DI TEPI PADANG