CADANGAN PEMBINAAN PAIP PEMBETUNGAN TAMBAHAN

RASIONALISASI LOJI RAWATAN KUMBAHAN


DI KAWASAN TADAHAN LOBAK 2
SEREMBAN
NEGARI SEMBILAN

JABATAN PERKHIDMATAN PEMBETUNGAN


TAKLIMAT PROJEK
SERTA
LAPORAN PEMBINAAN PAIP PEMBETUNGAN TAMBAHAN
DI KAWASAN LOBAK 2
KEPADA
MAJLIS PERBANDARAN SEREMBAN

DISEMBER 2012

PEMBINAAN JURUBINA SDN. BHD


Kontraktor Utama
ISI KANDUNGAN

1. MAKLUMAT ASAS PROJEK


2. MAKLUMAT PENGAWASAN DI TAPAK
3. LATAR BELAKANG PROJEK
4. SKOP KERJA
5. RINGKASAN KRITERIA REKABENTUK
6. PENYIASATAN TANAH
7. RASIONALISASI LOJI RAWATAN KUMBAHAN
8. LOKASI, KATEGORI SERTA JUMLAH TIAP-TIAP PE
9. PENGURUSAN PELAN LALULINTAS
KESELURUHAN KAWASAN KERJA
KAWASAN KERJA DI ZON A
KAWASAN KERJA DI ZON B
PERUMAHAN
LOBAK

TAMAN
PERMATA

`
PETRONAS

`
`

TAMAN
BAIDURI
TAMAN
KOOP

SK PUTERI
PIPE JACKING (1.695km)
SMK
PUTERI OPEN EXCAVATION
(2.041km)
PIPE JACKING (1.022km) SJK(C) CHAN WA

OPEN EXCAVATION (0.16km)

SJK(T) JLN LOBAK

TAMAN TUANKU ABDUL


RAHMAN

TAMAN SAGA
BIL. KRITERIA PERKARA

1 HALAJU 1.00 m/s to 3.50 m/s

i) SAIZ LURANG i) 1350mm & 1500mm.


2
ii) KEDALAMAN ii) 2.000m to 12.19.000m.

3 SAIZ FORCEMAIN 100mm

KAEDAH DIGUNAKAN UNTUK


PIPE JACKING &
4 PEMASANGAN PAIP
PENGOREKAN TERBUKA
PEMBETUNG
VCP 225mm
RCJP 300mm
5 JENIS PAIP & SAIZ RCJP 375mm
RCJP 450mm
RCJP 525mm
8. LOKASI, KATEGORI SERTA JUMLAH P.E BAGI TIAP-TIAP
STP
No Asset No Location Category Total of PE
1 SEN 243 Taman Bukit Jed (Fasa 1A & 1B) EA 5800
2 SEN 176 Taman Baiduri EA 1410
3 SEN 166 Taman Permata EA 3600
4 SEN 167 Taman Permata NPS 3600
5 SEN 068 Taman Koop ITPS 215
6 SEN 098 Tmn Tuanku Abd Rahman IT 400
7 SEN 175 Lobak CST 1000
8 - Flat Lobak CST 5000
9 - SMK Putri CST 400
10 - SRK Putri CST 400
11 - SJK(C) Chan Wa CST 300
12 - SJT(T) Lobak CST 300
13 - Taman Yong Seng IST 305
MAKLUMAT PEMILIK PROJEK
PAPANTANDA PEMBERITAHUAN KERJA-KARJA
PLASTIC HOARDING BARRICAGE
PAPAN TANDA PERINGATAN/PANDUAN TRAFIK
PAPAN TANDA PERINGATAN/PANDUAN TRAFIK
LENCONGAN TRAFIK
PANDUAN/KAWALAN TRAFIK
PAPAN TANDA PANDUAN TRAFIK
PAPAN TANDA PANDUAN TRAFIK
ANTARA JALAN-JALAN YANG
TERLIBAT DI SEPANJANG KERJA-
KERJA PEMASANGAN PAIP ADALAH:
ZONE A:
1)JALAN PERMATA 1 KE JALAN VELOO
2)JALAN BAIDURI 5 KE JALAN PERMATA 1
3)LORONG JALAN PERMATA 1 KE JALAN PERMATA 1

ZONE B:
1)PADANG MPS (HADAPAN S.J.K. TAMIL)
KERJA-KERJA YANG MELIBATKAN
DIBAHU JALAN ADALAH:

1) JALAN PERMATA 1
2) JALAN BAIDURI 5
3) LORONG JALAN PERMATA 1
4) PADANG MPS (HADAPAN S.J.K. TAMIL)
Zon A
MH A13

MH A14

MH A12

MH A12-1

MH A12-2F
JALAN BAIDURI 5
JALAN 2 LORONG 1 HALA

4m 4m

MH A12-2F

KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN BAIDURI 5
JALAN 2 LORONG 1 HALA

3.5m
12-2
MH A

7m

KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN PERMATA 1
JALAN 2 LORONG 1 HALA

MH A12

7m

3.5m

KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN PERMATA 1
JALAN 2 LORONG 2 HALA

MH A14

7m

3.5m

KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN PERMATA 1
JALAN 2 LORONG 1 HALA

MH A13

7m

3.5m

KERJA MELIBATKAN
BAHU JALAN
SAHAJA
Zon A
MH A10

MH A8

MH A9
MH A11

MH A8-1
JALAN PERMATA 1
JALAN 2 LORONG 1 HALA

MH A11

7m

3.5m

KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN PERMATA 1
JALAN 2 LORONG 1 HALA

MH A10

7m

3.5m

KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN PERMATA 1
JALAN 2 LORONG 1 HALA

MH A9

7m
3.5m

KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN PERMATA 1
JALAN 2 LORONG 1 HALA

MH A8

7m

3.5m

KERJA MELIBATKAN
BAHU JALAN
SAHAJA
LORONG JALAN PERMATA 1
JALAN 1 LORONG 1 HALA

MH A8-1

7m

4m

KERJA MELIBATKAN
BAHU JALAN
SAHAJA
Zon A

MH A1
MH A5

MH A4

MH A2

MH A6

MH A3
MH A7
JALAN PERMATA 1
JALAN 2 LORONG 1 HALA

MH A7

7m

3.5m

KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN PERMATA 1
JALAN 2 LORONG 1 HALA

MH A6

7m

3.5m

KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN PERMATA 1
JALAN 2 LORONG 1 HALA

MH A5

7m

3.5m

KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN PERMATA 1
JALAN 2 LORONG 1 HALA

MH A4

7m

3.5m

KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN PERMATA 1
JALAN 2 LORONG 1 HALA

MH A3

7m

3.5m

KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN LOBAK
JALAN 2 LORONG 2 HALA

4m

7m
MH A2

KERJA MELIBATKAN
BAHU JALAN
SAHAJA
JALAN LOBAK
JALAN 2 LORONG 2 HALA

4m
7m

MH A1

KERJA MELIBATKAN
BAHU JALAN
SAHAJA
KEDUDUKAN MESIN DAN PERALATAN DI
KAWASAN BAHU JALAN
JALAN 2 LORONG 1 HALA

Genset &
tools

Tank
water

Control
26m room

Jacking
BARRICAGE WIDTH = + 0.5 m pit

Excavator

Pipes

3.5m
KERJA-KERJA DIJALANKAN DIBAHU JALAN
JALAN 2 LORONG 1 HALA

KERJA-KERJA YANG DIJALANKAN DIBAHU JALAN


TIDAK MENGGANGGU ALIRAN TRAFIK
KEDUDUKAN MESIN DAN PERALATAN DI
KAWASAN BAHU JALAN
JALAN 2 LORONG 2 HALA

Genset &
tools

Tank
water

Control
26m room

Jacking
BARRICAGE WIDTH = + 0.5 m pit

Excavator

Pipes

3.5m
KERJA-KERJA DIJALANKAN DIBAHU JALAN
JALAN 2 LORONG 2 HALA

KERJA-KERJA YANG DIJALANKAN DIBAHU JALAN


TIDAK MENGGANGGU ALIRAN TRAFIK
Zon B
MH B7-1
MH A4-2

MH B7
MH A4-1

MH A4-1

MH B6
PADANG DEPAN S.J.K TAMIL

MH B7-1 LALUAN PAIP JAC


7m KING

LALUAN P
AIP JACKI
NG
MH B7 4m
PADANG DEPAN S.J.K TAMIL

LALUAN PAIP JACKING

MH B4-2

7m
LALUAN PAIP JACKING
4m
MH B7-1

LALUAN PAIP JACKING


PADANG DEPAN S.J.K TAMIL

MH B7 MH B7-1

LALUAN PAIP JACKING

LALUAN PAIP JACKING


4m MH B6

7m
PADANG DEPAN S.J.K TAMIL

MH B4
LALUAN PAIP JACKING
MH B5
7m
4m

7m

MH B6
LALUAN PAIP JACKING

4m
PADANG DEPAN S.J.K TAMIL

To be con
nected to
MH B4 MH B4-1
7m

LALUAN PAIP JACKING


4m

LALUAN PAIP JACKING


PADANG DEPAN S.J.K TAMIL

MH B4-1

LALUAN PAIP JACKING


LALUAN PAIP JACKING

7m
MH B4-2

4m
KEDUDUKAN MESIN DAN PERALATAN DI
KAWASAN BAHU JALAN
DI TEPI PADANG

Genset &
tools

Tank
water

Control
26m room

Jacking
BARRICAGE WIDTH = + 0.5 m pit

Excavator

Pipes

4m
KERJA-KERJA DIJALANKAN DIBAHU JALAN
DI TEPI PADANG

KERJA-KERJA YANG DIJALANKAN DITEPI PADANG


TIDAK MENGGANGGU ALIRAN TRAFIK
Laluan alternative ke Taman Yong Seng
GAMBAR-
GAMBAR KERJA
PEMASANGAN
PAIP YANG
MELIBATKAN DI
BAHU JALAN