Professional Documents
Culture Documents
Case Studies Electric Power
Case Studies Electric Power
Contents
• Investment Climate
Country Bond Rating: S&P BBB-
Billions of USD in Foreign Investment
• Physical
Economics of Natural Gas Combined Cycle
Natural Gas Availability
Transmission System
• Rates/Regulatory
Industrial Customer Rates
• Separation into Multiple Companies
Unbundled System
Cost-based Energy Bids
Capacity Price Up-lifts
• Generators whose plants are scheduled for dispatched one day in advance or
who are actually dispatched receive a pre-determined capacity payment for hours
falling outside low periods.
No long-term Contracts
Plant Operation - 1999
Electricity Sales
73 MW to Refinery
55 MW to Grid
• A few year before the California crisis virtually nobody questioned the
benefits of de-regulation. Utility companies, competitive suppliers,
environmental groups, consumer representatives and government
regulators all groups supported de-regulation. Legislation that de-
regulated the industry was often passed by unanimous margins and
competition was replacing government oversight all over the world.
That has all changed with the California crisis and the financial demise
of Enron.
• According to the Wall Street Journal:
“It was one of the great fantasies of American Business: a deregulated
market that would send cheaper and more reliable supplies of electricity
coursing into homers and offices across the nation…Now with the power
industry hovering uneasily between regulation and deregulation, it faces the
prospect of a market that combines the worst features of both: a return to
government restrictions, mixed with volatility and price spikes as companies
struggle to meet the nation’s energy needs.”
Understanding pricing and valuation in competitive markets is not less of
an issue because of questions related to the efficacy of regulation. Indeed,
the problems with Enron and California demonstrate the immense
complexity of risk assessment, pricing and valuation issues in the industry.
• Rolling Blackouts
• PG&E Bankruptcy
• Edison Electric Near Bankruptcy
• State Budgetary Surplus Eliminated
• Governor Arnold
80
• .
A-rated
1000
BBB-rated
800 BB-rated 60
Sub-Prime 28.0 31.6
26.1
600
40 18.5 19.3
400
20
-
• . 200
1/3/2007
2/3/2007
3/3/2007
4/3/2007
5/3/2007
6/3/2007
7/3/2007
8/3/2007
9/3/2007
1/3/2008
2/3/2008
3/3/2008
4/3/2008
5/3/2008
6/3/2008
10/3/2006
11/3/2006
12/3/2006
10/3/2007
11/3/2007
12/3/2007
• Results of Market
Market Power
Bankruptcy of Distributors
Price Volatility
Little Merchant Construction
• Regulatory/Market Structure Problems
Stranded Investment Charges
No Retail Price Signals
No Bilateral Contracts
No Capacity Pricing
• Characteristics of Physical System
Transmission Bottlenecks
Reliance on Imports
Hydro Volatility
Natural Gas Market Power
28,000
26,000
24,000
22,000 Therm al
20,000
18,000
16,000
14,000
12,000
10,000
8,000 QF
6,000
4,000
2,000 Nuclear
0
1
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
Time [Hours]
50,000
Load+
40,000 Op. Res.
Load
30,000
20,000
10,000
0
APR MAY JUN JUL AUG SEP
10
8
¢/kwh
6
4.2
3.6
4 2.9 3.1 2.7 2.9 3.1 3.1 3.3
2.6 2.5
2
0
00
01
02
03
04
05
06
07
08
09
10
20
20
20
20
20
20
20
20
20
20
20
California Energy Commission “Market Clearing Prices… 2000-2010”, Feb. 2000, p. 6
Cautious Development Scenario, nominal dollars
11.5
30
12
27.1 26.8 10.7
25 10
Total Cost $/Billion
15 6
10 7.4 3.1
4 2.9
5
2
0
1999 2000 2001 0
1998 1999 2000 2001
250
200
Average Load Peak Load
Incremental Cost ($/MW)
150
100
50
0
85200 95200 105200 115200 125200 135200 145200 155200 165200
Load (MW)
• Hydro System
• Reliant on Imports of NWPP Hydro Generation 2000 Relative
Energy to 1999 -- May-June
• Difficult to Build
NGCC 2000
• Hydro was 23% 0
below previous Week Week Week Week Week Week Week Week Week
levels -2000 1 2 3 4 5 6 7 8 9
aMW -4000
-6000
-8000
• But a detailed examination of recently released internal memos by Enron Corp. lawyers,
transcripts of trader conversations gathered by investigators, and scores of interviews
with market participants and regulators yields a comprehensive look at how the U.S.
energy industry cashed in on and contributed to California's energy crisis. Among the
findings:
Energy companies seized on loopholes and local shortages to charge prices hundreds of times
higher than normal.
Suppliers withheld power from the state's primary market, and sometimes idled power plants to
induce shortages and boost prices.
Gas companies manipulated supplies and prices, driving up the cost of a main ingredient of
electricity.
Enron played a much bigger role than previously believed in California's energy market. Its trading
strategies overwhelmed regulators and drove up prices.
• Almost from the start, participants on all sides probed for weaknesses. One way the ISO seeks to ensure reliability
is to pay plant operators to keep generators on standby to meet last-minute surges in demand. In the market's first
weeks, payments for this service, set by auction, were typically less than $10 a megawatt-hour. (A megawatt-hour
is roughly the amount of power needed to supply 1,000 homes for an hour.)
• Then on July 13, 1998 -- 3-1/2 months after deregulation started -- a unit of Houston-based Dynegy Corp. offered
to supply standby power at $9,999 a megawatt-hour. Dynegy was exploiting the fact that the market had been set
up with few rules on what suppliers could charge. The ISO had to accept the bid because it expected high power
demand and there were few other offers of standby power. Thus, Dynegy and three other suppliers wound up
splitting $8 million for keeping plants on call for five hours, according to state and federal records. Dynegy declines
to comment on the incident.
• No company devised more ways to take advantage of the system than Enron, which remade itself in the
1990s from a pipeline company to an energy trader. The Houston energy giant bought Portland General
Electric Co., a regional utility located in Portland, Ore., in 1997, and set up a trading desk later run by
Tim Belden. A former researcher at a federal energy lab who typically rode his bike to work, Mr. Belden
spent 15-hour days combing through regulatory filings trying to crack the code of California's new
market, according to former employees in the office.
• He wasn't afraid to take chances. A former co-worker recalls Mr. Belden losing $100,000 of Enron's
money on an "experiment" to see how prices would react if Enron simultaneously exported power from
California at several locations.
• Mr. Belden quickly focused on wringing profits from the state's aging and inadequate transmission
network. Enron bid aggressively at the ISO's 1999 auction for transmission rights on heavily used lines,
which gave Enron priority for moving electricity on these lines, and a share of the ISO's fees for
allocating capacity.
• Enron devised multiple strategies for overloading transmission lines and reaping payments for relieving
the congestion it had created, according to the memo by Enron's lawyers and interviews with former
traders. The congestion fees could be so lucrative -- as much as $600 a megawatt-hour -- that Enron
regularly transferred power across the state and sold it at a loss, with the fees more than making up the
difference, according to a former Enron trader.
• By the summer of 2000, Enron traders had a portfolio of such tactics, with colorful nicknames such as
"Death Star" and "Red Congo." Both involved scheduling power to flow in one direction on the ISO
system, and in the opposite direction on another system outside the ISO's control, such as a
transmission line operated by California cities. In that way, Enron could be paid for "relieving" congestion
on the ISO system without actually putting power on or taking it off the grid. To execute these strategies,
Enron created complicated chains of transactions using out-of-state partners.
MW
8,000
6,000
4,000
2,000
• suppliers began offering less power to the daily auctions at the Power Exchange and at
higher prices. On the afternoon of June 28, for example, prices climbed to $750 a
megawatt-hour, four to five times as high as on similarly hot days in the summer of 1999.
Power Exchange investigators later concluded that all of the power-plant operators --
Dynegy, Williams, Duke Energy Corp., Reliant Energy Inc. and Mirant Corp. -- as well as
marketers such as Enron had at times withheld electricity from its daily auctions. The
suppliers may have tried to sell the power to the ISO or out-of-state buyers, hoping to
fetch a higher price. Or, they may have idled the plants, hoping to induce a scarcity that
would drive prices even higher.
• Contributing to the increase in electricity prices during the crisis were even more dramatic
increases in the natural gas price than had occurred earlier in 2000. In December, the
California natural gas price jumped to about $50 per million Btu, a factor of 10 higher than
it had been.
• Although this price peak lasted for only two weeks, the spot natural gas prices in
California remained above $10 per million BTU until June of 2001 (see Figure 25, based
on data from Enerfax.com). These high prices did not result from limitations in the
availability of natural gas at the wellhead or at market centers, as shown by the prices of
natural gas at Henry Hub, Louisiana, the major market center. Rather the price spike
resulted directly from the large demand for natural gas to fuel electric generators during
the winter when the demand for natural gas naturally peaks, coupled by limitations in the
pipeline capacity to transport natural gas within the State and the absence of natural gas
held in storage from previous months.
• The sharp increase in natural gas prices, coming just when investor-owned utilities were
not paying generators for electricity they sold, provided strong incentives for generators
either to stop producing electricity or to bid very high prices to sell the electricity they did
generate. Thus, these natural gas prices probably contributed substantially to the
wholesale electricity price increases during the crisis, particularly to the December
electricity price spikes.
180.00
160.00
140.00
120.00
($/MWh)
100.00
80.00
60.00
40.00
20.00
0.00
Apr-98 Jul-98 Nov-98 Feb-99 May-99 Aug-99 Dec-99 Mar-00 Jun-00 Oct-00 Jan-01
Month
Cal NE PJM
0.9
0.8
0.7
0.6
(p-MC)/p
0.5
0.4
0.3
0.2
0.1
0
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
Residual Demand/ Capacity
• The premise that “The Market will Provide” is too simple for a critical
infrastructure such as the electric energy system - can have both over &
under supply
• Some one has to have the responsibility for ensuring adequate generation
supply
• Construction of power plants is very capital intensive so builders want some
guarantees of revenue for several years to lower their risks
• The time delay from when it is obvious new plants are needed to when they
can be sited, built and on-line is 2 to 4 years.
• Single Price Auction structure breaks down when there is a scarcity of
supply
• Bi-lateral deals and forward contracting for blocks of energy is essential to
reduce risks and guarantee adequate energy supplies
• The Philippines entered the IPP market early, with a 1988 presidential
decree authorizing private investment in the generation sector. Major
investment in IPPs occurred in response to a 1991-93 electricity crisis.
• The Electric Power Crisis Act passed in 1993 authorized negotiating IPP
contracts on a fast track basis.
• In terms of addressing the power shortage, this law was a success—
several thousand megawatts of generating capacity was installed in the
country in the first 18 months.
• Most of the generating capacity built during this time was based on
combustion turbines or diesel systems—the only generation plants that
could be brought to operation within a year—which are characterized by
low initial capital costs, but high operating costs.
• The fast track authority under this law expired in April 1994.
• The country had its first Build-Operate-Transfer contract in 1987, with Hopewell
Holdings Ltd. of Hong Kong tycoon Gordon Wu as the proponent. Hopewell
constructed two 100-megawatt gas turbine plants in Luzon.
• The venture was deemed so successful that the government was encouraged
to enter into more BOT power contracts and even enact the BOT law (Republic
Act 7718) that would allow Napocor to tap the private sector more effectively.
Past and present government officials agree that the early Hopewell contracts
provided the model for all future power deals with the private sector.
• But Napocor soon found itself with more IPP contracts, and more power, than it
could handle, and what was once thought of as a brilliant solution to the
country's power needs have now become problems themselves. At the time it
was accumulating IPP contracts, the government had also let the private
Manila Electric Co. (Meralco) to build its own power plants, which later
exacerbated an energy oversupply.
May 18,Subic
2001 Group 113
Electricity Case Studies March 25, 2024113
Case 1: Enron Subic
• Summary
Financial Close: 1993 (First Round)
Commercial Operation: 1994
PPA Agreement: 15 Years; Guarantee by Government
Bonds: $105 Million
Maturity 15 Years
Repayment Level
Interest Rate 9.5% (3.68% spread to Treasury)
Minimum DSCR 1.37
Completion Guarantee/Liquidated Damages
Capacity Charge $21.6/kW/Month
15-year Turnkey
Enron Power Enron
Phils. Op’g Co.
Performance BOT Construction Corp.
Undertaking Concession Contract
O&M Enron Subic
Supply Agreement Power Corp
Napocor Fuel Free
113MW
Ground Subic
Lease
Buyout Power Enron Power
Rights
Corp. Philippines Corp
• Capacity Charge
• O&M Charge Insurances
• Energy Charge
PPA US$105 million, 15-year Notes
Electricity Case Studies March 25, 2024116
113 MW Diesel Generator Power Station
Subic Bay, Philippines
Sources of Funds:
Notes $ 105 M
Subordinated Note 7
Contr. Of Shareholders 28
Working Capital 2
TOTAL $ 142
Uses of Funds:
Turnkey Contractor $ 112 M
Bonus to Turnkey Contractor 7
Development and other related costs and Fees 14
Pre operating, Start-up and Commissioning Costs 3
IDC 4
Working Capital 2
TOTAL $ 142
• Financial Covenants
Debt Service Cover Ratio 1.10
Debt Service Reserve Account: 6mos debt service deposit
Debt Payment Account: monthly retention
Restrictions on
additional indebtedness other than
financing acquisition of Additional Facilities @ max 75%
financing scheduled payments to EPOC
subordinated debt < US$ 25mln
working capital loan
shareholder payments / repayments
payments of sub-debt
investments other than permitted investments
In Conclusion:
Attractive Return
Manageable Risks
• Payments of Principal & Interest are fully guaranteed by Enron Corporation until the
Facility Completion Date.
• Completion Guarantee
• All principal and interest payments on the Notes are guaranteed fully by Enron
Corporation, and severally, in proportion to their ownership interest in the
Company, by House of Investment (HI) and Rizal Commercial Banking
Corporation (RCBC).
• Security:
Mortgage on all real property and security interest on all substantial tangible
property.
Security interest in Company’s cash and investment.
Collateral assignment of:
BOT Agreement
Turnkey Construction contract
Performance Undertaking
Other project contracts
• Capacity 440 MW
• Cost USD 808.9 Million
• Transmission 230 kV 31 km
• PPA
25 Years
covered costs as long as as-contracted performance met
• Offtaker: Meralco (First PPA with Private Utility)
• BOO without government guarantee
Uses of Funds
Generation Facility 419,560,000 419,560,000 953.55 52%
Transmission Line 23,306,000 23,306,000 52.97 3%
VAT, Insurance, Escalation 21,878,000 21,878,000 49.72 3%
Total EPCM Costs 464,744,000 464,744,000 1,056.24 57%
Contingent Commitments
Contribution Ownership
• Intergen 72.5%
71.875%
Bechtel and Shell Joint Venture
• Ogden Enterprises 27.5%
26.125%
• Local Developer
2.000%
Project Location Capacity Total Cost Cost per kW Operational Date Major Owners
• By 1998, peak capacity was 11,988 MW while peak demand was 6,421 MW.
Demand projections in the early- and mid-1990s forecast demand growth
ranging from 9.5-12% per year.
• A 1994 report by the World Bank already warned implicitly against the risk of
over-commitment through the uncoordinated signing of PPAs, which
essentially passed demand risk to the consumer through take-or-pay
provisions.
• The costs of IPPs were often high because the new capacity was not
consistent with the least-cost expansion path and the private sector required
high rates of return.
• The focus on production rather than efficient distribution put the public sector in
the position of retaining that activity in which it was least effective and
restricting the private sector from performing the customer focused activities
(distribution and supply) where it had real expertise. At the same time, it
isolated the private sector from the market through a combination of regulated
pricing and guarantees against commercial risks.
Estimated
Growth – 9.2%
Actual
Growth – 3%
50.00% 50.00
40.00% 40.00
Infllation Rate
30.00% 30.00 Exchange Rate
20.00% 20.00
10.00% 10.00
0.00% 0.00
61 63 65 67 69 71 73 75 77 79 81 83 85 87 89 91 93 95 97 99 01 03 05 07 09
19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 20 20 20 20 20
• Exceptionally high power rates were cited as one reason why Intel
Philippines, one of the country's biggest foreign investors and largest
employers, with over 5,000 workers, plans to close down its Philippine
operations and divert the company's investments to lower-cost
Vietnam and Malaysia. A recent government survey showed that the
high cost of electricity is one of the main reasons why foreign
investors are reluctant to locate their businesses in the Philippines.
• According to the Heads of ASEAN Power Utilities/Authorities, a
consultative group attached to the 10-member Association of
Southeast Asian Nations, the average cost of electricity in the
Philippines last year was 17.5 US cents per kilowatt-hour (kWh). That
is more than three times the 5.38 per kWh cost in Vietnam, and is
markedly higher then the 6.77 per kWh cost in Indonesia, 7.67 per
kWh in Malaysia and 8.50 per kWh in Thailand. Even high-cost
Singapore recorded cheaper power rates at 13.07 per kWh.
30.00 28.80
C
e
n 25.00
t
s
20.00
p
e 15.31
r 15.00
12.30 11.80 11.61
k 10.44 10.15
10.00 9.28
W
h 7.42 7.11 6.95 6.18
i 5.00
n
U 0.00
Philippines
Singapore
HK - Kolowoon
Iceland
South Africa
Australia
Finland
HK - Island
Perú
USA
Malaysia
Canada
S
D
• .
Jan 53
Jan 55
Jan 57
Jan 59
Jan 61
Jan 63
Jan 65
Jan 67
Jan 69
Jan 71
Jan 73
Jan 75
Jan 77
Jan 79
Jan 81
Jan 83
Jan 85
Jan 87
Jan 89
Jan 91
Jan 93
Jan 95
Jan 97
Jan 99
Jan 01
Jan 03
Jan 05
Jan 07
in project finance where a 20%-
30% equity buffer gives a bank
Index of Housing Growth and Population Growth
comfort that equity investment 1.6
0.8
92 Jan
99 Jan
06 Jan
93 Oct
00 Oct
07 Oct
97 Apr
04 Apr
94 May
01 May
08 May
91 Jun
94 Dec
98 Jun
01 Dec
05 Jun
95 Jul
96 Feb
02 Jul
03 Feb
93 Mar
00 Mar
07 Mar
90 Nov
96 Sep
97 Nov
03 Sep
04 Nov
92 Aug
99 Aug
06 Aug
Electricity Case Studies March 25, 2024169
Ignoring Economics and Long-Run Marginal Cost when
Evaluating Prices
• Loans were granted on the presumption
AES Drax thatand housing
UK Merchants
prices would follow historic trends and
continue to increase. The most fundamental of economic principles dictate that prices
Declines in prices
eventually movewere not predicted
to long-run marginalin cost,
merchant electricity
or the marketsaafter
cost of building new increases
home. Asin a supply.
Losses wereeconomics
corollary, estimated suggests
to be $100 billion.
that pricesIncan
themove
U.K. changes in the
to short-run marketwhen
marginal structure and
surplus
increased
capacitysupply
exists.pushed prices
The graph to marginal
of median cost.prices in the U.S. shown below illustrates how
housing
the basic economic principles were ignored.
• .
• The deregulation process started in 1990, after the UK Electricity Act signed in
1988.
• Central Electricity Generating Board was, until 1990, responsible for the
generation and transmission of electricity. After market opening, generation is
carried over by
National Power, and PowerGen (fossil fuel generators)
British Energy and Magnox (nuclear)
Eastern group, and a good number of independent generators recently created.
Scottish generation companies and Electricite de France are in charge of imports
into England and Wales.
• Total generation capacity is 70GwH.
• Low voltage transmission is done through 12 companies (Regional Electricity
Companies, or RECs). High voltage transmission is done by the National Grid
Company.
• Any approved generator can generate into the grid and contract through the
transmission companies delivery to retailers.
• “…in the US, private companies that own merchant plants have lost of more than $100
billion in market capitalization.”
• Banks are “now highly reluctant to take merchant risk of any kind… and they are skeptical
about long-term purchase or tolling contracts that in any way are considered to be out of
the money.”
New Merchant Capacity in Database
• “Merchants will have to redesign their business 35,000.00
models. Those players that have 80-90
percent of their capital in the form of debt won't survive. The ratings agencies have said 2 9 ,513
30,000.00
that such debt-to-capital ratios must be in the 50-50 range to earn investment grade
status so that the cost of borrowing is reasonable.”
25,000.00 2 3 ,9 4 2
MW
15,000.00 13 ,9 2 4
9 ,78 3
10,000.00
4 ,8 6 9 5,13 6
5,000.00 3 ,58 0
2 ,0 75 2 ,4 9 4
1,3 3 5 1,2 2 9
-
1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003
£/MWh
(99/00)
40 Transport Uplift
Uplift
35
Capacity Payment
30 SMP
25
20
15
10
0
1990/1 1992/3 1994/5 1996/7 1998/9 2000/1
SM P, marginal cost
for manipulation that generators with 80
60
significant market power enjoy under 40
0
• The ability to exercise market power 0 10000 20000 30000 40000
D emand, capacity
50000 60000 70000
is demonstrated on the graph below M arginal cost (Frontier estimates) Sample Pool price outcomes
• The problems for banks exposed the sector boil down to one thing:
overcapacity. There is calculated to be roughly 22% overcapacity and it is
therefore not surprising that prices have slumped so spectacularly. Prices are
now around 17 to 18 per MWH, down 40% from levels prior to NETA’s
introduction.
• The atomization of the generation sector was a function of new entrants and
forced sales and pricing power was lost before NETA was introduced.
40000 40000
40000 40000
30000 30000
30000 30000
20000 20000
20000 20000
10000 10000
0
• . 0
10000 10000
National
AES
Scottish &
British Energy
Scottish Power
Other
Bnfl Magnox
Powergen
Mission
EDF
TXU
NRG
0 0
Edison
Southern
Power
National
Scottish Power
Nuclear
Scottish Hydro
PowerG en
NG C
EDF
Electric
Power
Electric
D ebt Pct Equity IRR Debt Pct Equity IRR Debt Pct Equity IRR
0.0% 11.6% 0.0% 10.3% 0.0% 9.0%
19.2% 12.6% 19.2% 11.2% 19.2% 9.7%
37.3% 14.1% 37.3% 12.4% 37.3% 10.6%
54.5% 16.4% 54.5% 14.3% 54.5% 12.1%
62.8% 18.1% 62.8% 15.7% 62.8% 13.1%
70.8% 20.7% 70.8% 17.8% 70.8% 14.7%
78.7% 24.9% 78.7% 21.2% 78.7% 17.2%
86.4% 33.5% 86.4% 28.1% 86.4% 22.3%
93.9% 69.6% 93.9% 56.8% 93.9% 42.6%
22 22.0
21.0
20 20.0
19.0 Although NETA
18
17.0 has impacted
16 15.5 electricity prices,
14
NETA has not
12
generally been
10
1990 1991 1992 1993 1994 1995 1996 1997 1999 2000 2001 2002 2003
considered to be
the principal
underlying cause
behind the
decline in UK
power prices; this
is more likely due
to the over-
capacity in the
UK generation
market,
increased
competition and
fragmentation of
the market.
AES Drax Annual
Report
• Paul Hanrahan, said, “For the past 12 months, AES has worked
diligently to navigate the interests of Drax stakeholders through all of
thisturmoil, beginning with the onset of TXU Europe’s demise, through
their bankruptcy and beyond. We have operated the plant extremely
well,we have committed top management resources, we have
preserved the claims of Drax in the TXU Europe administrative
proceeding and we have led the process of restructuring and
reorganizing the very complex and oft-times conflicting set of creditor
concerns. We have done all of this in good faith towards preserving as
much value for all Drax stakeholders, and most importantly, we have
done this without any compensation to AES. In fact, we have offered
to put more money in to Drax as part of the restructuring. AES looked
at its participation as it would any new investment, applying rigorous
investment criteria to its commitment.At this time, we feel it
appropriate that the creditors of Drax exhibit a commitment to AES
0
5
01-91
04-91
07-91
10-91
01-92
04-92
07-92
10-92
01-93
04-93
07-93
10-93
01-94
04-94
10-95
01-96
04-96
07-96
10-96
01-97
04-97
07-97
10-97
01-98
04-98
07-98
10-98
01-99
04-99
07-99
10-99
01-00
04-00
07-00
10-00
01-01
AES:
04-01
07-01
10-01
01-02
04-02
07-02
10-02
01-03
04-03
07-03
10-03
01-04
04-04
07-04
10-04
01-05
04-05
Beta 1.81 Stock Volatiltiy 46.2% S&P Volatility 11.4%
07-05
10-05
01-06
04-06
07-06
10-06
01-07
04-07
07-07
10-07
01-08
04-08
07-08
March 25, 2024200
AES
S&P Index
Drax Case
Dabhol Loan
Power Agreement
Corp
• Project Included
Largest Independent Power
Producer – 695 MW + 1,320 MW or
2,015 MW. 22.4% of Capacity of
Maharashtra
LNG Re-gasification Plant
LNG Tanker to access supplies in
Qatar
85% Debt and 15% Equity
Equity
Enron 65%
Bechtel
GE
• First phase
Second phase
• 695 MW
1,320 MW
plant
capacity
• Cost of
LNG re-gasification
$920 M plant, storage, and harbor facilities to be built.
• Construction to
began
begin
1995,
afterproject
phase to
1 completed
come on-line in 1997
• Cost of
$1323/kW
$1.88 B
• Comparable
Cost per $1,466/kW
costs $650/kw
• May-June, 1992: India invites Enron Corp to explore the • June-Oct 2000: Maharashtra government allies
possibility of building a large power plant in Maharashtra. demand scrapping the project because of the cost
of the power it produces.
• June 20, 1992: Initial memorandum of understanding
signed between Enron and Maharashtra government for • Oct, 2000: MSEB defaults on its October payment
a plant with capacity of 2000-2,400 MW. The to DPC.
Maharashtra State Electricity Board is expected to pick
up a 10 per cent stake. • Dec, 2000: Maharashtra state announces plan to
review the project, stating that the tariff is too
• Jan 2, 1993: The Foreign Investment Promotion Board high.
clears proposal for a 1,920 MW plant, expandable to
2,550 MW. • Feb, 2001: The Credit Rating Information Services
of India Ltd cuts ratings on bonds issued by
• Dec 8, 1993: The power purchase agreement signed Maharashtra government due to defaults on
between Dabhol Power Company and MSEB for a 2,015 payments owed to Dabhol. Enron invokes the
MW project to be implemented in two phases. Union government guarantee.
• March-June, 1995: Following state elections, a new • April, 2001: Enron issues a notice of arbitration to
Maharashtra government, headed by the Shiv Sena, the Indian government to collect on the December
scraps the project, alleging corruption and high costs. bill of Rs 1.02 billion.
• Nov 1995: Project re-negotiated with a final capacity of • April, 2001: Enron invokes the political force
2,184 MW. MSEB's stake is upped to 30 per cent -- 15 majeure clause in its contract with MSEB, stating
per cent in the first phase, and a further 15 per cent upon that unfavorable political conditions have prevented
completion of the project. it from fulfilling contractual obligations.
• May, 1996: India extends counter-guarantee to the • April 23, 2001: DPC and its lenders meet in
project, under which the federal government promises to London to discuss the payments issue. Enron
cover any defaults by the state utility. seeks lenders' permission to issue a notice of
termination.
• May, 1999: Phase one of the project with a capacity of
740 MW begins operating. • April 25 2001: The board of Dabhol Power
Company authorizes management to terminate the
contract any time it chooses.
• PPA Contracts can transfer all demand and fuel cost risk. The
Dabhol PPA contract is illustrated below
• Endless disputes over prices and terms of the deal turned the venture
into a symbol of what can go wrong in large-scale development
projects when cultures collide.
• In April 1993, a World Bank analysis questioned the project's
economic viability, citing the high cost of importing and using liquefied
natural gas relative to other domestic sources of fuels. Because of
those findings, the World Bank refused to provide funds for the
project.
• "Price is becoming a sticky issue," the Financial Times reported.
"Indian officials see the price as very high compared to domestic gas
and imported and indigenous alternative fuels."
• Protesters took to the streets to support demands for changes in the
plant's design and -- more broadly -- to oppose the Indian
government’s economic liberalization policies. Social activists,
lawyers, villagers and farmers banded together in groups opposed to
the Enron project.
• The devaluation meant that Dabhol's energy prices would soar to
between two and five times the average price in the area.
Capacity of 388.5 MW
15 year PPA for 370 MW
• Natural gas fired (1x1) GE 9FA CCGT
1.64 mmscmd of gas allocated
on firm basis
• Project cost US$ 238 mn, project cost is
the lowest for any gas based plant
VPGL -
Vemagiri constructed in India
• Estimated first year tariff of Rs. 1.94/
kWh (approx 4 cents)
Fixed Charge - Rs. 1.01/kWh
Variable Charge - Rs. 0.93/kWh
• All the energy transactions in the Regulated Market are carried out through
auctions that are conducted by Aneel in accordance with MME rules. EPE
aggregates and reviews the future electricity consumption estimated by the
distribution companies. Assuming its estimated future power consumption,
EPE provides a list of power plants that can eventually balance supply and
demand in the regulated market. Aneel then auctions that list, having in mind
its obligation to keep tariffs at the lowest possible prices.
• In auctions for new capacity, investors will bid on a concession to provide a
certain amount of “assured energy” to the regulated market. Assured energy is
a number determined by government planners that reflects expected
hydrological conditions. For a hydro plant, assured energy is the amount of
energy that can be produced by the plant in the worst hydrological conditions,
given the integrated management of reservoirs. For a thermal plant, assured
energy is the amount of electricity expected to be dispatched, given
hydrological forecasts. For both types of plants, assured energy is the energy
that can be sold under long term contract—whether to the free or regulated
market
up…’” 2,000,000
1,000,000
0
1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008
• My contacts
Ed Bodmer
Phone: +001-630-886-2754
E-mail: edbodmer@aol.com
• Other Sources
Financial Library – project finance case studies including
Eurotunnel and Dabhol
Financial Library – Monte Carlo simulation analysis