AMI Rollout Strategy Deployment

AMI Deployment Strategy for 34 million meters over 15 years


40000
PRE-
COM PHASE 1 PHASE 2 PHASE 3 PHASE 4
35000 MERCI
AL
Number of AMI Meters

30000
(x thousand)

25000

20000

15000

10000

5000

Year to 0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Accumulation 104 150 1.365 3.426 5.486 7.547 9.790 12.034 14.277 16.520 19.236 22.210 25.185 28.159 31.133 34.108
Target per year 104 150 1.215 2.061 2.061 2.061 2.243 2.243 2.243 2.243 2.716 2.974 2.974 2.974 2.974 2.974

Target per year Accumulation

The deployment strategy in the PLN study is recommended to be divided into 4 phases, namely phase 1 (slow year 1-2), phase 2
(stabilization of year 3-5), phase 3 (Ramp up year 6-9), and phase 4 (mass 10-15th year)
AMI Infrastructure Background
An integrated multi-tiered (5.8/2.4 GHz network), multi-technology (RF Mesh & Cellular) end-to-end solution
 Spectrum regulations:
 83MHz available in 2.4GHz
 150MHz available in 5.8GHz

 RF Mesh NAN/FAN is meter


agnostic – ability to integrate
with multiple meter OEMs
 RF Mesh WAN is device
agnostic – ability to interface
with any Ethernet (TCP/IP)
device
 UnitySuite HES is cellular
technology agnostic – ability
to support RF Mesh and
Cellular-Based AMI networks