DC4 & 5 Cooling Management & DC 5 1st Floor Budgetory Working

You might also like

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 14

Ctrls Mumbai DC

World’s 1st LEED platinum Certified and


Asia’s Largest Rated 4 Data center

DC 5 Cooling Management
by DC4 Chillers
Presentation Date – 21st February 2022

Secure Scalable Carrier Neutral 99.995% Uptime

Report Prepared By- Ramdas Satpute


DC 4 Cooling Management

DC 4 Cooling System are explained as below

1. Chiller – 1800 TR – 2 Nos (Water cooled) working


450 TR – 4 Nos (Air cooled) Standby
2. Water cooled chiller Pumps :-
Condensor Pumps - 5400 GPM – 2 Nos
Primary Pumps - 3420 GPM – 2 Nos
Secondary Pumps - 3420 GPM – 2 Nos
Air Cooled Chillers – Pumps:-
AC assisting pump - 3420 GPM – 1 Nos
AC Primary Pumps - 855 GPM - 4 Nos

3. Thermal Storage Tank – 55 KL - 2 Nos

4. Cooling Tower – 1800 TR -2 Nos


DC 4 Cooling Management

DC 4 Cooling load calculation

Sr No Floor Design Cooling (TR)

1 Lower ground floor 6


2 Ground floor 127
3 1st floor - Server Hall 1 335
4 2nd floor 1646
5 3rd floor 1645

Total Required 3759 TR


DC 5 Cooling Management – (July 2022)
Option 1 - 1800 TR x 2 Water cooled Chiller (1W+1S) , AC Chiller for DC 1

Sr No Floor Design Cooling (TR ) on 100 % Working Load % Req TR

DC 4
1 LG 6 100% 6

2 Gr 127 50% 63.5


3 1st floor - Server Hall 1 380 30% 114
4 2nd floor 1650 30% 495
5 3rd floor 1650 30% 495

Total Required 3813 1173.5


Installed 1800
Balance 626.5

DC5 - 1st floor 1646 38% 625.48


DC 5 Cooling Management – (July 2022)
Option 2 - 1800 TR x 2 Water cooled working + 1800 Air cooled standby

Sr No Floor Design Cooling (TR ) on 100 % Working Load % Req TR

DC 4
1 LG 6 100% 6
2 Gr 127 80% 101.6

3 1st floor - Server Hall 1 380 80% 304


4 2nd floor 1650 80% 1320
5 3rd floor 1650 80% 1320

Total Required 3813 3051.6


Installed 3600
Balance 548.4

DC5 - 1st floor 1650 33% 544.5


DC 5 Cooling Management – (July 2022)

Option 3 - 1800 TR x 3 Water cooled Chiller (2W+1S) -


Third Chiller with all Equipment PO to be released by 1st week of March

Design Cooling (TR ) on 100


Sr No Floor % Working Load % Req TR

DC 4
1 LG 6 100% 6
2 Gr 127 80% 101.6
1st floor - Server Hall
3 1 380 80% 304
4 2nd floor 1650 80% 1320
5 3rd floor 1650 80% 1320

Total Required 3813 3051.6


Installed 3600
Balance 548.4

DC5 - 1st floor 1650 33% 544.5


DC 5 Cooling Management – (July 2022)

Option 4 - 1800 TR x 3 Water cooled Chiller (2W+1S) -


Third Chiller with all Equipment PO to be released by 1st week of March

Sr No Floor Design Cooling (TR ) on 100 % Working Load % Req TR

DC 4
1 LG 6 100% 6
2 Gr 127 70% 88.9
3 1st floor - Server Hall 1 380 70% 266
4 2nd floor 1650 70% 1155
5 3rd floor 1650 70% 1155

Total Required 3813 2670.9


Installed 3600
Balance 929.1

DC5 - 1st floor 1650 56% 924


DC 5 Cooling Management – (July 2022)

Option 5 - 1800 TR x 3 Water cooled Chiller (2W+1S) -


Third Chiller with all Equipment PO to be released by 1st week of March
Design Cooling (TR ) on 100
Sr No Floor % Working Load % Req TR

DC 4
1 LG 6 100% 6
2 Gr 127 60% 76.2
1st floor - Server Hall
3 1 380 60% 228
4 2nd floor 1650 60% 990
5 3rd floor 1650 60% 990

Total Required 3813 2290.2


Installed 3600
Balance 1309.8

DC5 - 1st floor 1650 79% 1303.5


DC 5 Cooling Management – (July 2022)

Option 6 - 1800 TR x 3 Water cooled Chiller (3W) - Air cooled Standby – Excluding 4 th floor.
Third Chiller with all Equipment PO to be released by 1st week of March
Design Cooling (TR ) on
Sr No Floor 100 % Working Load % Req TR

DC 4
1 LG 6 100% 6
2 Gr 127 100% 127
3 1st floor - Server Hall 1 380 100% 380
4 2nd floor 1650 100% 1650
5 3rd floor 1650 100% 1650

Total Required 3813 3813


Installed 5400
Balance 1587

DC5 - 1st floor 1650 96% 1584


DC 5 Budgetary Proposal

1. High Side Works - 23.42 Cr

Sr No Description Qty Unit Rate Amount


High Side

1 DG 4 Nos 15,743,720 69,272,368

2 Transformer with accessories 4 Nos 7,000,000 30,800,000

3 HT Panel & Incoming cable, bus duct 1 Lot 24,000,000 26,400,000

4 LT Panel 1 Lot 49,000,000 53,900,000

5 PDU 1 Lot 8,679,355 9,547,291

6 PDU 1 Lot 8,654,389 9,519,828

7 PAHU 1 Lot 26,315,000 28,946,500

8 UPS 1 Lot 2,885,979 3,174,577

9 Battery 1 Lot 2,376,000 2,613,600

Amount 234,174,163
DC 5 Budgetary Proposal
2. Low Side Works - 7.69 Cr
Sr No Description Qty Unit Rate Amount

1 DG Lifiting shifting 4 Nos 540,000 2,376,000

2 Electrical low side 1 Lot 5,497,050 6,046,755

3 HSD Low side 1 Lot 381,127 419,240

4 Civil Interior 1 Lot 17,674,102 19,441,512

5 HVAC Low Side 1 Lot 9,499,505 10,449,456

6 Raised floor 1 Lot 8,875,899 9,763,489

7 Grills & Gromets 1 Lot 1,558,550 1,714,405

8 IBMS 1 Lot 4,491,000 4,940,100

9 Pre Action 1 Lot 4,500,000 4,950,000

10 CAC 1 Lot 2,554,340 2,809,774

11 DG Exhaust 1 Lot 635,700 699,270

12 DG Exhaust 1 Lot 3,612,000 3,973,200

13 PAHU Low side 1 Lot 2,685,000 2,953,500

14 Dummy Panel 1 Lot 634,786 698,265

15 Lighting arrestor 1 Lot 182,800 201,080

16 UPS Low side 1 Lot 638,682 702,550

17 Signage 1 Lot 360,695 396,765

18 DC Acoustic 1 Lot 3,601,989 3,962,188

19 TST Low side 1 Lot 360,000 396,000

Amount 76,893,548
DC 5 Budgetary Proposal
3. Additional Chiller option & DC 4-DC5 Connectivity – 3.83 Cr
Sr No Description Qty Unit Rate Amount

1 Chiller 1 Nos 16,409,670 18,050,637

2 Cooling tower 1 Nos 2,310,000 2,541,000

3 TST 1 Nos 1,335,000 1,468,500

4 Primary Pump 1 Nos 483,875 532,263

5 Secondary pump 1 Nos 691,050 760,155

6 Condensor pump 1 Nos 825,080 907,588

7 Chiller Low side 1 Lot 2,253,779 2,479,157

8 Chiller & Pump piping 1 Lot 4,860,100 5,346,110

Amount 32,085,409

DC4 to DC 5 Connectivity

1 DC4 to DC 5 HVAC Low side 1 Lot 5,686,490 6,255,139


DC 5 Budgetary Proposal

Sr No Description Qty Unit Rate Amount

1 High Side Works 1 Lot 234,174,163

2 Low Side Works 1 Lot 76,893,548

2 Additional Chiller works 1 Lot 32,085,409

DC4 to DC 5 HVAC
4 Connectivity 1 Lot 5,686,490 6,255,139

5 Total 349,408,259
THANKING YOU

Prepared by –Ramdas Satpute