GIRDERS • 45.7 M • RDSO Drawing: B-17181series • Weight of the Girder: 138.346 MT • Overall length 47850 mm • Effective length - C / C bearing 47240 mm • Height of girder at center- 8117.5 mm • Truss centre - 5400 mm 45.7m Welded Open Web Girder SELECTION OF ASSEMBLY SITE
• The assembly of Girder has to be done on a
firm and levelled platform. • Hence, concrete platforms are most suitable for this. ERECTION FACILITIES
• Road mobile cranes are utilized for erection.
• Gantries and hoists can also be used. ASSEMBLY
• The bed for assembly can be made with
beams and packing plates. • The bed should be checked and levelled with water level. Contd…
• Bottom chord 2 nos. are laid from one end
with bottom gussets and the Cross Girders assembled in between bottom chords, also Stringers in between Bottom Chords. Contd..
• Joints shall normally be made by
• filling not less than 50% of the holes with • service bolts and barrel drifts in the ratio of • four to one. The service bolts are to be fully • tightened up as soon as the joint is • assembled. Contd.. • Similarly the successive bottom chords are laid with cross girders and stringers. • Bottom laterals are assembled in position. • The cross and diagonal measurements are checked and all the black bolts tightened. • Camber jacks are inserted over the platform below every bottom panel joints in such a way that all the joints are in run out condition except the central jack. Contd..
• Levels are taken at the top of bottom chord at
every nodal point. • All the vertical member are erected at the nodal points and diagonals are fixed subsequently with temporary gussets (gusset holes are drilled for the camber profile). • Bottom chords are checked to ensure to be in the same level. Contd..
• Camber is provided to all panel joints of the
bottom chords as per the camber diagram by lowering the jacks at the ends, keeping the central jack without disturbing. • Camber readings are checked and adjusted for the correctness. Contd.. • Top chord members are erected from centre to outwards so that they are elastically strained. • Temporary gussets are replaced with permanent gussets before drifting. • Drifts are driven with hammer. Trueness of holes in the adjacent group of holes is checked. • Care should be taken so that the holes are not damaged (elongated or teared). Contd.. • Chain pulley block is used to for assembling the members to keep the joints in position. • End rakers are erected in the last, the upper end is first connected and drifted, then the connection is made at the lower end. • Sway bracings, top lateral bracings and portal bracings are erected subsequently. • All the joints are tightened and drifted. Contd..
• Jacks are lowered duly keeping the end
supports in position. • Dead load camber is checked by levelling instrument, also with water level. The measurements are recorded. PROBLEMS ENCOUNTERED AND REMEDIAL MEASURES • Care is to be taken to drive the drifts and close supervision is required to avoid elongation or tearing of drilled holes in the gussets and members. PROBLEMS ENCOUNTERED AND REMEDIAL MEASURES • Measuring with Levelling instruments may be a failure due to the poor accuracy in reading on longer lengths. • Measuring of camber with a piano wire of 0.5 mm dia. With 10 kg weights at both ends will be a failure due to sag in longer lengths.
Solution: Water level with a diameter of 6 mm
and length 10 metre longer than the girder can be used to check the level of the girder. PROBLEMS ENCOUNTERED AND REMEDIAL MEASURES • Slight deformation of the chord members. • Gap between the chord ends at the junctions.
• Solutions: Jacks can be used to lift the floor
system. Chain pulley blocks can be used to erect the members in position.