Professional Documents
Culture Documents
3 - Smed1
3 - Smed1
Reduction
Tools and Techniques SMED
Module Objectives
2
Introduction
Set B
Tool /
Fixture / Material
Set A
Tool /
Fixture / Material
3
Introduction
4
Purpose
Set B
Tool / Support Pull System Implementation:
Fixture / Material Quicker setup/changeovers facilitate
Set A
Tool / small lot production, small lot
Fixture / Material production facilitates pull systems
5
Definition
6
Why Quick Changeover/SMED?
7
Why Quick Changeover/SMED?
8
Why Quick Changeover / SMED?
The goal is to maximize Run Time by minimizing Set
Up and other lead time
9
Why Quick Changeover/SMED?
A B C A B C
30 minute changeover
12 times/day Same run time, more changeovers
30 minute changeover
OR 6 times/day
Total available daily runtime = 21 hours
10
Components of Set-Up Process
50%
30%
15% 5%
11
Components of Set-Up Process
Fixture exchange represents a low percentage of the total set-up time
Most set-up time is actually spent in chasing tools, components, fixture / part
adjustments and trial runs
A significant - 30% of the set-up time can be immediately eliminated
at almost no cost
Actions such as:
Cleaning the work area,
Organizing the storage racks
Storing common tools close to the machines at no cost can
reduce the set-up significantly
WASTE ELIMINATION!!
12
Changeover - An everyday example
On your own?
By a tire workshop?
13
Before Quick Changeover
14
After Quick Changeover
16
Step 1 - Identify Internal & External Steps
How to:
Record the process (use a Simple Time Recording Sheet,
Standard Work Combination Sheet or SOE)
Form a team
Interview operators Some steps may be identified
as unnecessary and eliminated
Videotape from the procedure if they are
Stopwatch analysis obsolete or no longer
practical for the current
operation.
17
Step 2 - Convert Internal Steps to External
Objectives:
• To reduce internal setup time. The more setup steps, decisions,
adjustments, etc. that can be done on external time, the better.
Internal Setup
Activity #1 After Improvement Activity #2
18
Step 2 - Convert Internal Steps to External
How to:
Through the elements recorded in Step 1 (Identify Internal & External
Steps)
Identify all internal steps, eliminate all unnecessary steps
Analyze all essential internal steps to determine if opportunity exists to
convert internal steps to external steps:
– Can adjustment blocks be used in lieu of making machine adjustments?
– Can dies be preheated independent of the equipment operation?
– Can procedures/techniques be developed to insure that all tools, equipment,
and materials are staged in the immediate work area before the machine is
idled?
– Is all post setup work (tooling service, cleaning, data tracking, etc.) being
done after the equipment resumes operation?
19
Step 2 Convert Internal Steps to External
- Example (Elimination of Adjustments)
20
Step 2 Convert Internal Steps to External
- Example
Other examples:
•Standardize common temperature profile for curing
•Etc.
21
Step 2 Convert Internal Steps to External
Summary
Convert internal Steps to external steps.
• Review Current Process with the team.
• Brainstorm ideas to move internal tasks to external
tasks.
• Assign owners to improvement ideas identified and
identify dates for completion.
• Review the progress on a regular basis.
22
Step 3 - Reduce Internal Setup Time
Objectives:
• To reduce internal setup time. The internal setup steps
and decisions need to be simple and precise while
adjustments got to be reduced and eliminated.
Primary Focus
External Setup External Setup
Internal Setup
Activity #1 Activity #2
Internal
Setup
Activity #1 Activity #2
23
Step 3 - Reduce Internal Setup Time
How to:
Analyze the remaining internal setup tasks to
reduce/eliminate adjustments:
Can adjustment blocks or preset gauges be used?
Can tooling presets be used?
Is equipment, fixtures, The assumption that
adjustment is unavoidable
and tooling clean and
leads to unnecessary lengthy
serviceable? internal setup times and
Can locating/centering requires a high level of skill
techniques be employed? and experience on the part of
the operator.
24
Step 3 - Reduce Internal Setup Time
How to:
Accomplish setup tasks Every effort should be made to
in parallel where possible (Can use personnel that will not
impact the operating time of
additional resources be utilized other equipment or those that
to support the may have reduced workloads
setup/changeover?) due to the changeover that is in
process.
25
Step 3 - Reduce Internal Setup Time
Summary
• Eliminate adjustments.
26
Step 4 - Reduce External Setup Time
Objectives:
Since the maximum external setup time must be less
than the time to run a production lot, reducing
external setup time typically is less critical than
reducing internal setup time.
27
Step 4 - Reduce External Setup Time
How to:
Store fixtures, dies, tools, raw materials and documentation
as close as possible to the point of use:
– Arranged in sequence of use
– Shadow boards used
– Addressed and labeled
– Color coded
Use setup kits and/or carts
– May include fasteners, jig, fixtures, tools, etc.
– May be integrated as part of the equipment
– May also be utilized for raw materials
Improve Material Handling
– Provide adequate access for fork trucks / carts
– Provide visual means (Andon) of notifying material handlers of
impending changeover
– Eliminate/minimize the need for mechanized material movement
28
Step 4 - Reduce External Setup Time
Store fixtures, dies, tools, raw materials and documentation
close to the point of use:
– Arranged in sequence of use
– Shadow boards used
– Addressed and labeled
– Color coded
29
Step 4 - Reduce External Setup Time
30
Step 4 - Reduce External Setup Time
Summary
31
Step 5 - Repeat Steps
How to:
Standardize/Document: Each step of the setup/changeover must
be standardized and documented through the use of written
procedures and/or checklists. This is not only necessary to sustain the
improvements, but is necessary for future improvement activities.
32
Step 5 - Repeat Steps
Why?
Example: Review Changeover Times
Average Time per Changeover
70
60
50
40
Minutes
30
20
GOAL = 10 MIN. 10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Day of Month
Date 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Changeovers 2 3 1 2 4 2 3 1 2 4 2 3 1 2 4 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2
Time 98 195 55 106 200 130 180 58 110 200 102 150 45 140 260 180 58 114 186 60 98 135 44 84 117 45 80 105 31 60
Ave Time 49 65 55 53 50 65 60 58 55 50 51 50 45 70 65 60 58 57 62 60 49 45 44 42 39 45 40 35 31 30
33
Step 5 - Repeat Steps
34
Additional Options to Consider
35