Professional Documents
Culture Documents
1 Project Appraisal
1 Project Appraisal
12
Project Appraisal (A Preliminary Analysis)
In order to evaluate a project we may face two different scenarios
i) Perfect Certainty
ii) Uncertainty
• In case of perfect certainty single parameter criteria is used (based
on maximization of return).
• In case of uncertainty usual single parameter criteria does not work.
• Under uncertainty we use simple two parameter criteria and refined
two parameter criteria.
• In simple two parameter criteria in addition to Monitory reward we
have to consider uncertainty associated with such a reward.
13
Project Appraisal (A Preliminary Analysis) Cont.
Simple two Parameter Criteria
Expected Value of X = Expected Value of Y E(X) = E(Y) &
Standard Deviation of X < Standard Deviation of Y <
Then X is preferred over Y
Expected Value of X > Expected Value of Y E(X) > E(Y) &
Standard Deviation of X = Standard Deviation of Y =
Then X is preferred over Y
Expected Value of X > Expected Value of Y E(X) > E(Y) &
Standard Deviation of X < Standard Deviation of Y <
Then X is preferred over Y
Expected Value of X > Expected Value of Y E(X) > E(Y) &
Standard Deviation of X > Standard Deviation of Y >
14
Simple two parameter criteria failed
Project Appraisal (A Preliminary Analysis) Cont.
Simple two Parameter Criteria
Expected Value of X = Expected Value of Y E(X) = E(Y) &
Standard Deviation of X > Standard Deviation of Y >
Then Y is preferred over X
Expected Value of X < Expected Value of Y E(X) < E(Y) &
Standard Deviation of X = Standard Deviation of Y =
Then Y is preferred over X
Expected Value of X < Expected Value of Y E(X) < E(Y) &
Standard Deviation of X > Standard Deviation of Y >
Then Y is preferred over X
Expected Value of X < Expected Value of Y E(X) < E(Y) &
Standard Deviation of X < Standard Deviation of Y <
Simple two parameter criteria failed 15
Project Appraisal (A Preliminary Analysis) Cont.
Refined two Parameter Criteria
Expected Value of X = Expected Value of Y E(X) = E(Y) &
Coefficient of Variation of X > Coefficient of Variation of Y >
Then Y is preferred over X
Expected Value of X < Expected Value of Y E(X) < E(Y) &
Coefficient of Variation of X = Coefficient of Variation of Y =
Then Y is preferred over X
Expected Value of X < Expected Value of Y E(X) < E(Y) &
Coefficient of Variation of X > Coefficient of Variation of Y >
Then Y is preferred over X
Expected Value of X < Expected Value of Y E(X) < E(Y) &
Coefficient of Variation of X < Coefficient of Variation of Y <
Even refined two parameter criteria failed
16
Project Appraisal (A Preliminary Analysis) Cont.
Refined two Parameter Criteria
Expected Value of X = Expected Value of Y E(X) = E(Y) &
Coefficient of Variation of X < Coefficient of Variation of Y <
Then X is preferred over Y
Expected Value of X > Expected Value of Y E(X) > E(Y) &
Coefficient of Variation of X = Coefficient of Variation of Y =
Then X is preferred over Y
Expected Value of X > Expected Value of Y E(X) > E(Y) &
Coefficient of Variation of X < Coefficient of Variation of Y <
Then X is preferred over Y
Expected Value of X > Expected Value of Y E(X) > E(Y) &
Coefficient of Variation of X > Coefficient of Variation of Y >
Even Refined two parameter criteria failed 17
Projects
Situations Prob. Cement Co. A Pharma B Cosmetics C Covid Vex. D Tourist E
Covid 0.5 - (5,000,000.00) 10,000,000.00 50,000,000.00 10,000,000.00
Recovery 0.5 10,000,000.00 15,000,000.00 30,000,000.00 - 50,000,000.00
Expected Return 5000000 5000000 20000000 25000000 30000000
Variance 25000000000000 100000000000000 100000000000000 625000000000000 400000000000000
Standard Deviation 5000000 10000000 10000000 25000000 20000000
CV 1.000 2.000 0.500 1.000 0.667
18
Comparison of Five Different Projects
1. Cement Co. A VS Pharma B STPC Cement Co. A is
preferred
2. Cement Co. A VS Cosmetics C STPC We can’t decide!
3. Cement Co. A VS Covid Vex D STPC We can’t decide!
4. Cement Co. A VS Tourist E STPC We can’t decide!
In such a case we have to use refined two parameter criteria.
2. Cement Co. A VS Cosmetics C RTPC Cosmetics C is
preferred
3. Cement Co. A VS Covid Vex D RTPC Covid Vex D is
preferred
4. Cement Co. A VS Tourist E RTPC Tourist E is preferred
More Interesting Comparisons:
5. Cosmetics C VS Covid Vex D Both STPC and RTPC failed
6. Cosmetics C VS Tourist E Both STPC and RTPC failed 19
(in such a case even a layman can decide). Therefore we have to
discuss some other undiscounted measures
Utility Based Appraisal
In case if we are not in a position to decide on the
basis of single parameter criteria or simple two
parameter criteria or even refined two parameter
criteria then what should we do?
• In such a case we have a number of alternatives
the most simplest one is based on the utility.
• Therefore, now we will discuss Utility based
approach.
• A Sure/guaranteed return/reward/money will
worth more than an uncertain/risky
return/reward/money.
20
• What is a utility function?
Cosmetics C Tourist E
Utility 3,162.28 3,162.28
Utility 5,477.23 7,071.07
E(U) 4,319.75 5,116.67
Cosmetics C Covid. Vex. D
Utility 3,162.28 7,071.07
Utility 5,477.23 0
E(U) 4,319.75 3,535.53
21
Criticism of Utility Based Approach
Project A Project B
Prob. Project B
0.89 1,000,000
0.10 5,000,000
22
Criticism of Utility Based Approach Cont.
Project A Project B
0.89 - 0.9 -
23
Criticism of Utility Based Approach Cont.
Project A Project B
0.01 - 0.02 -
Project A Project B
0.71 - 0.72 -
25
Stochastic Dominance
• There are many types of the utility functions and the utility
functions are subjective (depend upon something i.e. utility
functions are non standardize).
• Expected utility takes into account discrete probability
distribution whereas, stochastic dominance consider whole
probability distribution.
• FDSD More is preferred over less U1 du/dx>0
• SDSD Individuals are risk averse U2 du/dx>0 &
d(du/dx)/dx<0
• TDSD Is based on positive skewness U3 du/dx>0
d(du/dx)/dx<0 & d{d(du/dx)/dx}/dx>0
• Although the concept of stochastic dominance is based on the
derivative of the utility function but we will not calculate utility
here. 26
Decision Rule:
If all the values of F(A)-F(B) are positive/non-negative then B A
If all the values of F(A)-F(B) are negative/non-positive then A B
27
Ans: As all the values of F(A)-F(B) are positive therefore, B A
Stochastic Dominance Cont.
SDSD: Consider the following projects
Project A Project B Prob.
0 -5,000 0.5
10,000 15,000 0.5
E(Return) 5,000 5,000
SD σ 5,000 10,000
Decision Rule:
If all the values of ∫[F(A)-F(B)] are positive/non-negative then B A
If all the values of ∫[F(A)-F(B)] are negative/non-positive then A B
Ans: As all the values of ∫[(A)-F(B)] are non-positive therefore, A 28
B
Stochastic Dominance Cont.
TDSD: Consider the following projects
Project
A Prob. Project B Prob.
0 0.25 100,000 0.75
200,000 0.75 300,000 0.25
E(Return) 150,000 150,000
X F(A) F(B) F(A)-F(B) ∫[F(A)-F(B)} ∫∫[F(A)-F(B)}
0 0.25 0.0 0.25 0.25 0.25
100,000 0.25 0.75 -0.50 -0.25 0
200,000 1.0 0.75 0.25 0 0
300,000 1.0 1.0 0 0 0
Decision Rule:
If all the values of ∫∫[F(A)-F(B)] are positive/non-negative and E(B) ≥
E(A) then B A
If all the values of ∫∫[F(A)-F(B)] are negative/non-positive and E(A) ≥
E(B) then A B 29
Ans: As all the values of ∫∫[(A)-F(B)] are non-negative and E(B) ≥
E(A) therefore, B A
Stochastic Dominance Cont.
Project A Prob. Project B Prob.
0 0.25 100,000 0.75
200,000 0.50 300,000 0.25
400,000 0.25
E(Return) 200,000 150,000
X F(A) F(B) F(A)-F(B) ∫[F(A)-F(B)} ∫∫[F(A)-F(B)}
0 0.25 0.0 0.25 0.25 0.25
100,000 0.25 0.75 -0.50 -0.25 0
200,000 0.75 0.75 0 -0.25 -0.25
300,000 0.75 1.0 -0.25 -0.5 -0.75
400,000 1.0 1.0 0 -0.5 -1.25
Decision Rule:
If all the values of ∫∫[F(A)-F(B)] are positive/non-negative and E(B) ≥
E(A) then B A
If all the values of ∫∫[F(A)-F(B)] are negative/non-positive and E(A) ≥ 30
E(B) then A B
Ans: The values of ∫∫[(A)-F(B)] are both positive and negative therefore, we
Are the Undiscounted Measures Enough for Project Appraisal?
400,000 0.25
SD σ 141421.356 86602.54
31
CV 0.70710678 0.57735
Benefit Cost Ratio / Profitability Index
Formula:
BCR= (future cash inflows /Initial investment).
• The Profitability Index/Benefit Cost Ratio defines how much project
will earn per dollar of investment.
• The value of an anticipated future cash flows divided by initial
outflow gives the profitability index (PI) or BCR of the project. It is
also one of the easy investment appraisal techniques.
• Suppose, the value of anticipated future cash flow is $120,000 &
the initial outflow is $100,000. Then the profitability index/BCR is
1.2. i.e. $120,000 / $100,000.
• This means each invested dollar is generating a revenue of 1.2
dollars.
• If the profitability index is more than 1, the project should be
accepted & if it is less than 1 it should be rejected.
32
2. Discounted Measures
I. Discounted Payback Period:
“The period of time required to recover the discounted initial investment on
the basis of discounted future cash flows”.
• It only differs from the payback period in the sense that rather than
nominal future cash flows we use discounted values of future cash flows.
For Example,
XYZ Org. is considering buying a machine costing $100,000.
There are two options Project A and Project B.
Project A will generate revenue of $ 50,000, $ 50,000 & $ 20,000 in year 1,
year 2 & year 3 respectively.
Project B will generate revenue of $ 30,000, $ 40,000 & $ 60,000 in year 1,
year 2 & year 3 respectively.
Rate of Interest is 10%
Payback period is 2.88 years & 2.88 years for Project A & Project B
respectively.
DPBP says Both the projects are equally good but layman can decide even 33
in this case.
Discounted Payback Period Cont.
Project A’s DPBP = 2.88 years Project B’s DPBP = 2.88 years
Cash flows 50,000 50,000 20,000 Cash flows 30,000 40,000 60,000
Discounted
CF 45454.55 41322.31 15026.3 Discounted CF 27272.73 33057.85 45078.89
34
II. Net Present Value (NPV)
NPV is based on the Concept of PV.
Formula:
NPV= PV of future cash inflows – Initial investment or
NPV ={ + + …….. } – Initial Investment
• It is the most common method of investment appraisal.
• Net present value is the sum of discounted future cash
inflow & outflow related to the project.
• Generally, the weighted average cost of capital (WACC) is the
discount factor for future cash-flows in the net present value
method.
• For simplicity we will use interest rate as a discount factor.
• NPV sums up the discounted net cash inflows from the
investment & deducts the initial investment to give the ‘net 35
present value’.
• The Project may be accepted if the NPV is positive.
Net Present Value(NPV) Cont.
For Example,
• XYZ Org. is starting the project at a cost of $100,000.
• The project will generate cash-flow of $40,000, $50,000
& $50,000 in year 1, year 2 & year 3 respectively. The
company’s WACC/i is 10%. Find out NPV.
• Formula of NPV = [ $40,000/( 1+0.1)1] +
[ $50,000 / (1+0.1)2 ] +[ $50,000/ (1+0.1)3 ] – 100,000
• Net present value = $36,363.63 + $41,322.31 +
$37,565.74 – $100,000
• = $115,251.68 – $100,000
• The net present value of the project is $ 15,251.68
• The NPV is positive therefore project may be accepted. 36
III. Internal Rate of Return(IRR)
“The rate of discount/cost of capital at which NPV of future
cash flows becomes zero”. Or
“An internal rate of return is the discounting rate, which
brings discounted future cash flow at par with the
discounted initial investment”.
• It is such a discount rate at which the project will neither
make a loss nor make a profit.
• It is obtained by the trial & error/ hit and trial method.
• We can also state that IRR is the rate at which the NPV of
the project will be zero. i.e. Present value of cash inflow
– Present value of cash outflow = zero
NPV = 0 = PV of future cash flows – Initial investment 37
or
NPV = 0 = { + + …….. } – Initial Investment
Internal Rate of Return(IRR) Cont.
Steps
1. Choose a Particular i for discounting.
2. Choose a Higher i if the NPV on the basis of previous step is
positive and vice versa.
3. Round the answer in downward direction
A -100,000 120,000 0
B -100,000 0 144,000
40
Difference in Time Horizon of the Projects Cont.
• On the basis of IRR both the projects gives the same return.
• IRR=20%
• Are you sure both the projects are equally good?
• If yes then Why?
• If No the why not?
PBP says project A is better.
DPBP gives contradictory results at interest rate of less than 20% (A
is better), 20% (A is better) and more than 20% (none is
preferable).
NPV also gives contradictory results at interest rate of less than
20%, 20% and more than 20%.
If i=0 NPV of Project A is 20K & NPV of Project B is 44K.
In order to compare such projects where the time horizon is
different we have to calculate either NPV or IRR.
41
If i=10 Project A is worse and Project B is better.
If i=20 we have already discussed that both are equally good.
Problems Associated with main
Discounted Measures.
1. IRR assumes reinvestment at IRR which sometime
may not be a feasible idea.
• Suppose over the years there is change in interest
rate so how we can use a single i/discount rate over
the years.
• In such a situation we can use NPV because NPV
does not assume a single discount rate.
Conclusion:
Do not use IRR criteria if there is a change in
discount rate.
42
Problems Associated with main Discounted
Measures Cont.
2. Sometimes / occasionally Internal rate of Return gives
Multiple IRRs commonly known as MIRR.
-++++ (1 IRR)
- + - - + + (2 IRRs)
IRR depends on number of sign change.
3. Both IRR and NPV can’t distinguish between lending and
borrowing.
Year 0 Year 1
Projects Cost Return
A -100,000 120,000
B 100,000 -120,000 43
Problems Associated with main Discounted
Measures Cont.
4. Consider the case of different time horizon.
44
Problems Associated with main Discounted
Measures Cont.
5. Case of different initial Investment.
45
Discounted Measures Cont.
Case of Mutually Exclusive Projects:
Example of ME projects:
• A construction company may have to face two ME projects A
technically advanced apartment or an office block.
• A organization may face two mutually exclusive energy options
oil vs natural gas or petrol vs diesel that is newly designed
production process may operate on oil or natural gas.
• Similarly, management have to decide energy or environment
efficient cars are designed to use either petrol or diesel.
• Undertaking a project right now or to wait for favorable
situation (after few years).
• A cheaper short term project or an expensive long term
project.
• Expensive project for higher profits or a cheaper project for 46
50
Discounted Measures Cont.
Year 1 Year 2 Year 3 Year 4 Year 5
NPV at
Cost/Inv. SV Return Return Return Return Return 10%