LOR JOINERY

FIRE RATED DOOR


25/10/2022
What is a Fire Rated Door?

A fire door is the door component of a fire rated assembly.

They are required in many areas of buildings to protect occupants, block the
spread of flames and smoke, and minimize the overall property damage that can
occur during a fire. Fire rated doors are built and tested to withstand the heat,
smoke, and flames of a roaring fire while also providing a means of escape.
However, the fire door alone does not offer fire protection – it is the fire door
assembly that when used together offers fire protection. If one component of the
opening is not listed for use as part of the fire door assembly, the entire assembly
is void of its fire-resistance rating.
Fire Door Ratings and Types

Fire doors are rated in terms of minutes/hours; the fire rating defines how
long the assembly was tested to withstand a fire. Some common fire door
ratings are 30, 60, 90, and 120 (minutes). The fire rating required depends on
the adopted building codes and the location of the door opening.

Fire rated doors and frames are available in many types including wood,
hollow metal, and specialty products such as FRP (Fiber Reinforced
Polymer). Some door types, such as wood doors, also
require intumescent seals either built into the door edge or supplied as a
separate item that attaches to the fire door frame.
Standards of Fire Doors
• BS 476 Part 22
• BS EN 1634-1
• UL 10C

Third Party Certification Body


• CCS – Conformity Certification Services
• BM TRADA Ventures
• IFC Certification Limited

Certification Authorities
• Civil Defense
Critical Steps of Fire Doors

1. Design
2. Submission
3. Procurement
4. Production
5. Installation
6. Quality
Design
• Test report or global assessment number must be mentioned in all fire rated door set's
drawing or in the door schedule.
• Technical lead to check supporting documents for fire door set
– Test Report
– CoC
– DCD Certificate (inform MR is DCD certificate is not available)
• Door configuration and frame detail must match with tested door set.
• Intumescent strip and kit detail must match with tested door set.
• Door schedule and drawing to be shared with MR to verify.
• Correct door schedule is very important to get equipment supply certificate.
How to Design?
• For Project Based in UAE
Testing is mandatory
 Check if we have already tested the door set
 Do we have CoC for tested door set
 Design the door set based on test report
 Propose ironmongeries based on tested door set
 Submit the drawing for approval

• For Project Based Outside UAE


Depends on Specification and the Local Authorities Requirements
 Door schedule and summary should be shared with core suppliers
 Core supplier will suggest what design to be followed
 Propose ironmongeries based on GAs
 Door set can be designed based on GAs
 Submit the drawing for approval
FR Door Schedule
– FR Doors
Assessment/Test Report Standard Testing Facility Certification Body Leaf Dimention (mm) FD Rating Configuration Core

170518496 BS 476 Part 22 Material Lab Conformity Certification Services 2600x1111+1099x65 90 LSADL FireBan

171218557 BS 476 Part 22 Material Lab Conformity Certification Services 2547x1085+1086x55 60 USADL FireBan

200202750 BS EN 1634-1 Material Lab Conformity Certification Services 2300x1100x65 90 LSASL FireBan

200926817 BS 476 Part 22 Material Lab Conformity Certification Services 2329x778+912x65 90 LSADL FireBan

201128829 UL 10C Material Lab Conformity Certification Services 2790x1114x45 60 LSASL DANSNBAN

210206852 UL 10C Material Lab Conformity Certification Services 2368x1119x45 60 LSASL DANSNBAN

210207853 UL 10C Material Lab Conformity Certification Services 2368x1119x50 90 LSASL DANSNBAN

QH058 (Door Set B) BS 476 Part 22 Thomas Bell-Wright bmtrada 2168x1116x56 60 LSASL Strebord 54

QH058 (Door Set A) BS 476 Part 22 Thomas Bell-Wright bmtrada 2134x1084x65 60 LSASL Ramkor 64

170412479 Specimen 2 BS 476 Part 22 Material Lab bmtrada 2400x1050x55 60 LSASL FireBan

170412479 Specimen 1 BS 476 Part 22 Material Lab bmtrada 2800x1100x55 60 LSASL FireBan

170411474 Specimen 1 BS 476 Part 22 Material Lab bmtrada 2600x1150x65 90 LSASL FireBan

170411474 Specimen 2 BS 476 Part 22 Material Lab bmtrada 2600x1150x65 120 LSASL FireBan

180114562 BS 476 Part 22 Material Lab bmtrada 2942x1155+1170x65 60 LSADL FireBan

QH150 (Door Set B) BS 476 Part 22 Thomas Bell-Wright bmtrada 2132x1084x65 90 LSASL Ramkor 64

QH150 (Door Set A) BS 476 Part 22 Thomas Bell-Wright bmtrada 2350x1020x59 90 LSASL WSCP Core

190909700 Specimen 2 BS EN 1634-1 Material Lab Conformity Certification Services 2249x1014x65 90 LSASL FireBan

191222725 Specimen 1 BS EN 1634-1 Material Lab Conformity Certification Services 2300x1100x55 60 LSASL FireBan

PB042-2 BS 476 Part 22 Thomas Bell-Wright bmtrada 2101x900x64 60 LSASL Ramkor 64

2206231005 UL 10C Material Lab Conformity Certification Services 2800x1050x45 60 LSASL DANSNBAN

2210061023 UL 10C Material Lab Conformity Certification Services 2500x1050x1035x45 60 LSADL DANSNBAN

190727685 BS EN 1634-1 Material Lab Conformity Certification Services 2487x986+986x65 60 UDADL FireBan
Submission
• For Project Based in UAE
Testing is mandatory
 Materials as per tested door set
 Test report (only if client or consultant ask for it)
 CoC – Certificate of Compliance
 DCD certificate
 Certificate of registration

• For Project Based Outside UAE


Depends on Specification and the Local Authorities Requirements
 Materials as per GA
 Certificate of registration

• All the submission must go through fire door MR.


Procurement
• All the materials to be procured as per submission and approval.
• All requisition of fire rated door must be signed by fire door MR.
• Any subcontract regarding fire door must go through MR.
Production

• Drawing must go through transmittal and must be signed by fire door MR.
• Fire rated door to be produced as per approved drawing without any tolerance.
• Fire rated door must be inspected and record in check sheet/s by QAQC and
production team after every steps of production.
• Intumescent strip must be installed before CNC work.
Installation
• Fire rated doors must be installed as per approved shop drawing without any tolerance.
• Intumescent strip and kit should be installed as per approved shop drawing (if
intumescent strip not installed in production).
• There should not be any gap between ironmongery and intumescent strip.
• Joint in intumescent strip is only allowed towards the bottom of door set.
• Fire rated door must be inspected and record in check sheet/s by site team after every step
of installation.
• Site team to request for fire labels with installation check sheet/s.
• Fire door MR must visit the site for inspection of fire rated door based on check sheet
provided before releasing fire labels.
• Site team to install the fire label below the top hinge on door leaf.
• Site team to maintain record of fire labels and shared with MR.
Questions?