AHP - PMPL - Monthly Report For Mar-24 Highlights
AHP - PMPL - Monthly Report For Mar-24 Highlights
2 ESP DERM – 8,9,10 jamming clear & maintenance work. VIKAS 16.03.2024 DONE
1
UNIT#2
2
EQUIPMENT: ESP DERM – 8,9,10 jamming clear & maintenance work.
.
Activities carried out
Maintenance/jamming clear of Vertical and horizontal Tumbling hammer DERM
system of ESP.
Removing of rack and pinion gears of Vertical shaft and jamming clear work..
Removing of rack and pinion gears of Horizontal shaft and jamming clear work.
Trial run of the DERM System 8,9,10.
3
EQUIPMENT: ESP Ash conveying system.
.
Activities carried out
Dome jamming clear and Bellow fit-up work
Intake valves jamming clear.
Power cylinder guards fixing work.
NRV Cleaning rubber replacement work.
Poppet valve service and box-up.
Conveying lines and bend box.