Professional Documents
Culture Documents
Work Plan
Work Plan
River Tista
Tunnel No 13 (L – 2565 m)
Tunnel No 12 (L – 1406 m)
TUNNEL
No. 13
Construction of two Tunnel, T-12(Between KM 37+097 to KM 38+531 approx.) and T-13 (between
KM 38+775 to KM 41+403 approx.) on Sevok (West Bengal) to Rangpo (Sikkim) New Single line
BG Railway Line Tunnel Project.
Agency M/s CS-DHORAJIA (JV)
All approach roads are completed up to the portal, Portal development work are
Progress
completed, Mining of T12 & T13 is completed, Lining of T12 is Completed
Third Stage Concrete of T12, Lining of T13, Third Stage Concrete of T13, Grauting, Sub-
Balance Work
station Niche excavation and support system work.
Status of tunnel no T-12 and T-13
Total Progress as on 01.02.2024
Tunnel No 12 (L-1406 m)
37+097 M
38+531 M
T12 P1
T12 P-2
T12 Mining Completed= 1406 M
Tunnel No 13 (L-2560 m)
41+403 M
T13 Mining Completed= 2560 M
38+775 M
T13 P2
T13 P1