CS- Dhorajia JV

TUNNEL No. 12 & 13


Work Program for Balance Work as
of 01-02-2024.
Alignment Of Tunnel T12 & T13

Rangpo Chu River

River Tista

Tunnel No 13 (L – 2565 m)

Tunnel No 12 (L – 1406 m)
TUNNEL
No. 13
Construction of two Tunnel, T-12(Between KM 37+097 to KM 38+531 approx.) and T-13 (between
KM 38+775 to KM 41+403 approx.) on Sevok (West Bengal) to Rangpo (Sikkim) New Single line
BG Railway Line Tunnel Project.
Agency M/s CS-DHORAJIA (JV)

Date of LOA 05.10.2020

Completion Period 24 Months

Date of completion 04.10.2022

Time Extension 31-10-2024

Contract value Rs. 373.25 Cr.

Revised Contract value Rs. 458.75 Cr.

Financial Progress (Rs.) Rs. 387.37 Cr. approx till date.

All approach roads are completed up to the portal, Portal development work are
Progress
completed, Mining of T12 & T13 is completed, Lining of T12 is Completed

Third Stage Concrete of T12, Lining of T13, Third Stage Concrete of T13, Grauting, Sub-
Balance Work
station Niche excavation and support system work.
Status of tunnel no T-12 and T-13
Total Progress as on 01.02.2024
Tunnel No 12 (L-1406 m)

37+097 M

38+531 M
T12 P1

T12 P-2
T12 Mining Completed= 1406 M

T12 Lining Completed= 1406 M

Tunnel No 13 (L-2560 m)

41+403 M
T13 Mining Completed= 2560 M
38+775 M

T13 P2
T13 P1

Ring Closing and Kerb work is in progress