Professional Documents
Culture Documents
s12-s17 Mba Acm CCM Red Flag Clauses Project MGMT 2022 23
s12-s17 Mba Acm CCM Red Flag Clauses Project MGMT 2022 23
Kumthekar NICMAR 1
CONTRACT and CLAIMS
MANAGEMENT
Dr. Madhav
Kumthekar
Associate Professor,
NICMAR, Pune
RED FLAG CLAUSES
• Time period of contracts are mentioned but to avoid disputes, the starting date is to be
clearly identified.
• CPWD - Cl. 5: The date of commencement of work shall be the date of start as specified in schedule
‘F’ or the first date of handing over of the site, which ever is later, ……
Commencement of Work
• FIDIC (1999) - Cl. 8.1 : Engineer gives the Contractor not less than 7 days’ notice of
Commencement Date; Commencement Date shall be within 42 days of Letter of Acceptance.
• FIDIC (2017) - Cl. 8.1 : not less than 14 days’ notice of the Commencement Date;
Commencement Date shall be within 42 days of Letter of Acceptance.
Notice of Commencement
04/18/2024 Dr. Madhav B. Kumthekar NICMAR 14
Time of Completion
• The contractor failed to complete the work in 125 days excluding Sundays and holidays
because of bad weather and acts of the owner.
• The owner, thereupon, deducted from the contract price compensation at $25 per day.
• The contractor raised a claim to recover the sum so withheld.
Contractor's contention
Reason
• The owner and his architect, at the time the contract was entered into, must have
known the meaning of the term "working days" when used in a construction contract.
Where time is of the essence of the contract and is extended, the extended
date is also of the essence of the contract.
Un-Liquidated Damages :
• Not pre-fixed or determined.
• Requires the victim to present evidence for establishing the amount
• The word liquidated merely signifies that the precise amount of the daily
damages to the owner
• It is established by agreement
• The liquidated damages is deducted by the owner from the sum that is due
to the contractor at the time of final payment.
• When the project delay is the fault of both the owner and the contractor, the
owner’s recovery of liquidated damages is generally precluded/ prohibited.
Delay of the project caused by the owner is another cause of time extension.
• Delays on construction projects and the claims originating from such delays are an
integral part of the modern construction process.
• Construction projects have a tendency to suffer from delays and such delays carry
potential losses for all parties:
– for the employer (client, owner) through loss of use,
– for the contractor and subcontractors through their prolonged presence on site.
• Non - Excusable Delays are those delays that occur due to events which are within the
Contractor’s control.
• Eg. Slow progress of contractor/subcontractor, breakdown of equipment
• Non - Compensable Delays are those delays where the Contractor is not entitled to
extension of time and /or additional compensation though it is an excusable delay.
• Eg. Beyond owner control events like unforeseeable weather, strikes
• Non Excusable
Time extension + LD relief + Compensation
• The contractor shall execute the work in the most substantial and
workmanlike manner conforming exactly, fully, and faithfully to the designs,
drawings, and specifications.
• The condition may further provide that the contractor should appoint a
qualified engineer to get the work done according to the contract.
Contractor’s
Materials
Implied
Obligations for
Workmanship
Quality of
Work
Design
• If the plans supplied by the employer are insufficient to produce the result
desired, the contractor is not responsible if he carries out the plans.
non-hazardous materials
The Engineer
Examination, shall give a Notice
inspection, to the Contractor
If Defective or
measurement or not according
describing the item
testing of any Plant, to the contract of Plant, Materials,
Materials, design or
Contractor’s design workmanship that
or workmanship has been found to be
defective.
04/18/2024 Dr. Madhav B. Kumthekar NICMAR 127
Provisions in Standard Form Contracts
FIDIC - Clause 7.5 [Defects and Rejection] 2017
Proposal Submission by Contractor for necessary remedial work.
Proposal review by Engineer and Notice for rectification (if any)
Re-Submission of Revised Proposal by Contractor.
Notice Issue by Engineer within 14 days after receiving the
Contractor’s proposal (or revised proposal).
Failure by the Engineer shall be considered as a Notice of
No-objection.
04/18/2024 Dr. Madhav B. Kumthekar NICMAR 128
Provisions in Standard Form Contracts
FIDIC - Clause 7.6 [Remedial works]
• The contractor’s liability continues to remove and re-execute the defective
work or any work urgently required for the safety of the works for any
cause, notwithstanding any previous test or certification by the engineer.
• The conditions of the contract include a clause that empowers the owner to suspend
the work.
• This suspension is not considered as a breach of contract on his part.
• This clause protects the owner in the event of an emergency or an unexpected event.
Example …
• Assume an owner has signed a contract to construct the first storey of an already
existing ground floor house.
• The construction of the first storey is partially completed when the walls of the old
structure develop cracks.
• Under such circumstances, the engineer, on behalf of the owner, should have the
power to suspend the work until he can determine what is to be done.
• The investigations regarding the causes of the development of cracks and the remedial
measures may cause a considerable delay before he is sure that he can advise the
owner to go ahead with the work.
It should be noted….
• The right to suspend the work is not given to the contractor.
• The owner should make judicious use of the authority
• When a contract specifies a definite time for completion, an extension of time should be
granted to the contractor to make up for the time lost due to suspension.
• The extension should be liberal enough so that the contractor gets sufficient margin for
resumption of the work at a speed at which he was progressing when the suspension
was ordered.
• The contractor is entitled to reasonable compensation for his unavoidable expenses on
account of the suspension.
Suspension:
• Temporary stoppage of the work.
• May be due to reasons attributable to client or contractor.
• May affect part/whole work.
• May lead to Omission/termination.
• Care during suspension by contractor.