Professional Documents
Culture Documents
Roll-Out RAN TA-Report Q04-22 DeepDive Final en-GB
Roll-Out RAN TA-Report Q04-22 DeepDive Final en-GB
• Cologne - 24 January 2023 - Roll-out RAN TA Report Q04/22 - Strictly Confidential (S1)
Overview
1. All sub-projects further delayed compared to November 2022 planning. Catch-up will start from Q1 2023, as
backbone and LTE technology are now available for commissioning LTE sites.
2. Radio planning pipeline now "in front of the wave", problematic is the implementation with all site suppliers, i.e.
both shareholders (anchor customers, regional projects and target sites) and commercial site suppliers (DFMG,
Vantage, ATC).
3. The critical bottleneck is currently the construction planning resources that all sub-projects access in parallel.
According to the JV, there is no problem with construction resources in view of the comparatively small number of
sites, provided that a forecast is available.
4. The problem of radio relay connections will continue to decrease with increasing network expansion, as the
number of remote stations available for connection increases with the rollout.
5. Process optimisation with site suppliers initiated, further escalation with selected suppliers, including
shareholders required
6. The basic problem of the many sub-projects - which prevent a concerted, uniform approach and repeatedly lead
to rescheduling - remains.
3. overview of target figures (budget Nov 22) versus forecast figures from the projects
Regional deployment projects and phasing 450c and target projects
3. overview of target figures (budget Nov 22) versus forecast figures from the projects
Regional deployment projects and phasing 450c and target projects
3. overview of target figures (budget Nov 22) versus forecast figures from the projects
Regional deployment projects and phasing 450c and target projects
For test CDMA, more than half realised, upgrade dual-mode initially only
EWE 99 95 55 55 90
only at 4 locations for tests
Total 128 185 220 244 278 308 334 359 372
EWE / CDMA 55 68 75 83 90 94 99 99 99
Resin / CDMA 5 7 7 7 8 8 8 8 8
NetAachen / CDMA 14 14 14 14 14 14 14 14 14
WWN / CDMA 24 27 28 33 34 35 37 39 41
NetCologne1 / Nokia 0 8 10 10 10 14 14 14 14
SaxonyNetwork /Nokia 0 0 0 1 8 15 22 32 37
EAM / Nokia 0 0 2 9 15 24 27 33 33
WEMAG2 / CDMA 2 8 23 26 29 34 35 35 35
1) +10 locations in Q1 25
2) +5 locations in Q1 25
Total -79 -59 -53 -49 -57 -42 -37 -27 -22
EWE / CDMA -8 0 0 0 0 0 0 0 0
Resin / CDMA -2 0 0 0 0 0 0 0 0
NetAachen / CDMA 0 0 0 0 0 0 0 0 0
WWN / CDMA -5 -4 -5 -3 -4 -5 -5 -5 -4
1) +10 locations in Q1 25
2) +5 locations in Q1 25
Short-term connection to LTE central technology/backbone, achievable for most anchor customers by March
SIM card procurement realised at an early stage over 50 test SIM cards per anchor customer
Publication and ongoing processing of a terminal whitelist in coordination with the anchor customers
Additional services from anchor customers (network upgrades) and 450connect (especially services & IT)
Aiming for a sufficiently uniform and fair solution within the framework of existing business planning
Coordination of the transitional solution with all ACs has taken place
Construction of commercial dual-mode base stations and connection to Nokia Core - transitional solution LTE
operation
Use of web portal by anchor customers (testing & provisioning of commercial SIMs)
Clarification AKV
3. overview of target figures (budget Nov 22) versus forecast figures from the projects
Regional deployment projects and phasing 450c and target projects
Budget Nov 22
Regional projects Q4 2022 Q1 2023 Q2 2023 Q3 2023 Q4 2023 Q1 2024 Q2 2024 Q3 2024 Q4 2024
Total 25 51 113 156 195 219 219 220 221
EnBW 16 38 90 125 160 178 178 178 178
Middle Rhine 6 8 15 22 24 27 27 27 27
OVAG 3 5 8 9 11 14 14 15 16
Query Q4.22
Regional projects Q4 2022 Q1 2023 Q2 2023 Q3 2023 Q4 2023 Q1 2024 Q2 2024 Q3 2024 Q4 2024
Total 0 11 29 78 121 153 172 189 221
EnBW 0 9 24 64 88 118 136 153 178
Middle Rhine 0 1 2 7 25 26 27 27 27
OVAG 0 1 3 7 8 9 9 9 16
Delta
Regional projects Q4 2022 Q1 2023 Q2 2023 Q3 2023 Q4 2023 Q1 2024 Q2 2024 Q3 2024 Q4 2024
Total -25 -40 -84 -78 -74 -66 -47 -31 0
EnBW -16 -29 -66 -61 -72 -60 -42 -25 0
Middle Rhine -6 -7 -13 -15 1 -1 0 0 0
OVAG -3 -4 -5 -2 -3 -5 -5 -6 0
Phase 2 (West Energy to EDIS) Q4 2022 Q1 2023 Q2 2023 Q3 2023 Q4 2023 Q1 2024 Q2 2024 Q3 2024 Q4 2024
Budget Nov 22 0 26 83 165 247 295 320 342 360
Project (forecast figures) 0 7 7 69 198 266 304 342 360
Delta 0 -19 -76 -96 -49 -29 -16 0 0
Forecast based on
target figures (Nov
Phase 3 (Bavaria/South Saxony/South Hesse) Q4 2022 Q1 2023 Q2 2023 Q3 2023 Q4 2023 Q1 2024 Q2 2024 Q3 2024 Q4 2024 22 budget) with risk
Budget Nov 22 0 0 0 55 115 175 235 295 307 discount
Phase 4 (SHW/South Eifel/Hunsrück) Q4 2022 Q1 2023 Q2 2023 Q3 2023 Q4 2023 Q1 2024 Q2 2024 Q3 2024 Q4 2024
Budget Nov 22 0 1 2 4 4 30 67 90 109
Project (forecast figures) 0 0 0 0 4 30 67 90 109
Delta 0 -1 -2 -4 0 0 0 0 0
Total Q4 2022 Q1 2023 Q2 2023 Q3 2023 Q4 2023 Q1 2024 Q2 2024 Q3 2024 Q4 2024
Budget Nov 22 54 176 266 406 548 682 804 909 958
Project (forecast figures) 18 98 145 257 470 632 776 909 958
Delta -36 -78 -121 -149 -78 -50 -28 0 0
20.04.2024 Roll-out RAN TA Report Q04/22 - DeepDive - Strictly Confidential S1 23
Agenda
3. overview of target figures (budget Nov 22) versus forecast figures from the projects
Regional deployment projects and phasing 450c and target projects
BTB released - - - 2 - 2
EP released - 1 6 5 - 12
AP released - 2 3 1 - 6
GU commissioned 42 10 1 - 2 57
Infrastructure ready 11 2 2 1 1 17
eNodeB installed 2 - - 1 - 3
Total 56 15 12 10 3 96*
STOB received 41 13 10 5 2 71 27
All sites in WK with planning date Infra completion by end of June `23
Locations for CL in WK with plan date completion infra by February/mid-March `23
Locations provided by Vantage or ATC -> Power supply issue
The following colour coding is shown:
Next step:
Identifying the "clusters" that can be integrated, e.g. Hanover
Identify the sites to be prioritised to ensure the link chains for CL, e.g. the Burgdorf/01BURGDORF01 site.
Close coordination and synchronisation with RiFu planning, prioritisation of frequency applications if necessary.