SWASTIK-EQUIPLAVAGGI JV General Consultant for Chennai Metro Rail

Project – Phase II

Contract C4-DM100
Monthly Progress
Review-12
Agenda
Review Meeting 12

1 Projects Overview 9 Interface Matrix for ICF

2 Current Progress 10 Site Pictures & Manufacturing Progress Pictures


3 Vendors Approval Status 11 Variation Status
4 PO Issued Status
12 PMIS Submission Progress and S Curve
Project's Key Dates for Design
5 13 Priority Delivery Equipment List
Submission & Progress
14 Early Delivery Equipment List
6 Project's Key Dates Plan
15 NONO Equipment FAT Status
7 List of Key Personnel
16 Interface Key Issues & Key Issues
8 Interface Agreement Progress
Projects Overview

CLIENT :- CHENNAI METRO RAIL LIMITED (CMRL)

CONSULTANT :- AEON

MAIN CONTRACTOR :- SWASTIK- EQUIP LAVAGGI JV

CONTRACT :- C4 – DM100

MEETING :- MONTHLY PROGRESS REVIEW MEETING - 12

VENUE :-MetroS CMRL Office, CHENNAI


Current Progress

Notice to Proceed (NTP) : 14.03.2023


Duration of Contract : 530 days (excluding DLP)

Financial Progress Physical Progress

Description Amount Description As on 31th Mar 2024


(INR)

Project Value 31,80,46,212.09


Planned Progress 36.00%

Cumulative Payment 1,52,26,065.68


Certified up to Mar 2024 Actual Progress 26.41%

% of Planned Payment 10% on NONO for 09


Nos. Equipment

% of Payment Received 9.606%


Design Submission Summary
Vendor Approval

Under Review with


Total Equipment NONO NOWC REJD
GC

12 12 0 0 0

Design Approval

Under Review
Total Equipment NONO NOWC REJD Yet to submit
with GC

12 9 0 0 3 0
Vendors Approval Status (1/6)

Proposed Vendors Approved Vendors


Sr. Location & Remarks
Equipment Date of
No. Vendors Vendors Date of
Submissio Country
Name Name Approval
n

DM10 Automatic Train Equip 14.03.2023 Equip Approved


1 Wash Plant Lavaggi Lavaggi 06.06.2023 Vesime , Italy

Beaz Beaz
Battery 14.03.2023 02.06.2023 Hoogkarspel, Approved
Solutions Solutions
Operated Rail B.V B.V Netherlands
DM10
2 cum Road
Shunter
(BORRS) G. Zwiehoff 14.03.2023
GmBH

Bertolotti 10.03.2023 Bertolotti 02.06.2023 Florence (Italy), Approved


Synchronized France
DM10 Pit Jacks
3 (UFLS) for 3 Pfaff 10.03.2023 Pfaff 17.04.2023 Approved
Car Trains
Autolift 10.03.2023
Vendors Approval Status (2/6)

Proposed Vendors Approved Vendors


Location &
Sr.
Equipment Date of Remarks
No. Vendors Date of Country
Vendors Name Submissio
Name Approval
n

Visiona Control 14.03.2023


Wheel Industrial
Profile
DM104 Measuring
System
(WPMS) -
Wayside Riftek LLC 14.03.2023 Riftek 05.01.2024 Belarus Approved
Vendors Approval Status (3/6)
Proposed Vendors Approved Vendors
Sr. Equipme Location & Remarks
No. nt Date of Vendors Date of
Vendors Name Country
Submission Name Approval

EOT Krane Mfg. 24.03.2023


Crane
(10t/3t) Alpha Services 24.03.2023
DM105 Double
Girder
Cat. I K2 Cranes and Chennai
K2 Cranes and 24.03.2023 15.04.202 Approved
Components 3 (Tamil Nadu),
Components Pvt Ltd Pvt Ltd India

Grip Engineers Pvt. 15.03.2023


Ltd.

EOT Krane Mfg. 24.03.2023


Crane
DM106 (10t/3t)
Double Alpha Services 24.03.2023
Girder
Cat. II
K2 Cranes and Chennai
Vendors Approval Status (4/6)
Proposed Vendors Approved Vendors
Sr. Location & Remarks
Equipment
No. Vendors Date of Vendors Date of Country
Name Submission Name Approval

Grip Engineers 15.03.2023


Pvt. Ltd.

Krane Mfg. 24.03.2023


EOT Crane
DM107 (5t) Single
Girder Alpha Services 24.03.2023

K2 Cranes and K2 Cranes and Chennai


Components 24.03.2023 Components 15.04.2023 (Tamil Approved
Pvt Ltd Pvt Ltd Naidu), India

Gemini Power
Hydraulics Pvt. 11.03.2023
Self-
Propelled Ltd.
DM108 Battery-
Operated
Scissor Lift Godrej & Boyce 11.03.2023 Godrej & Boyce 17-04-2023 New Delhi, Approved
Mfg. Co. Ltd. Mfg. Co. Ltd
India
Vendors Approval Status (5/6)
Proposed Vendors Approved Vendors
Sr. Location & Remarks
Equipment Date of
No. Vendors Vendors Date of
Submissi Country
Name Name Approval
on

Battery Godrej & Godrej &


Operated 11.03.2023 Boyce Mfg. 15.04.2023 New Delhi, Approved
Boyce Mfg. Co.
Forklift Truck Ltd. Co. Ltd. India
DM10 with
9 Extendable
Arms Action
Construction 31.03.2023
1) 3T 02Nos. Equipment’s
2) 2T 02 Nos. Ltd.

Tech Mark Tech Mark Pune


Automation & 11.03.2023 Automation 17-04-2023 (Maharashtra) Approved
Vertical Controls. & Controls.
DM11
0 Storage , India
System
Tech Mech 13.03.2023
World
Vendors Approval Status (6/6)

Proposed Vendors Approved Vendors


Sr. Location &
Equipment Date of Remarks
No. Vendors Vendors Date of
Submissi Country
Name Name Approval
on

Key Management DAccess DAccess Pune


DM111 Security 11.03.2023 Security 17-04-2023 Approved
System (Min. 100 System System (Maharashtra),
Keys Holder) Pvt. Ltd. Pvt. Ltd.
India

Autolift 11.03.2023
Synchronized
Mobile Jacks (12 Florence (Italy),
Bertolotti 11.03.2023 Bertolotti 02-06-2023 France Approved
DM112 Nos.) and Car
Body Stands (12
Nos.)
Pfaff 11.03.2023 Pfaff 17-04-2023 Approved
PO Issued Status (1/2)
Copy of Un-priced
Sr. No. Equipment OEM’s Name PO Issuance Date
shared with CMRL

DM101 Automatic Train Wash Equip Lavaggi 12.06.2023 Yes


Plant

Battery Operated Rail


DM102 cum Road Shunter Beaz Solutions B.V 07.06.2023 Yes
(BORRS)

DM103 Synchronized Pit Jacks Bertolotti S.P.A 07.06.2023 Yes


(UFLS) for 3 Car trains

Wheel Profile Measuring


DM104 System (WPMS) - Riftek 16.01.2024 Yes
Wayside

DM105 EOT Crane (10t/3t) K2 Cranes 15.05.2023 Yes


Double Girder Cat. I

DM106 EOT Crane (10t/3t) K2 Cranes 15.05.2023 Yes


Double Girder Cat. II

DM107 EOT Crane (5t) Single K2 Cranes 15.05.2023 Yes


Girder
PO Issued Status (2/2)

Copy of Un-priced
Sr. No. Equipment OEM’s Name PO Issuance Date
shared with CMRL

DM108 Self-Propelled Battery- Godrej & Boyce


Operated Scissor Lift 31.10.2023 Yes
Mfg. Co. Ltd

Battery Operated Forklift


Truck with extendable
DM109 arms Godrej & Boyce
31.10.2023 Yes
Mfg. Co. Ltd
1) 3t = 2 Nos.
2) 2t = 2 Nos.

Tech Mark
DM110 Vertical Storage System Automation & 15.05.2023 Yes
Controls.

DM111 Key Management System DAccess Security


(Min. 100 Keys Holder) 07.06.2023 Yes
System Pvt. Ltd.

Synchronized Mobile
DM112 Jacks & Car Body Bertolotti S.P.A Italy 07.06.2023 Yes
Stands (12 Nos.)
Project's Key Dates for Design Submission & Progress (1/8)

Contractual
Actual Design Revised/Re-
Sr. No. Equipment Design Key Design Approval Date
Submitted Date submission date
Date

Rev 0 Submitted dated


R0 REJD: 21.08.2023
04.08.2023
DM101 Automatic Train 12-06-2023 In Review
Wash Plant Rev 1 Submitted dated
In Review
11.03.2024

Rev 0 Submitted dated


05.07.2023 Rev 0 REJD: 24.07.2023

Rev 1 Submitted dated Rev 1: NOWC received


06.09.2023
Battery Operated dated 25.09.023
NONO Recieved
DM102 Rail cum Road 12-06-2023
Rev 2 Submitted dated Rev 2: NOWC recieved
Shunter (BORRS) 01.11.2023
dated 16.11.2023

Rev 3 Submitted dated Rev 3: NONO received


26.12.2023
Dated 01.02.2024
Project's Key Dates for Design Submission & progress (2/8)

Contractual
Actual Design Revised/Re-
Sr. No. Equipment Design Key Design Approval Date
Submitted Date submission date
Date

Rev 0 Submitted dated Rev 0 REJD:


01.09.2023 27.09.2023
Synchronized Pit
Rev 1 Submitted dated Rev 1 NOWC
DM103 Jacks (UFLS) for 12-06-2023 25.10.2023 16.11.2023 NONO Recieved
3 Car trains
Rev 2 Submitted dated Rev 2 NONO Recieved
14.12.2023 02.01.2024

Wheel Profile
Measuring Rev 0 Submitted dated
DM104 12-06-2023 In Review
System (WPMS) 03.04.2024

- Wayside
Project's Key Dates for Design Submission & progress (3/8)
Contractual Actual Design Revised/Re-
Sr. No. Equipment Design Approval Date
Design Key Date Submitted Date submission date

Rev 0 submited dated: Rev 0 REJD:


12.06.2023 27.06.2023
EOT Crane Rev 1 submitted dated: Rev 1: NOWC received
DM105 (10t/3t) Double 12-06-2023 NONO Recieved
Girder Cat. I 18.08.2023 dated 12.09.2023

Rev 2 submitted dated: Rev 2: NONO received


17.10.2023 dated 26.10.2023

Rev 0 submitted dated: Rev 0 REJD:


12.06.2023 27.06.2023
EOT Crane
Rev 1 submitted dated: Rev 1: NOWC received NONO Recieved
DM106 (10t/3t) Double 12-06-2023
21.08.2023 dated 12.09.2023
Girder Cat. II
Rev 2 submitted dated: Rev 2: NONO received
26.10.2023 Dated 01.11.2023
Project's Key Dates for Design Submission & progress (4/8)

Contractual
Actual Design Submitted Revised/Re-
Sr. No. Equipment Design Key Design Approval Date
Date submission date
Date

Rev 0 submitted dated: Rev 0 REJD:


12.06.2023 27.06.2023

EOT Crane (5t) Rev 1 submitted dated: Rev 1: NOWC received NONO Recieved
DM107 12-06-2023
Single Girder 22.08.2023 dated 12.09.2023

Rev 2 submitted dated: Rev 2: NONO received


17.10.2023 dated 26.10.2023
Project's Key Dates for Design Submission & progress (5/8)

Contractual
Actual Design Submitted Revised/Re-
Sr. No. Equipment Design Key Design Approval Date
Date submission date
Date

Rev 0 submitted dated Rev 0


REJD:11.12.2023
28.11.2023

Rev 1 submitted dated Rev 1

08.01.2024 REJD:15.02.2024
Self-Propelled
DM108 Battery-Operated 30.09.2023 NONO Received
Rev 2
Scissor Lift Rev 2 submitted dated
Submitted based on
19.01.2024
MOM

Rev 3 submitted dated NONO Received dated


19.01.2024 17.03.2024
Project's Key Dates for Design Submission & progress (6/8)
Contractual
Actual Design Revised/Re-
Sr. No. Equipment Design Key Design Approval Date
Submitted Date submission date
Date

2 Ton: R0 submitted dated 2 Ton Rev 0


17.01.2024 REJD:23.01.2024
3 Ton: R0 submitted dated 3 Ton Rev 0
17.01.2024 REJD:30.01.2024

2 Ton: R1 submitted dated 2 Ton Rev 1


Battery Operated
Forklift Truck with 07.02.2024 NOWC : 23.02.2024
DM109 extendable arms 30-09-2023 NONO Received
3 Ton: R1 submitted dated 3 Ton Rev 1
1) 3t = 2 Nos.
2) 2t = 2 Nos. 07.02.2024 NOWC: 23.02.2024

2 TON
2 TON: R2 submitted dated NONO Received dated
18.03.2024
07.03.2024
3TON: R2 submitted dated 3 TON
NONO Received dated
19.03.2024
25.03.2024
Project's Key Dates for Design Submission & Progress (7/8)

Contractual
Actual Design Revised/Re-
Sr. No. Equipment Design Key Design Approval Date
Submitted Date submission date
Date

Rev 0 submitted dated: Rev 0


04.10.2023 REJD:11.10.2023

Vertical Storage Rev 1 submitted dated: Rev 1


DM110 30-09-2023 In Review
System 02.02.2024 REJD:19.02.2024

Rev 2 submitted dated:


In Review
19.03.2024

Rev 0 submited dated: Rev 0: NOWC received


Key Management 29.09.2023 dated 07.10.2023
DM111 System (Min. 100 30-09-2023 NONO Recieved
Keys Holder) Rev 1 submited dated: Rev 1: NONO received
20.10.2023 dated 26.10.2023
Project's Key Dates for Design Submission & Progress (8/8)
Contractual
Actual Design Revised/Re-
Sr. No. Equipment Design Key Design Approval Date
Submitted Date submission date
Date

Rev 0 Submitted dated Rev 0 NOWC received


25.07.2023 dated 04.08.2023

Synchronized
Rev 1 Submitted dated Rev 1 NOWC received
Mobile Jacks 12-06-2023 dated 16.09.2023 NONO Recieved
11.08.2023
(12 Nos.)
Rev 2 Submitted dated Rev 2 NONO received
04.10.2023 dated 19.10.2023

GAD R0 Submitted
DM112
dated: 02.08.2023
NONO Received on GAD
dated 25.09.2023
GAD R1 Submitted
Car Body dated: 09.08.2023
Stands (12 12-06-2023 NONO Recieved
Nos.) Rev 0 submitted dated
Rev 0 NOWC: 11.12.2023
28.11.2023

Rev 1 submitted dated : Rev 1 NONO Received


26.12.2023 dated 01.01.2024
Project's Key Dates Plan
Project's Key Dates Plan (1/3)
*Planned FAT Delivery T&C
Contractu Revised/ Actual Actual
Date Date Date
Sr. No. Equipment al Design Resubmission of Delivery T&C
[Intermediate As per As per
Key Date Design date Date Date
Key date] Contract Contract

Automatic Rev 1 submitted


15-08-
DM101 Train Wash 12-06-2023 dated 11.03.2024 16-08-2024 17-05-2024 30-09-2024
2024
TBD
Plant (In Review)

Battery
Operated Rail
NONO Received 05-08-
DM102 cum Road 12-06-2023 15-06-2024 06-07-2024 TBD TBD
2024
Shunter dated 01.02.2024
(BORRS)

Synchronized
Pit Jacks NONO Received 15-08-
DM103 12-06-2023 22-07-2024 17-05-2024 TBD TBD
(UFLS) for 3 2024
Car trains dated 02.01.2024

Wheel Profile
Measuring REV 0 Submitted
15-08-
DM104 System 12-06-2023 dated 02.04.2024 30-08-2024 17-05-2024 TBD TBD
2024
(WPMS) - (In Review)
Wayside

*Intermediate key date – Non Contractual key date


Project's Key Dates Plan (2/3)
*Planned FAT Delivery
Contractu Revised/ Actual T&C Date
Date Date Actual
Sr. No. Equipment al Design Resubmission Delivery As per
[Intermediate As per T&C Date
Key Date of Design date Date Contract
Key date] Contract

EOT Crane NONO


DM105 (10t/3t) Double 12-06-2023 Received dated TBD 17-04-2024 TBD 16-07-2024 TBD
Girder Cat. I 26.10.2023

EOT Crane NONO


DM106 (10t/3t) Double 12-06-2023 Received dated TBD 17-04-2024 TBD 16-07-2024 TBD
Girder Cat. II 01.11.2023

NONO
EOT Crane (5t)
DM107 12-06-2023 Received dated TBD 17-04-2024 TBD 16-07-2024 TBD
Single Girder
01.11.2023

Self-Propelled
NONO
Battery- Ready for FAT
DM108 30-09-2023 Received dated 16-06-2024 TBD 25-08-2024 TBD
Operated
17.03.2024
Scissor Lift

*Intermediate key date – Not Contractual key date


Project's Key Dates Plan (3/3)

*Planned Delivery
Contractual Revised/Re- Actual T&C Date Actual
FAT Date Date
Sr. No. Equipment Design Key submission of Delivery As per T&C
[Intermediat As per
Date Design date Date Contract Date
e Key date] Contract

NONO FAT
Self-Propelled Received dated Completed
DM109 30-09-2023 16-06-2024 03-04-2024 25-08-2024 TBD
Battery-Forklift 18.03.2024 & dated
25.03.2024 28.03.2024

Vertical Storage Rev 2 TBD


DM110 30-09-2023 TBD 16-06-2024 TBD 25-08-2024
System In Review

Key Management NONO 01 of 02 Qty


TBD
DM111 System (Min. 100 30-09-2023 Received dated FAT done on 16-06-2024 TBD 25-08-2024
Keys Holder) 26.10.2023 20.12.2023

Synchronized NONO
Mobile Jacks Received dated
(12 Nos.) 19.10.2023
TBD
DM112 12-06-2023 25-07-2024 17-05-2024 TBD 31-07-2024
NONO
Car Body Stands
Received dated
(12 Nos.)
01.01.2024

*Intermediate key date – Not Contractual key date


List of Key Personnel
Project C4-DM100

Shobhit Saxena Shubham Singh


Head Project Design Manager

Parthe Pandarinath Rizwan Ahmed Khan


Genba
Service Manager
Project Manager

N. Saravanan Himanshu Srivastava


Interface Manager Document Controller
Access Date

Actual Access date


Access Date (Handover to DM100
As per Contract
Description Contractor)
From Civil

AD-01: EOT Crane


28.01.2024 13.04.2024
Installation

AD-02: Auto Train Wash


07.05.2024 07.05.2024
Plant installation

AD-03: Other Depot


27.05.2024 27.05.2024
Machine installation
Interface Agreement Progress

Status of Interface Agreement


Interface Contractor Remarks
Signed/Unsigned

Civil Signed

Rolling Stock Signed

OHE Signed

Track Signed

E&M Signed

Signaling Signed

Pit wheel Lathe


Interface Matrix for ICF (1/3)

DM ID DM Name OHE Track Civil RST E&M Signalling Total Open Closed

Total 4 1 10 3 6 7 31

DM101 ATWP Open 4 1 10 3 6 7 31

Closed 0 0 0 0 0 0 0

Total 1 3 1 5

DM102 BORRS Open 1 3 1 5

Closed 0 0 0 0

Total 2 5 3 3 13

DM103 SPJ Open 2 5 3 3 13

Closed 0 0 0 0 0
Interface Matrix for ICF (2/3)

DM ID DM Name OHE Track Civil RST E&M Signalling Total Open Closed

Total 2 2 2 3 3 12

DM104 WPMS Open 2 2 2 3 3 12

Closed 0 0 0 0 0 0

Total 2 4 3 9

DM105 EOT-01 (C-I) Open 2 4 3 9

Closed 0 0 0 0

Total 2 4 3 9

DM106 EOT-01 (C-II) Open 2 4 3 9

Closed 0 0 0 0
Interface Matrix for ICF (3/3)
DM ID DM Name OHE Track Civil RST E&M Signalling Total Open Closed
Total 4 3 7
DM107 EOT-01 (C-III) Open 4 3 7
Closed 0 0 0
Total 1 1
DM108 Scissor Lift Open 1 1
Closed 0
Total 1 1
Battery
DM109 Open 1 1
operator forklift
Closed 0
Total 3 2 5
DM110 VSS Open 3 2 5
Closed 0 0 0
Total 2 2
DM111 KMS Open 2 2
Closed 0 0
Total 2 4 3 3 12
MLJ & Car
DM112 Open 2 4 3 3 12
Body Stand
Closed 0 0 0
107 107 0
SITE PICTURES dated (1/2)
SITE PICTURES dated (2/2)

ATWP Site
STATUS OF KEY MANAGEMENT SYSTEM

SAT has been performed for Key Management System. Awaiting handover
certificate from CMRL
STATUS OF FORKLIFT 2 TON & 3 TON

Successful FAT has been conducted dated 28.03.2024


STATUS OF FORKLIFT 2 TON & 3 TON

Forklift’s delivered at Koyambedu depot


dated 03.04.2024
STATUS OF PIT JACK & MOBILE JACK

Raw Material has been procured.


Pit Jack & Mobile Jack status

Other Electricals and Mechanical Items has been procured


STATUS OF BORRS

Sheet Cutting and Fabrication work are under progress.


Variation Status

Equipment Variation Status Detail

EOT 5ton Single Girder: 02 Nos Approval Received

Scissor Lift: 01 No. Approval Received

Software and Hardware modification in TBD


BORRS for interface with Pit Wheel Lathe

RFID tags , Reader and Integration in TBD


software for AWPMS
PMIS Submission Progress
PMIS Progress Indicator/S Curve

Physical Progress Planned S curve


120.00%

100.00% 100.00% 100.00% 100.00%

91.80%

82.10%
80.00%

60.00% 59.40%

49.80%

40.00%
36.20%

26.41%
22.70%
20.60%
20.00%
15.60% 13.60%
9.20% 9.20% 10.00% 14.20%
9.20% 11.02% 9.60% 9.70% 8.20%
7.40% 10.00%
5.20% 7.40% 10.05% 5.60%
5.85% 6.55%
5.20% 2.20% 4.90%
1.80%
2.40% 3.40% 0.80%
0.00% 1.00%

Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Jun-24 Jul-24 Aug-24 Sep-24 Oct-24

Plan for the Month Plan Cumulative Achieved Cumulative


Priority Delivery Equipment List
Designated
S.NO. Description Qty Remarks
Depot
Joint site visit conducted on 1st & 2nd Mar, 2024
at Koyambedu and Poonamallee Depot. Detailed
Report and Design Document has been submitted
1 WPMS- Wayside (DM104) 01 Koyambedu for approval. (Please note that lead time of
Delivery of sub assemblies which need to be
Outsourced will take around 3 months time.)

2 Key Management System (DM111) 01 Koyambedu 01 System has been installed at Koyambedu
Depot.

3 Vertical Storage System VSS (DM110) 01 Koyambedu Revised Design Document has been submitted
awaiting approval from GC/CMRL

4 Self Propelled Battery- Operated 01 Wimco Nagar Depot Please refer to Key Issues Slide
Scissor Lift (DM108)
Early Delivery Equipment List (Requested by Swastik)

Contractual Requested Delivery


Sr. No Equipment Delivery Date Dates Remarks

DM 105 Electric Overhead Travel (EOT);10/3 TON 17.04.2024 TBD Refer to Interface Issue Slide
Double Girder CAT-I

Electric Overhead Travel (EOT); 10/3 TON


DM 106 Double Girder CAT-II 17.04.2024 TBD Refer to Interface Issue Slide

DM 107 Electric Overhead Travel (EOT); 5 TON 17.04.2024 TBD Refer to Interface Issue Slide
Single Girder

DM 108 Scissor Lift 16.06.2024 Before 30th April

DM 109 Fork Lift 16.06.2024 Before 31.03.2024 Delivered on 03.04.2024

DM 110 Vertical Storage System (VSS) 16.06.2024 Before 31.03.2024 Design Document in review with
GC/CMRL

01 no. installed at Koyambedu Depot.


DM 111 Key Management System (KMS) 16.06.2024 Before 31.03.2024 Remaining 01 no. will be deliver as per
requested date.
NONO Equipment FAT & Delivery Status
Sr. No Equipment Delivery Date Proposed FAT FAT Location Remarks
Date (Tentative)
Battery Operated Rail
DM102 cum Road Shunter 12-06-2023 15-06-2024 Delhi, India
(BORRS)

DM -103 Synchronized Pit Jacks 17-05-2024 30.07.2024 Delhi, India


(UFLS) for 3 Car Trains (Contractual Date)
Electric Overhead Travel Before 31.03.2024 K2 Cranes Factory, Refer to Interface Issue Slide
DM 105 (EOT);10/3 TON Double (Requested) TBD Chennai, India
Girder CAT-I
Electric Overhead Travel Before 31.03.2024 K2 Cranes Factory, Refer to Interface Issue Slide
DM 106 (EOT); 10/3 TON Double (Requested) TBD Chennai, India
Girder CAT-II

DM 107 Electric Overhead Travel Before 31.03.2024 TBD K2 Cranes Factory, Refer to Interface Issue Slide
(EOT); 5 TON Single Girder (Requested) Chennai, India

Key Management System Before 31.03.2024 01 no. installed at Koyambedu.


DM 111 (KMS) (Requested) 30.03.2023 Pune, India Remaining 01 no. will follow the
mentioned dates.

DM112 Synchronised Mobile Jacks 17-05 2024 02.07.2024 Delhi, India


and Car Body Stand (Contractual Date)
INTERFACE KEY ISSUES (1/2)

Sr. No. Equipment OEM’s Name Interface Key Issues

Automatic
Equip Incorporating the requirements of Civil and MEP for
DM101 Train Wash
Lavaggi
Plant ATWP in final GFC drawings of CMRL.

1. Incorporating the requirements of Civil and MEP


Synchronized
Bertolotti for SPJ in final GFC drawings of CMRL.
DM103 Pit Jacks for 3
S.P.A Italy
Car trains 2. Drain points in Pits for PIT JACK needs to be
taken care.
INTERFACE KEY ISSUES (1/2)

Sr. No. Equipment OEM’s Name Key Issues

Synchronized Incorporating the requirements of Civil and MEP for SMLJ in final
DM112 Bertolotti S.P.A Italy
Mobile Jack GFC drawings of CMRL.

Dimensions has been taken from site by OEM accordingly


DM 105,
procurement of raw material and manufacturing is started. However it
DM 106, EOT Cranes K2 Cranes
was noticed during measurement the LT (longitudinal travel) is more
DM 107
than specified in tender issue to be discussed.

Pit Wheel Lathe CAD layout received from CMRL/GC, OEM is


EOT Cranes 02 preparing the GAD for submission.
DM107 K2 Cranes
Nos. (Variation) Awaiting CAD layout of Depot store where second EOT will be
installed.
KEY ISSUES (1/2)

Sr. No. Equipment OEM’s Name Key Issues

Self-Propelled
DM108 Godrej Scissor Lift are ready for the FAT. Date of FAT and
Battery-Operated
Location will be shared officially shortly.
Scissor Lift 1/6

DM 110 Vertical Storage


Tech Mark Design Document approval pending.
System (VSS)
KEY ISSUES (2/2)

Other Key Issues

1. Interface Between BORRS and Pit wheel Lathe scope issue to be discussed as it
involves extra cost
2. RFID tags (WPMS) for Koyambedu depot will be at additional cost the same needs to
Miscellaneous be discussed.
3. For additional Scissor Lift, can Swastik claim 10% on Design Document?
4. For additional EOT 5 Ton, Whether complete Design Document needs to submitted
or only GAD will be enough for NONO on Design Document?
THANK YOU