REPLACEMENT OF 4MVA

TRANSFORMER @ BPS1
PROJECT 2021-0395
June 15, 2023 – Weekly Meeting
Proposed Catch Basin in Bundwall
4-MVA TRANSFORMER BUNDWALL CONCERN
BUNDWALL CATCH BASIN
4-MVA TRANSFORMER PROJECT STATUS
SITE ACCEPTANCE TEST STATUS

 1. MVSG (34.5KV) (VCB, CT, PT, LA, Protection Relay & Bus bar)
 a. CT IR, Windings, Ratio Test – Done (Passed: March 8 & 28, 2023)
 b. Lightning Arrester Insulation Resistance Test– Done (Passed: 3/28/23)
 c. PT Insulation & Windings Test and Ratio Test – Done (Passed: 3/29/23)
 d. Protection Relay Test (Software for Setting) – Done (Passed: May 5, 2023)
 e. VCB IR, Contact Resistance, & Contact Timing Test – Done (Passed: May 4, 2023)
 f. Bus bar Hi-pot Test – Done (Passed – May 10, 2023)

 2. MVSG2 (2.4KV) (VCB, CT, PT, LA, Protection Relay & Busbar)
 a. CT IR, Windings, Ratio Test – Done (Passed: March 8 & 28, 2023)
 b. Lightning Arrester Insulation Resistance Test– Done (Passed: 3/28/23)
 c. PT Insulation & Windings Test and Ratio Test – Done (Passed: 4/14/2023)
 d. Protection Relay Test ((Software for Setting) - Done (Passed: May 18, 2023)
 e. VCB IR, Contact Resistance, & Contact Timing Test - Done (Passed: May 4, 2023)
 f. Bus bar Hi-pot Test (RAMP Needed for Testing)
 3. Grounding Protection System Test – done (Passed: 3/29/23-Wed)
 4. Cables Insulation Resistance Test & High Potential Test
 a. Service Pole to 34.5kv MVSG1 Incoming Line – Done (Passed-3/28/23-Tuesday)
 b. 34.5kv MVSG1 Outgoing Line to Transformer Primary Line – (IR Passed-4/26/23)
 c. Transformer Secondary Line to 2.4kv MVSG2 Incoming Line - (IR Passed-4/26/23) Hi-pot (passed:
May 22, 2023)
 d. 2.4kv MVSG Outgoing Line to MCC Panel Incoming Line - (IR Passed-4/26/23) Hi-pot (passed: May
18)
 5. SF6 LBS – (April 26, 2023) Retest (Passed: May 18, 2023)
 6. NGR Test – Done (Passed: May 4, 2023)
 7. 4MVA Transformer – SAT Done – (Passed May 4&5, 2023)

 Summary of Testing: Start: March 8,2023 – Completion: May 22, 2023


REMAINING WORKS

ENERGIZATION: (Testing & Commissioning) – Shutdown - TBD


TAPPING OF THE SYSTEM TO THE BALARA DISTRIBUTION LINE
 Termination at MCC Panel Incoming Terminals

POST ENERGIZATION WORKS


 Punch Listing & Documentation (On Going)
 Dismantling of Allis Chalmer Transformer and its appurtenances

 Progress Accomplishment: WPR#70 – 94.8% (June 4-10, 2023)


SITE OBSERVATION REPORT: PUNCH LIST /
FINDINGS

1. CAD Weld of Grounding System Test Pit – 6/19/23


2. Body ground of MVSG & Battery Bank – 6/15/23
3. Torque of all Bolts – 6/14/2023
4. Seal all cable entry – 6/15/23
5. Provide support for rubber mat for 2.4kv MVSG – 6/15/23
6. Cable tagging @ 2.4kv MVSG protection relay cables – 6/20/2023
7. Label of 34.5kv MVSG Common wires of Protection Relay – 6/20/23
8. Separate 2.4kv XLPE grounding wires connection to grounding bus bar – 6/15/23
9. Base cement of Battery Bank – 6/15/23
10. Rectify dent at the back of 2.4kv MVSG Panel – 6/16/23
11. Gravel bedding – 6/20/23
12. Touch up paint for all scratches of the MVSG panels – 6/19/23

THANK YOU!