Recovery Plan Pipa Senbal Rev2
Recovery Plan Pipa Senbal Rev2
Project Status
Remaining Work
Schedule Analisis
Mitigasi Plan
Issue Perizinan
Strategi Precom
Jul '22
Jul '23
Jun '22
Jan '23
Jun '23
Apr '22
Ags '22
Sep '22
Okt '22
Nov '22
Des '22
Feb '23
Apr '23
Mei '22
Mar '23
7-Mei
14-Mei
21-Mei
28-Mei
Jul '22
Jul '23
Jun '22
Nov '22
Jan '23
Jun '23
Apr '22
Ags '22
Sep '22
Okt '22
Des '22
Feb '23
Apr '23
Mei '22
Mar '23
7-Mei
14-Mei
21-Mei
28-Mei
100.00%
90.00%
EPC S-Curve 91.46%
Weight
Prev. Prog. Progress This
Progress Accum. Variance
Rencana (Period)
80.00% 0.8055130593
Overall
A Project Management 5.75% 77.95% 77.42% 1.23% 1.23% 79.18% 78.66% -0.53% -0.03%
B Engineering 1.83% 100.00% 100.00% 0.00% 0.00% 100.00% 100.00% 0.00% 0.00%
0.00%
Jul '22
Jul '23
Jun '22
Jan '23
Jun '23
Apr '22
Ags '22
Sep '22
Okt '22
Nov '22
Des '22
Feb '23
Apr '23
Mei '22
Mar '23
7-Mei
14-Mei
21-Mei
28-Mei
C Procurement 51.15% 87.61% 72.12% 3.17% 4.17% 90.78% 76.28% -14.50% -7.42%
D Construction 38.46% 98.55% 64.55% 0.19% 0.10% 98.74% 64.65% -34.09% -13.11%
E Pre Com, Com & Start up 2.81% 3.50% 0.00% 20.24% 0.00% 23.73% 0.00% -23.73% -0.67%
Total 100.00% 89.12% 67.99% 2.34% 2.24% 91.46% 70.24% -21.22% -21.22%
OVERALL SCHEDULE
Terdapat potensi keterlambatan on stream proyek, dari 1 Juli 2023 menjadi 31 Juli 2023 (1 bulan slippage based on Project Master Schedule). Hal ini dikarenakan keterlambatan
konstruksi pipeline dan SM Balikpapan.
EPC Award
DED
HAZID / HAZOP
Procurement (LLI)
Pipeline
Split Tee
USM Metering
LBCV
Valve
Construction
Pre-Commissioning
Commissioning & Gas In
MS 9 Start HDD
Project Master Schedule MS 10 Start TLB Minimum Mechanical Completion
Update Recovery 2km
Procurement Status
No. Target Description Jul ‘22 Ags ‘22 Sept ‘22 Okt ‘22 Nov ‘22 Des ‘22 Jan ‘23 Feb ‘23 Mar ‘23 Apr ‘23 Mei ‘23 Jun ‘23 Concern Status
13/04/ SP3MKL
MS 1 22 7 Mei 23
Milestone Material
MS1+3 PO Ultra Sonic Meter 11 Keydoc: 100% 10 25 ATA 23 Spool & skid
MS 2 Package On Site
bulan PO Fabrikasi: 91,65% (Delivery USM, Spool+Skid On Site) FAT Site SAT
MS1 + 21 3 2 14 ETA 22 Actuator
MS 3 PO Shut Down Valve Keydoc: 100% Function Test selesai, Outstanding SDV 101 SDV-101
4 bulan FAT Site
PO Produksi: 78,81% Test SAT
MS1 + PO Motor Operated 25 Keydoc: 100% 14 ATA On Site
MS 4 6 Mar 22
4 bulan Valve
PO Produksi: 100% (Material on Site) FAT Site SAT
MS1 + 23 14 ETA 16 Actuator
MS 5
4 bulan
PO Control Valve 5 Keydoc:100% FAT CV 1,2,3 Delivery CV 1, 2 & 3
PO Produksi: 89,49% FAT Site SAT
MS1 + PO Line Break Control Actuator
MS 6 4 bulan Valve
28 Keydoc: 90% 14 24 ETA 23
PO Raw Mat: 80,88% (Assembly Valve & Actuator) FAT Site SAT
MS1 + PO Manual Valve On Site
MS 7 4 bulan (Pipeline) 22 Keydoc: 100% 28 30 ATA 27
Shipment
PO Produksi : 100% FAT Site SAT
MS1 + PO Manual Valve
MS 7 10 Keydoc:100% 22 31 ATA 17 ETA 17
4 bulan (Piping) Shipment Delivery
PO Produksi : 100% FAT Site Site (+) SAT
MS1+3 PO Monolithic On Site
MS 8 1 Kdoc: 100% 28 14 ATA 14
bulan Insulating Joint Shipment
PO Prod : 100% FAT Site SAT
Others Critical Material
2. Paket A. On progress assembly Valve dan Keterlambatan proses assembly & testing • Daily monitoring assembly dan percepatan
LBCV Actuator per di Ws Jakarta. Keterlambatan delivery Jkt-Bpn jadwal function test.
B. Rencana function test : 23 Mei 2023 • Pembahasan detail pengiriman Jkt-Bpn
Target Baseline : 24 Mei 2023
Current forecast : 2 Juni 2023
3. Paket A. Spool & Skid telah terpasang Keterlambatan aktivitas integrasi dan Percepatan jadwal pemasangan shelter metering
Metering B. USM, H2 analyser, dan Misc on site, SAT
pemasangan menunggu penyelesain
Shelter Metering dan Control Room Target Baseline : 23 Mei 2023
Current forecast : 5 Juni 2023
4. Material SM Senipah & Balikpapan Slippage target MS-11 : 12 Juni 23 untuk • Daily monitoring kedatangan remaining
Station Status matrl mechanical (100%), Piping ready for Com MS Senipah & material Electrical, Instrument, piping, paling
(80%), instrument (50%), electrical (72%) Balikpapan lambat W4 Mei 2023
• Proses takeover scope pengadaan material &
Progress civil terlambat terkendala Target Baseline : 12 Juni 2023 jasa sipil
pengadaan Matrial & jasa civil akibat Current forecast : 30 Juni 2023
cashlow Sub Kontraktor
Construction Pipeline
Manpower Status
100
Pipa Tertanam Curve Total : 250 orang (17 team TLB,
1 tem auger, 3 team HDD)
80 78.0 78.0 78.0 78.0 78.0
74.0
Spread 1 : 132 orang (11 tim TLB)
64.0
Var : -26.1 km
60 54.0 Spread 2 : 103 orang (5 team TLB,
1 team Auger, 3 team HDD)
318 2410 1962 44.0 51.3 51.6 51.9
7275 40 34.0 44.5 47.8 Spread 3 : 15 orang (1 team TLB)
KM
24.0 32.8 37.6 40.3
Equipment Status Qty
20 11.5 22.12 TLB Actual TLB Plan (PMS) Mesin HDD 7 unit
0.5 12
0 Auger 2 unit
65035 1.1 4.5
7-May
14-May
21-May
28-May
Nov '22
Jul '22
Ags 22
Sep '22
Okt '22
Des '22
Jan '23
Feb '22
Mar '233
Apr '23
Excavator 48 unit
Sideboom 7 unit
Dry Open Cut HDD Auger Swampy OP Crossing Vacum Truck 9 unit
Meter
Km
60 40000
TitiK
Actual 46,5 Km
Remaining 13,6 Km
Remaining 14,3 Km
Productivity 3 hari/titik
pertaminagas www.pertagas.pertamina.com
Highlight Issue Construction
No Perihal Status/Concern Risiko Mitigasi
1. Pipeline Re- A. Kelanjutan Pekerjaan Konstruksi di Kp • Social issue (penolakan warga) di • Pendekatan tokoh masyrakat untuk mediasi.
Route 3- Kp 15 (remaining 14,3 km) Kelurahan teluk pemedas, Kuala Rencana menurunkan 16 tim (siang &
B. Terdapat tambahan 3 - 4 titik Crossing Samboja malam) dgan productivity 350 m/day start
HDD • Diperlukan penambahan resource W3 Mei 23
minimum 16 tim TLB • Penambahan resource dengan takeover
• Diperlukan penambahan mesin HDD lingkup kepada subkon baru
• Penambahan 1 Mesin HDD untuk
penyelesaian khusus area non re-route
2. Pipeline Area Non Kota • Terdapat section area longsor (800 • Mobilisasi mesin HDD dari Area Kota untuk
Non Re- A. Penyelesaian Section Tahura 1,2 km meter) sehingga memerlukan percepatan penyelesain 30 Mei 2023
route Saat ini on progress (5%) tambahan titik HDD dan Boring. • Finalisasi desain dan koordinasi dengan tim
B. Crossing Sungai Merdeka • Belum bebasnya area entry exit land & humas
C. Penyelesaian Remaining Tie in • Lokasi tie in yang cukup terbatas, dan • Penambahan tim (23 Tim) dan evaluasi
D. Perbaikan kualitas reinstatement productivity rendah. kinerja harian
• Komplain dari masyarakat dan • Takeover scope reinstatement dengan bekerja
Pemda Samarinda terkait kualitas dengan konstraktor specialist Reinstatment
reinstatement
Area Kota
Penyelesaian Section Kota Balikpapan (5,2 • Penyetopan oleh pemkot BPN,
km). Saat ini pekerjaan belum dapat bekerja keluhan masyarakat terkait kualitas • Percepatan penyelesaian titik reinstatement
Kembali reinstatement. yang menjadi keluhan dgan takeover scope
• Section padat penduduk dengan reinstatement, menunjuk specialist
utilitas padat
Highlight Issue Construction
No Perihal Status/Concern Risiko Mitigasi
3 Tie in PHM A. Pelaksanaan Hot Tap 42”x16” Keterlambatan Pek Hot Tap dikarenakan • Percepatan Fabrikasi n Pengiriman as per
Area B. Pekerjaan Tie in Box Valve delay fabrikasi Split tee sehingga recovery proc plan page 5
C. Pekerjaan Pipa 20”- 70 meter menggeser aktivitas lainnya (tie in box • Koordinasi dngan pihak PHM untuk finalisai
D. Pekerjaan Pipa 16” -1200 meter, on valve dan penanaman pipa 20”) desain, procedure dan work permit
progress clearing & Grading. Target • Penyediaan Tim dedicated area Tie in PHM
penyelesaian 8 Juni 2023
4. SM Senipah A. Realisasi progress 34% dari rencana Potensi tidak tercapainya Milestone (M- • Percepatan penyelesaian dengan melakukan
100% (delay 66%) akibat adanya 11) Ready For Commissioning SM takeover scope pengadaan matril civil dan
dispute scope dan kondisi cashflow Senipah electrical & instrument
subkontraktor yang terkendala • Penambahan resource dan jam kerja pek
B. Keterlambatan Civil Work (Shelter Baseline : 12 Juni 23 civil, piping, & electrical instrument
Metering, Control Room) Current Forecast : 18 Juni 23 • Monitoring critical activity : fabrikasi spool,
C. Keterlambatan Mech Work (8 of 13) shelter metering, control room untuk
D. Keterlambatan Piping (1461of 3840) kelanjutan pekerjaan integrasi equipment e&i
E. Belum mulainya pek E & I • Menjalankan skema MC dan partial
commissioning
5. SM A. Realisasi progress 55% dari rencana Potensi tidak tercapainya Milestone (M- • Percepatan penyelesaian dengan melakukan
Balikpapan 100% (delay 45%) akibat kondisi 11) Ready For Commissioning SM takeover scope pengadaan matril civil dan
cashflow subkon yang terkendala Senipah electrical & instrument
B. Keterlambatan Civil Work (Shelter • Penambahan resource dan jam kerja pek
Metering, Control Room, Closed drain, Baseline : 12 Juni 23 civil, piping, & electrical instrument
Open drain Current Forecast : 30 Juni 23 • Per skema MC dan partial commissioning
C. Keterlambatan Mech Work (6 of 13)
D. Keterlambatan Piping (1413 of 3840)
E. Belum mulainya pek E & I
F. Tie in Jalur NG 20” to FC RU V
G. Tie in Jalur Flare 8” Eksisting
Schedule SM Senipah
Deskripsi Mei Juni Juli
W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
Civil Work
Under Ground Open Drain;
Above Ground
Ctrl Room Roofing, Wall, rise floor, window
Shlter Mtr
Erection
Mechanical 5 unit
Piping
Shop Weld 1461 of 3291 (44%)
Field Weld Remaining 676 dia inch
E&I
Install MV Tie in Power
Elec. System Tray, Puling
Field Instr. Install PI, PG,
Wiring
Precom
Station Section SAT Equip, Hydrotest, Loop Test,
Function Test
Schedule SM Balikpapan
Deskripsi Mei Juni Juli
W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
Civil Work
Under Ground Closed & Open Drain;
Above Ground
Ctrl Room Roofing, Wall, rise floor, window
Shlter Mtr
Erection
Mechanical 4 unit
Piping
Shop Weld 1880 of 3268 (57%)
Field Weld 1152 dia inch
Natural Gas 180 of 4470 dia inch
Productivity :
- Piping station : 20 DI/welder/day
- Piping NG : 180 DI/day
pertaminagas www.pertagas.pertamina.com
STATUS LAHAN & PERIZINAN
No Perihal Status/Concern Tindak Lanjut Construction
Target
1. Perizinan Tahura Persetujuan pelaksanaan kerja sama dari Draft perjanjian antara KPB, Dinas Kehutanan Prov dan 8 Mei 2023
KSDAE KLHK telah terbit per 27 Mar 23 Ditjend KSDAE KLHK telah disusun, Telah terbit SK
pendampingan sebagai dasar pelaksanaan konstruksi. Start (LBCV 1-
8 mei 23 dengan durasi selama 22 hari. LBCV2)
2. Perizinan BUJT KP 32 Surat KPB perihal Permohonan Izin Mendorong pihak Pgasol untuk melakukan Langkah 15 Mei 2023
Pemanfaatan Rumija Tol telah terbit per 28 Mar percepatan dan pendampingan intesif melibatkan pihak
2023 Land PTG, dan KPB. (LBCV 2-
Selanjutnya Pgasol akan menjalankan proses Diperlukan lampiran BA Survey untuk upload ke OSS. LBCV3)
pengajuan, estimasi 2-3 bulan Meeting Pembahasan Mou 18 Mei 23
3 Re-route Tol IKN Kp 64 Meeting dengan BBPJN dan kontraktornya • Secara prinsip diperbolehkan melakukan konstruksi 14 Mei 2023
telah dilakukan pada 4 Mei 2023, beberapa terleih dahulu pararel proses pembebasan lahan
status lahan ada yg belum dibebaskan • Agenda survey dan pemasangan patok jalur pipa gas
Tidak terdapat anggaran terkait box culvert dengan mengindari bangunan eksisting. (LBCV 4-
untuk desain pelindung pipa Pertagas • Surat notifikasi kepada BBPJN untuk desain proteksi LBCV5)
pipa.
4 Lahan LBCV 4 Lokasi sudah ditentukan, saat ini dalam proses • Ttd notaris sudah on progress pengajuan PR untuk W2 Mei 2023
appraisal KJPP pembayaran DP 50% sewa ke pemilik.
Rencana serah terima mundur dari di w4 April • Pararel untuk bisa dilakukan finalisasi desain dan (LBCV 4-
2023 menjadi W4 mei 2023 pekerjaan survey/soil untuk percepatan pekerjaan LBCV5)
5 CA with Mubadala Pembahasan draft Perjanjian CA antara PTG & • Percepatan pembahasan, dengan target penyelesaian 3 June 2023
Mubdala sebelum libur lebaran.
• Draft sudah disampaikan Mubadala, dalam tahap
finalisasi. Saat ini sirlulir ttd kepada pihak (SNP-LBCV 1)
pertaminagas www.pertagas.pertamina.com
PARTIAL PRE-COMMISSIONING
0,00% Keterangan
TIE IN HOT TAP CC : Construction Completion
33,69%
TIE IN RDMP
COMPLETION
NOTICE DICIPLINE
PIPING
COMPLETION
NOTICE DICIPLINE
CIVIL
1. REPORT
COMPLETION COMPLETION MC
SYSTEM SUB-SYSTEM INSPECTION
NOTICE DICIPLINE NOTICE SYSTEM
SENIPAH PIG LAUNCHER 2. TESTING
MECHANICAL SUB-SYSTEM CERTIFICATE
3. PUNCHLIST
COMPLETION
NOTICE DICIPLINE
ELECTRICAL
COMPLETION
NOTICE DICIPLINE
INSTRUMENT
2022 2023
OBJECTIVES + GOALS JUL AGS SEP OKT NOV DES JAN FEB MAR APR MEI JUN JUL
Plan Pipa Tertanam (km) 1.9 9.9 18.3 29.1 39.0 49.8 58.5 66.8 75 79.2
Aktual Pipa Tertanam Non-reroute (km) 1.2 5.1 13.2 23.4 32.8 37.6 40.3 44.5 44 47.5
Total Pipa Tertanam 1.2 5.1 13.2 23.4 32.8 37.6 40.3 44.5 47.8 51.3
Deviasi -0.7 -4.8 -5.1 -5.7 -6.2 -12.2 -18.2 -22.3 -27.2 -27.9
Lahan Tersedia 28,6 28,6 59.7 59.7 59.7 61 79.2 79.2 79.2 79.2
As Built Schedule 6
SC
Recovery Construction Pipeline R1
R2 R3
Recovery Precomm Precom 12
STASIUN SENIPAH
MS Milestone Due Date Status No Description Progress Manpower Status
MS11 Station Ready for Operation 12-06-23 Civil Work 1 Soil improvement 75.00% Total : 52
2 Foundation Pig Launcher 99.50%
PMT: 14
3 Foundation Metering shelter 83.90%
Civil Team : 27
4 Foundation Lighting Pole 97.00%
Piping Team : 11 (3 welder)
5 Foundation Closed Drain Drum 99.80%
DI
3000 2750.0 2 PO Valve tie in 4 Oct 22 A 100%
2500 2000.0 Actual
1500.0 3 PO Gasket & Nut 6 Jan 23 A 100%
2000
Piping (1445 of 3840 DI) 1500 Plan
1000.0 4 Split Tee+Valve MoS Mei 23 50%
Fabrication 1000 500.0 1445.0
1335.01413.0
Progress Cut Off 14 Mei 23 500 846.0
496.0
E&I MS-11 0 208.0 296.0
696.0 5 Mock Up Mei 23 0%
Rencana 100%
7-May
14-May
21-May
28-May
5-Mar
12-Mar
19-Mar
26-Mar
Feb '23
Apr'23
6 Hot Tap Mei 23 0%
Realisasi 33,96% 14 May 23 Precm Gas In
7 Comm & Gas In Jul 23 0%
Site Prep
14000 Fabrikasi Pipa No Deskripsi Target Prog.
12000 100
Civil 10044.0 10044.0 1 PO Valve TP-002 10 Ags 22 A
Continue Metering & Equipment Foundation %
10000
DI
Mechanical 8000 2 PO Valve TP-007 7 Feb 23 A
100
Install Pig Receiver, Gas Receiver & Filter (3 of 11 unit) 5900.0 %
6000
Piping 2002.0 100
Line 20” & 8” &Fabrikasi 4000 1582.0 3 MoS Pipe 20” 6 Nov 22 A
(2002 of 10444 DI) 1400.0 %
Progress Cut Off 14 Mei 23 2000180.0 264.0 1065.0 Actual Plan
E&I 0 4 MoS Pipe Fitting 12 Apr 23 A
100
Rencana 100% MS-11 %
14
21
28
7-May
Mar ...
Feb '23
Apr '23
Realisasi 55,47% 14 Mei 23 Precm Gas In 5 Piping Install On Progres 5%
Control Room Found. Gas Metering Found. ShelterMetering Found. Gas Filter Install Gas Receiver Security Pos
- Pondasi Co2 snuffing 15Apr - Fab. piping 5May (139 of 415 DI)
- Pondasi Vent KO pot 15Apr (100%) - Piping test package 10May
- Install CO2 snuffing 26Apr - Leak test 14May
Vent - Install Vent KO Pot 26Apr - MC Sub-System 21May
PID-005
Pondasi 0% - Wall 3Apr (100%) - Fab. piping 5May (64 of 209 DI)
Close Drain - Install CDD 15Apr - Piping test package 10May
PID-004 - Leak test 15May
- MC Sub-System 21May
Pondasi IA receiver 100% - Pondasi air compressor 10Apr (100%) - Fab. piping 5May (4 of 195 DI)
- Pondasi air dryer 10Apr (100%) - Piping test package 10 May
Instrument & utility - Install air receiver 12Apr - Leak test 15 May
air system - Install air compressor 26Apr - MC Sub-System 21 May
PID-006 - Install air dryer 26Apr
Pondasi 100% - Install pig launcher 7Apr (100%) - Piping test package 7May
Pig Receiver - Fabrikasi piping 28Apr (0 of 483 DI) - Leak test 14May
PID-001 - MC sub-system 21May
Pondasi DST & EDG 100% - Fabrikasi platform 10Apr - Fabrikasi piping 7may (69 of 128 DI)
Diesel Oil & EDG - Install DST 15Apr - Piping test package 14May
PID-009 - Install EDG 15Apr - Leak test 21May
Subsystem Timeline
Maret April Mei Juni Juli
Cut off 7 Mei 2023 2023 2023 2023 2023 2023
Install water tank 30 Apr - Fabrikasi piping 5may (16 of 215 DI)
Utility water - Piping test package 14May
PID-010 - Leak test 21May
- MC Sub-System 28May
Pondasi control room 100% Control room 30Apr (Kolom, Roof, - Security post 14May - Access road 5 Jun
Dinding, Pintu, Jendela) - Flag pole 21May - MC Sub-System 5 Jun
Building - Wind Shock 21May
- Fence & gate 21May
- ICSS 14May
- LDS 21May
Instrument & - CCTV 21May
telecom package - Scada 21May
- MC Sub-System 28May
- Pondasi 100% - Install pig launcher 7Apr - Piping test package 14May
Pig Launcher - Fabrikasi piping - Leak test 21May
PID-003 - MC sub-system 28May
Pondasi IA receiver 100% - Pondasi air compressor 14Apr - Fabrikasi piping 7may
Instrument & utility - Pondasi air dryer 14Apr - Piping test package 14May
air system - Install air receiver 7Apr - Leak test 21May
PID-007 - Install air compressor 28Apr - MC Sub-System 28May
- Install air dryer 28Apr
Pondasi DST & EDG 100% - Fabrikasi platform 10Apr - EDG shelter 7May
- Install DST 15Apr - Fabrikasi piping 7may
Diesel Oil & EDG - Install EDG 15Apr - Piping test package 14May
PID-008 - Leak test 21May
- MC Sub-System 28May
Subsystem Timeline
Cut off 02 April 2023
Maret April Mei Juni Juli
2023 2023 2023 2023 2023
- Install water tank 10May
- Fabrikasi piping 7may
Utility water - Piping test package 14May
PID-009 - Leak test 21May
- MC Sub-System 28May
Pondasi control room 100% - Roof control room 14Apr - Control room building 7May Access road 5jun
- Security post 14May
- Flag pole 28May
Building - Wind Shock 28May
- Fence & gate 28May
- MC Sub-System 28May
- ICSS 28May
- LDS 28May
Instrument & - CCTV 21May
telecom package - Scada 28May
- MC Sub-System 28May
Entry Exit Exit Entry Exit Entry Entry Exit Exit Entry
DDW45 A V C430 V C430 Goodeng DDW40
171 179 441 305 176
10 Apr’23 15 Apr’23 21 Apr’23 15 May’23 4 Mar’23
KP 70+264 KP 70+435 KP 70+435 KP 70+614 KP 70+626 KP 71+067 KP 71+125 KP 72+430 KP 71+601
KP 71+425
Tanah Ruko Ruko Sebelah Sebelah Zipur Zeni Toko Sepatu Toko Sepatu Kopi
Kosong Depan Pom Fotocopy Makam Makam Mantan
Bensin Reamer 28”
Entry Exit
DDW40
149
17 Feb’23
KP 71+604 KP 71+753
Kopi
Jatim Raya
Mantan
Update tgl 30 Apr’23
SCHEMATIC HDD KOTA
Entry Exit Entry Exit Exit Entry Entry Exit
Exit Entry DDW45 B V C430
DDW40 DDW40 DDW45 B
103 220
187 120 100
4 Apr’23 31 Mar’23
12 Apr’23 29 Mar’23 15 Apr’23 KP 72+864
KP 72+341 KP 72+453 KP 72+556 KP 72+644
KP 71+987 KP 72+174 KP 72+221 KP 72+350 KP 72+450
Bakwan Mebel Kayu Paldam
Toko Bunga Pagar Hijau Pagar Hijau Cheng Cheng Global Com
Cuci Mobil
Reflexi Malang
Wakanda
Mesin Rusak Pullback,done
Entry Exit Entry Exit Exit Entry Exit Entry Entry Exit
F RX40 DDW40 G 5800
V C430
293 293 161 300
157 29 Mar’23
3 Mar’23 4 Feb’23
30 Jan’23 15 Feb’23 KP 74+100
KP 72+888 KP 73+181 KP 73+636 KP 73+797 KP 73+800
KP 73+243 KP 73+415 KP 73+432 KP 73+589
TK Pagar Seng Pagar Seng Ruko sebelah
Paldam Kelurahan T. Sampah Sebelah Depan TK
Rajawali
Indomaret Masjid
Stuck, di
string 9 of 13
Entry Exit Entry Exit Entry Exit Exit Entry
V 220 V 220 V 220 V 220
Note : Total HDD Kota 25 Titik
477 477 290 527
12 may’23 3 Apr’23 22 Nov’22 31 Des’22 Sudah dikerjakan, 14 Titik
KP 74+135 KP 74+391 KP 74+415 KP 74+601 KP 74+656 KP 74+946 KP 74+135 KP 75+651 On Progres, 1 Titik
Ruko sebelah ATM ATM SPBG SPBG Scrap Scrap Station Belum Dikerjakan, 8 Titik
Rajawali Mandiri Mandiri Rapak Rapak RU RU BPN Berhenti, 2 Titik