PROJECT DETAILS
Particulars (Rs in Cr) Sept 2023 Oct 2023 Nov 2023 Dec 2023
Actual 0
Variance 0
Sr. Description Site Excavation PCC Footing Shear wall Plinth Beam
no. Cleaning upto plinth
level
5. Barrrack 0% 0% 0% 0% 0% 0%
6. Multipourpose
Hall 0% 0% 0% 0% 0% 0%
7. Shops 0% 0% 0% 0% 0% 0%
8. Infrastructure
0% 0% 0% 0% 0% 0%
MPR Of Sept and Plan for Oct
Activity Unit Total Qty Plan –Sept’23 Achieved- Sept- Plan –
23 Oct’23
Excavation for A Building cum 5071 3300 3300 1771
PCC for A building cum 44 44 0 44
Footing For A building cum 382 382 0 382
Shear wall upto plinth level for A cum 145 145 0 145
Building
Excavation for B Building cum 4200 4200
PCC for B building cum 44 44 0 44
Footing For B building cum 382 382 0 382
Excavation for C Building cum 4200 4200