Professional Documents
Culture Documents
2-11 Process Constraint Identification (ABBE-R031104)
2-11 Process Constraint Identification (ABBE-R031104)
2-11 Process Constraint Identification (ABBE-R031104)
Identification and
Time Trap Analysis
Activities Tools
• Identify Potential Root Causes • Process Constraint ID and Takt Time
Analysis
• Reduce List of Potential Root Causes
• Cause & Effect Analysis
• Confirm Root Cause to Output Relationship
• FMEA
• Estimate Impact of Root
• Value StreamCauses
Mapping on Key Outputs
• Value of Speed (Process Cycle
• Hypothesis Tests/Conf. Intervals
• Prioritize Root Causes
Efficiency/Little’s Law)
• Operational Definitions
• Simple and Multiple Regression
• Complete Analyze• Data
Gate Collection Plan
• Statistical Sampling
• Measurement System Analysis
• ANOVA
(MSA)
• Gage R&R • Components of Variation
• Kappa Studies
• Control Charts • Conquering Product and Process
• Histograms Complexity
• Normality Test
• Process Capability Analysis • Queuing Theory
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 2
Learning Objectives
Learn the difference between a capacity constraint and a time trap
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 3
Lean Definitions
The following terms are used frequently to quantitatively describe the output of a process and the critical process steps:
Capacity: The maximum amount of product (output) a process can deliver (produce) over a continuous period of time
Example: The capacity of our process is 120 mortgage applications per day
Takt Rate: The amount of product (output) required by the customers over a continuous period of time
Example: Our customers submit a Takt Rate of 130 applications per day
Time Trap: Any process step that inserts delay time into a process
Example: Our property appraisers evaluate 120 properties per day, all other process steps can process 145 applications per day
Constraint: A time trap that is unable to produce at the exit rate required to meet customer demand (internal or external takt
rate)
Example: Our property appraisers can only evaluate 120 properties per day, but customer demand is currently 130 applications per day!
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 4
What Is a Time Trap?
Time traps insert delay time into a process
Time traps can create long lead times, large downstream inventories, large WIP,
Time traps are principally due to long setup times, machine or human downtime, or quality problems
Time traps can change over time (monthly, weekly, even daily) based upon product mixes or special causes
(new product introductions, special orders, etc.)
Time traps can be caused by physical problems (such as process flow, personnel availability, part/supply
shortages, equipment availability, etc.)
Time traps can also be caused by non-physical problems (such as procedures, morale, unsafe work
environments, lack of training, etc.)
There is ALWAYS a time trap in a process!
This is a
Time Trap!!
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 5
What Is a Constraint?
Constraints limit the output capacity of the process (sometimes called
bottlenecks)
Constraints have less capacity than the prior or subsequent steps/operations
Constraints are time traps that cannot meet customer demand (a
constraint is ALWAYS a time trap, but a time trap may not be a constraint!)
Constraints can change over time (monthly, weekly, even daily) based
upon product mixes or special causes (new product introductions, special
orders, etc.)
This is a
Constraint!!
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 6
How Are Time Traps Created?
Poor process flow
Machine capacity Distance
People
Lack of parts Safety concerns
Transportation methods (cranes, foot, etc)
Handoffs
Large batch sizes
Poor scheduling
Operational deficiencies
Product mix
Setup
Scrap (low yield)
Downtime
Excessive WIP
Rework
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 7
The Importance of Time Traps
The most limiting time trap of this process is here.
If we do not understand where the time traps exists, we may end up focusing our project on the wrong process activity.
Activity 1 2 3 4 5 6 7
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 8
The Importance of Constraints
This time trap is also a constraint…
Demand
Unless we attack the constraint, we will continue to be unable to meet customer demand.
Activity 1 2 3 4 5 6 7
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 9
Black Belt Project Focus
Time Traps or Constraints
Time Traps
Focus on time trap identification if the goal of your Black Belt project is to improve efficiencies
( in inventory, lead time, output rates, etc.)
Constraints
Focus on constraint identification if the goal of your Black Belt project is to increase capacity
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 10
Constraint
Identification
Takt Rate Analysis
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 12
Takt Rate Analysis
Constraint
Takt Rate = Identification
Customer Demand Main Production Board: Operation 3
The Constraint is the operation or process Yesterday: 443 Units 1.61 Units/ labor hr
Today:
that produces below the Takt Rate
445 Units 1.62 Units/ labor hr
Hour Takt Rate Actual +- Diff Comments
8-9 AM 60 59 -8
10-11AM 60 61 -4
2-3 PM
60
45
58
44
-3
-4
Production Time Available 3-4 PM 30 29 -5
Step 1: Write in the number of units produced and the units/hour from yesterday
Step 2: Write in the number of units to produce and the units/hour goal for today,
confirm the takt rate for each hour (account for breaks and lunch)
Step 3: Each hour, write in the number of units produced in the previous hour
Example Step 4: Write in the cumulative difference between the scheduled units
produced and the actual units produced
Step 5: Write in any comments (frame welder down, no glass) as a reason for
meeting or not meeting the takt rate.
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 13
Constraint vs. Time Trap
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 14
Constraint Exercise #1:
Great XYZ Company
We are the owners of the Great XYZ Company and need to know the following to maximize production
capabilities. The customer demand appears to be high compared to our production abilities. What do you
think?
1. What is the net operating time (hours per week)?
2. What is the factory takt rate (units/hour)?
3. What is the time trap in the process? What is its’ capacity (in units per hour)?
4. Is the time trap a constraint (can it produce to the takt rate – Yes/No)?
5. If an additional piece of equipment is purchased to increase capacity at the time trap, what is the new capacity?
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 15
Constraint Exercise #1:
The Process
Operation 1 Operation 2
Ship
Operation 3 Operation 4
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 16
Constraint Exercise #1:
Basic Operating Data
The company has a customer demand of 16,000 units per week.
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 17
Constraint Exercise #1:
Operating Capacity
Operation Capacity/Mach # Machines
Operation 1 60 units/hr 3
Operation 2 25 units/hr 5
Operation 3 35 units/hr 5
Operation 4 80 units/hr 2
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 18
Results Constraint Exercise #1:
Great XYZ Company
1. What is the net operating time (hours per week)?
__________________________________________
2. What is the factory takt rate (units/hour)?
__________________________________________
3. What is the capacity time trap in the process? What is its’ capacity (in units per hour)?
__________________________________________
4. Is the time trap a constraint (does it take longer than the takt rate – Yes/No)?
__________________________________________
5. If an additional piece of equipment is purchased to increase capacity at the time trap, what is the new capacity?
__________________________________________
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 19
Constraint Identification
Load Factor Report Analysis
For environments where the
constraint changes daily due to
product mix (i.e. a job shop)
However, in some instances, the constraint shifts frequently depending on the product mix
Different product mixes may have different processing times at each operation, or they may have
different operation routings. This is often the case in job shops
In these types of environments, it is necessary to identify the constraint each day as the
production mix changes
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 21
Load Factor Report Analysis
The Load Factor Report: Load Factor
Report
Provides visibility to the constraint operations that are
loaded over capacity
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 22
Load Factor Report
The Load Factor Report has the following information:
Work Center – Operation number assigned to process units
Capacity – Productive hours per shift (hours)
Load – Current queue for operation (hours)
Load Factor – Factor calculated by dividing load (queue) by capacity of the operation
Target Load Factor – Targeted load per machine expressed in days
Deviation – Over (+) or Under (-) the target Load Factor expressed in days
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 23
Example:
Load Factor Report
Load Factor Report
Operation Capacity Load Factor Target Deviation
Hours Hours Days Days (+/-)
261100 6.5 51.3 7.89 1 6.89
261102 6.5 5.9 0.91 1 -0.09
261400 6.5 5.1 0.78 1 -0.22
261406 6.5 0.6 0.09 1 -0.91
Operation #261100 is loaded over capacity, therefore a constraint
Goal – eliminate constraint #261100 by reducing the Factor Days to be less than or equal to the
Target Days. This is accomplished by either:
Off-loading work to another area
Increasing capacity at this operation (more people, time, equip.)
The Load Factor Report is created prior to the beginning of the working shift
A flag can then be placed at the constraint operation for visibility
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 24
Time Trap
Identification
Time traps impact efficiencies by requiring more inventory, more equipment, more
people, more material, and more time in order to meet customer demand
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 26
Where Are the Time Traps?
Where the Inventory Stacks Up?
Careful!
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 27
Remember ACE Manufacturing?
Where Was the Time Trap?
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 28
Pareto Principle and Time Traps
Applying the Pareto Principle to time traps means that in most environments, 80%
of the inefficiency or delay is caused by 20% of the steps in the process
Turning this around then states that making improvements to 80% of the steps in
the process has little to no impact on efficiency or speed
Therefore it is critical that our Black Belt projects are focused on the time traps
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 29
Time Trap Identification
Workstation Turnover Time
For example, how do setup times, processing times, and batch sizes affect individual workstations?
We can use some fundamental mathematics that relate these parameters in a term called Workstation
Turnover Time (which is analogous to inventory turns), to calculate the time trap.
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 31
Workstation Turnover Time
(WTT)
WTTk = [(Setup Time i ) + (Process Time i x Batch Size i )]
WTT is the Workstation Turnover Time - the amount of time to
setup and run all parts at a given workstation once.
Where k = 1 to number of workstations in the process
Where i = 1 to n part numbers routed across that workstation
We will develop this equation later in the course (to help us
analytically size batches), but it is important here too.
To determine which workstation is the critical time trap, simply
calculate WTT for each workstation in the process – the station
with the longest WTT is the critical time trap
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 32
Process Constraint Identification:
Understanding WTT
Workstation Z processes three parts: A, B, C
Scenario 1: If the parts are run sequentially (one after another), then:
WTT for workstation Z is defined as:
Setup A Process A Setup B Process B Setup C Process C Setup A Process A Setup B Process B Setup C Process C
WTTZ WTTZ
Setup A Process A Setup B Process B Setup A Process A Setup C Process C Setup A Process A Setup B Process B
WTTZ
WTT for workstation Z is the same in both scenarios.
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 33
Workstation Turnover
Time Example
Use the data given below to solve for WTT=[(Setup Timei ) + (Process Timei x
Batch Sizei)]
WTT = [(SetupA)+(Process TimeA x Batch SizeA) + (SetupB) + (Process TimeB x Batch SizeB)]
[(4 hrs) + (.01 hrs/unit x 1000 units) + (4 hrs) + (.01 hrs/unit x 1000 units)
WTT = [(4 hrs) + (10 hrs) + (4 hrs) + (10 hrs)]
WTT = 28 hrs
A B C
Setup A 4 hrs
Setup B 4 hrs
Process Time A 0.01 hrs/unit
Process Time B 0.01 hrs/unit
Batch Size A 1000 units
Batch Size B 1000 units
Demand A 35.71 units/hr
Demand B 35.71 units/hr
Available hours 40 hrs/week
WTT = ?? hrs
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 34
WTT Example Explanation
Given the workstation data of setup time, process time, and batch size, the WTT in this example is 28 hrs.
This 28 hour WTT is a reflection of the workstation’s inflexibility. Because of the setup time and required batch size,
this workstation is injecting delay time into the process.
Calculating WTT for each workstation in the process allows us to find the workstation that is injecting the most delay
time. This workstation is the critical time trap.
In the future, we will learn how to analytically size batch sizes given workstation data such as setup time, scrap, rework,
downtime, etc. As batch sizes are changed due these parameters, WTT will change. So ultimately WTT is impacted by
all of these parameters as well.
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 35
Time Trap
Identification
Excel Exercise
Process Constraint ID & Time Trap Analysis © 2003 ALCAN - George Group Curriculum Slide 37