Professional Documents
Culture Documents
Pile Foundation Part IV
Pile Foundation Part IV
Dr. Nu Nu Win
Professor
Department of Civil Engineering
Yangon Technological University
05/06/2024 1
Pile Load Tests
Pile load test: (a) using kentledge, (b) using reaction pile,
• In Figure a, a kentledge, consisting of heavy weights, is
required to hold the reaction beam in place, and the
hydraulic jack is used to jack against the beam and hence
apply the pile load.
• In Figure b, two reaction piles, located far away from the
test pile, anchor the horizontal reaction beam to the
ground.
Pile load test: (a) using kentledge, (b) using reaction pile,
• The loads are applied in increments as specified by the
relevant standards, with sufficient time between the
load increments. Generally, the piles are loaded well
beyond their working loads (e.g., 2 times).
• On reaching the maximum load for the test, the pile is
unloaded in steps. The dial gauges measure the
settlement of the pile head where they are mounted.
This is the total or gross settlement, denoted as
• Due to the compressibility of the pile material, the pile
it self undergoes some elastic compression, known as
the elastic shortening or elastic compression of the
pile, denoted here as .
• The net settlement of the pile is the settlement of the pile
point, which is slightly less and is denoted as . Therefore, at any
load,
(a) Remolded or compacted zone around a pile driven into soft clay;
Figure (b) nature of variation of undrained shear strength () with time
around a pile driven into soft clay
• This results in a reduction of undrained shear strength,
(Figure :b). With time, the loss of undrained shear strength is
partially or fully regained.
• The time lapse may range from 30 to 60 days For piles driven
in dilative (dense to very dense) saturated fine sands,
relaxation is possible.
• Negative pore water pressure, if developed during
pile driving, will dissipate over time, resulting in a
reduction in pile capacity with time after the driving
operation is completed.
• At the same time, excess pore water pressure may
be generated in contractive fine sands during pile
driving. The excess pore water pressure will
dissipate over time, which will result in greater pile
capacity.
• Several empirical relationships have been
developed to predict changes in pile capacity with
time.
An excellent review of most of the works has been given by
Sawant et al. (2013). Figure shows the load test results of a
20 m long concrete pile (406 mm x 406 mm) embedded in
sand. Using Davisson’s method, determine the ultimate
load Qu. Given: Ep = 30 x kN/.
Elastic Settlement of Piles
• The settlements in piles are relatively low when
compared to their shallow foundation counterparts.
• Under working loads with a factor of safety on the
order of 2–3, the settlement is about 1% of the pile
diameter.
• Two methods of estimating the pile settlements are
discussed in this section. The first one is a simplified
method based on what was proposed by Poulos and
Davis (1974).
• The second one is a more rational and rigorous method
proposed by Vesic (1977).
• They are both based on elastic analysis
METHOD OF POULOS AND DAVIS
05/06/2024 50