GSS Project Update 01-04-2024
GSS Project Update 01-04-2024
1
P R O J E C T S U P D AT E
2
P R O J E C T S U P D AT E
Part 1 - Domestic Arrival Passenger Exit Route
Milestone (Update)
-
-
-
Procurement Strategy
3
P R O J E C T S U P D AT E
Part 2 - Staff and Service Entrance Part 2 - Staff and Service Entrance
Submittal / MTS Date Action By Remarks
Architecture
Pt.2 Staff and Service Entrance
drawing
HVAC drawing
Light have been installed in site
Gypsum Board
EMT and Accessories Shifting at Site
Procurement Strategy 4
P R O J E C T S U P D AT E
Part 3 - Domestic Security Check Expansion
Submittal / MTS Date Action By Remarks
Architecture
PT.3 Domestic Security Check
Expansion drawing
ARCH drawings have been submitted
Waiting for approvals
5
P R O J E C T S U P D AT E
Part 4 - Modification of Immigration Offices and Airport Clinic at International Arrival
Support Needed
Project Phases Start Finish Duration (Days) Progress
Immigration Office Modification 13-Apr-24 6-Jun-24 54 %
6
P R O J E C T S U P D AT E
Support Needed
Public address
Project Phases Start Finish Duration (Days) Progress
HVAV as built drawing
Non-security Deportees Lounge 13-Apr-24 6-Jul-24 54 %
7
P R O J E C T S U P D AT E
Architecture drawing
Pt.6 International Security Check
Expansion
8
P R O J E C T S U P D AT E
Architecture drawing
PT.7 Prayer Rooms