Government Security Support Project - GSS

1
P R O J E C T S U P D AT E

Government Security Support Project

Project Phases Start Finish Duration (Days)


Engineering + mobilization 1-Feb-24 13-Mar-24 41

Staff and service Entrance 16-Mar-24 9-May-24 54

Non-security Deportees Lounge 13-Apr-24 6-Jul-24 54

Immigration Office Modification 13-Apr-24 6-Jun-24 54

Domestic hall expansion 22-Jun-24 5-Sep-24 75

Domestic Arrival Exit Route 17-Aug-24 31-Oct-24 75

International Security Check Expansion 7-Sep-24 28-Nov-24 66

Prayer Room 7-Sep-24 29-Oct-24 52

Testing, Commissioning & Handover 30-Nov-24 26-Dec-24 26

2
P R O J E C T S U P D AT E
Part 1 - Domestic Arrival Passenger Exit Route

Submittal / MTS Date Action By Remarks

PT.1 Domestic Arrival Passenger Exit Route


Architecture drawing

Milestone (Update)
-
-
-

Procurement Strategy

Project Phases Start Finish Duration (Days) Progress Required Support


Domestic Arrival Exit Route 17-Aug-24 31-Oct-24 75 %

3
P R O J E C T S U P D AT E
Part 2 - Staff and Service Entrance Part 2 - Staff and Service Entrance
Submittal / MTS Date Action By Remarks

Architecture
Pt.2 Staff and Service Entrance
drawing
HVAC drawing
Light have been installed in site
Gypsum Board
EMT and Accessories Shifting at Site

EMT works and first fix approximately


VSS drawing
completed
Paint
Conduct final survey before starting gypsum
board works. Tiles
RSAF Signed MOM and Agreed to New
Layout Lights
EMT (1st fix)
Data cables
Electrical cables
Support Needed
Project Phases Start Finish Duration (Days) Progress
Staff and service Entrance 16-Mar-24 9-May-24 54 %

Procurement Strategy 4
P R O J E C T S U P D AT E
Part 3 - Domestic Security Check Expansion
Submittal / MTS Date Action By Remarks

Architecture
PT.3 Domestic Security Check
Expansion drawing
ARCH drawings have been submitted
Waiting for approvals

Start work date : SAT 22-Jun-24

Complete work : 75 working day

Project Phases Start Finish Duration (Days) Progress Support Needed


Domestic hall expansion 22-Jun-24 5-Sep-24 75 %

5
P R O J E C T S U P D AT E
Part 4 - Modification of Immigration Offices and Airport Clinic at International Arrival

Submittal / MTS Date Action By Remarks

PT.4 Modification of Immigration


Offices and Airport Clinic at Architecture
International Arrival drawing
Drawings have been submitted for approval.

Support Needed
Project Phases Start Finish Duration (Days) Progress
Immigration Office Modification 13-Apr-24 6-Jun-24 54 %

6
P R O J E C T S U P D AT E

Part 5 - Non-Security Deportees Lounge


Submittal / MTS Date Action By Remarks

PT.5 Non-Security Deportees Lounge


Architecture drawing
Architectural Layout Approved Plumbing Drawing
Fire Protection Layout Under Review VSS drawing
Electrical Drawing
Ceiling Drawing
Floor Plan drawing

Support Needed

Public address
Project Phases Start Finish Duration (Days) Progress
HVAV as built drawing
Non-security Deportees Lounge 13-Apr-24 6-Jul-24 54 %

7
P R O J E C T S U P D AT E

Part 6 - International Security Check Expansion


Submittal / MTS Date Action By Remarks

Architecture drawing
Pt.6 International Security Check
Expansion

Architectural Layout Under Review

Project Phases Start Finish Duration (Days) Support Needed


International Security Check Expansion 7-Sep-24 28-Nov-24 66

8
P R O J E C T S U P D AT E

Part 7 - Prayer Rooms


Submittal / MTS Date Action By Remarks

Architecture drawing
PT.7 Prayer Rooms

Architectural Layout Under Review

Project Phases Start Finish Duration (Days) Support Needed


Prayer Room 7-Sep-24 29-Oct-24 52