Professional Documents
Culture Documents
Preventive Vigilance in Works
Preventive Vigilance in Works
“Just" "Fair"
refers to an action refers to an action that
justified under the treats people as they
circumstances deserve to be treated
Challenge
The challenge before us is
to create an environment in
which the honest can work
fearlessly and the corrupt
are punished promptly.
Central Vigilance
Commission
Central Vigilance Commission (CVC) is an apex Indian governmental
body created in 1964 to address governmental corruptions.
Surveillance
Preventive Punitive
and
Vigilance Vigilance
Detection
Preventive Vigilance
To study and modify procedures if required to
increase transparency and accountability.
To undertake review of regulatory functions to
avoid discretion in decision making.
To educate employees for creating awareness
about rule provisions and simplifying the
cumbersome procedures if required.
To identify gray areas which are prone to
corruptions and unplug them. Also, suggesting
ways for systemic improvement to avoid re-
occurrence.
Preventive Vigilance
To prepare list of Officers of Doubtful Integrity (ODI) (officers
who are found to be lacking in integrity during/ after inquiry).
Monitoring
appointment of IO and Examination/ Recommending any
To check timely issue
PO in RDA cases and Processing of IO’s work for intensive
of penalty order by DA.
to ensures adherence report. examination by CTEO.
of time schedule.
Surveillance
Main Allegations:
1)The date of start of work- 28.08.2018 with
completion period of 60days (SDOC-
27.10.2018).PG Submitted on 23.08.2018.
However, the Contract was terminated on
01.09.2018 without even waiting for the first
milestone, which indicates bad intention of EE.
2) EE forced to use equipment of certain make only.
Facts:
1) Work- Providing and installing of Open
Gym Equipments ( in the Constituency of
CM,Delhi)
2)Tender awarded on 18.08.2018. DOS-
28.08.2018,PG Submitted on 23.08.2018
before
3) Is notice required & reasonable time of notice?
Vigilance
Unit: 4) what was the urgency of terminating the earlier
contract within a span of 1 week after award when the
contractor had already given the BG showing his
earnestness
5) Substantial increase in cost in second call with respect
to 1st call
Pros:
(i)the requisition of this work was received from the office of
Observation of Hon’ble Chief Minister of Delhi. However, from the
Vigilance Unit documents, it is observed that no correspondence from the
client has been made to execute the work on Priority.
regarding “what
was the (ii) In the 2nd call of tender of the said work, the number of days
from the date of issue of letter of Acceptance for reckoning
urgency of the date of start has been kept as 03 days in Schedule ‘F’ of
terminating the the agreement instead of 10 days as mentioned in the
agreement of 1st call, showing some urgency to complete the
earlier contract work at the earliest.
within a span of
(iii)The Executive Engineer, Delhi High Court Civil Division (M-
1 week after 431), PWD, GNCTD has specifically mentioned in their letter
award” dated 24.08.2022 that gym equipment has to be installed on
priority.
Observation of
Vigilance Unit
regarding “what (iv) The Complainant has not submitted the programme chart
was the within 3 days from date of start ,as per the provisions of the
agreement. Moreover, the complainant has not proposed for
urgency of procuring materials from the list of Approved Makes or from
terminating the any other equivalent makes till the termination of the
contract.
earlier contract
within a span of (v) The the contractor has installed 23 nos. of open gym
equipment against the tendered quantity of 24 nos within
1 week after one month of stipulated date of completion
award”
Cons:
The work under Agreement No. 30/EE/DHC(M-431)/2018-19, which
Observation of
was awarded after recalling of the same tender, was also delayed by 110
Vigilance Unit
days. It is observed from the proforma of extension of time granted to the
regarding “what
contractor in recalled tender that out of 110 days, 71 days are due to
was the
non-availability of the site to the contractor.
urgency of
terminating the As evident from the EOT form, initially only 10 out of 24 sites were
earlier contract available to the contractor under Agreement
within a span of No. 30/EE/DHC(M-431)/2018-19. Therefore, it is certain that the same
1 week after number of sites were available for the contractor M/s Deen Dayal
Common Lapses
Execution of Work through spot quotation in the cases also where tender can
be done or calling NIQ through web publicity
Reimbursement of ESI & EPF Contribution not on actual basis
Non withholding of amount due to non achievement of milestone
Testing of materials from non approved outside laboratories
Review of Hindrance Register, Site order book, Cement Register etc. not as
per the provisions of CPWD Works Manual
Delay in Finalisation of Bill
Common Lapses
The authorities preparing, examining and sanctioning extra/substituted items
should ensure proper preparation of nomenclature of items and record specific
reasons to execute them. Casual remarks/reasons like “Required as per site
conditions” or “Required at site” etc should not be recorded(5.11.1(3)) Execution
as per Architectural drawings and structural drawings
Items claimed by the contractor which in the wisdom of the Engineer in Charge
are not admissible for payment, measurements should be recorded without
prejudice for record purposes only under heading “Inadmissible items claimed but
not included in the payment” so that in case it is subsequently decided to admit
the contractor’s claims in DRC/Arbitartion/Court proceedings, there should be no
difficulty in determining the quantities of such work done(5.12.3)
Common Lapses
Following to be
done…..
Aware about the Manual and procedure laid
down
Go through the Agreement so that you can be
aware about the TOR stipulated in the
agreement
Read the items or specifications stipulated in the
agreement
Allow the items only after checking
specifications stipulated in description of
item/agreement
Analyze before taking decision
Following to be
done…..
Keep yourself update with the latest
development
Keep regular monitoring & supervision of work
you are getting executed
Read about the testing procedure of various
items
Systematic inspections by all concerned officers
are essential particularly of those services and
components which are prone to higher wear and
tear and nearing to outlive/outlived their life.
Some Inspiring Quotes
o To enhance Integrity.
o To minimize corruption
Ethical Practices
Example:
‘Do what you say’ and ‘say what you
do’.
Organizational Integrity