Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 30

CONSTRUCTION METHODS &

TECHNIQUES

Ground Improvement Techniques

Some cases
Prof. Sanjay Bhoyar
NICMAR SANJAY BHOYAR
Case-1:
 Improvement of open stack ground
behind 7th cargo berth at Kandla Port
 Area: 250m x 90m
 Ground strata: 20m deep marine clay
 Shear strength = 20kN/m2
 Design load intensity: 50kN/m2
 Pile foundation is impracticable & very
expensive
NICMAR SANJAY BHOYAR
Solution:
Sand Drains & Pre-loading
 Sand drains:
 200 mm dia.
 1.5m c/c
 500 mm thick sand blanket
 Soil Preload
 6m high
 Monitoring for:
 Settlement, &
 Pore water pressure
NICMAR SANJAY BHOYAR
 Pore water pressure stabilized within
6 months
 Pre-load removed
 Shear strength = 45 kN/m2
 Berth # 7 is operational for last 6
years, &
 Open stack ground is performing
satisfactorily

NICMAR SANJAY BHOYAR


Case -2:
 Residential project (Kerala):
 45 acre land
 48 (G+1) independent bunglows
 Amenities
 Site : low lying
 1.2 m fill in place
 Proposed finished GL - 0.8m above
 Soil strata:
 Silty clay
NICMAR SANJAY BHOYAR
Finished GL (0.8m above)

0.00m
Red Earth fill (N=4)
1.20m
Very soft silty clay (N= 1; PI=78%)
6.50m
Soft silty clay (N=2-4; PI=63%)
9.00m
Loose dirty fine sand (N=2-4)
12.50m
Loose clayey sand (N=9)
14.20m
Dense clayey sandy silt (N=30-40)
18.00m
Very Dense clayey sandy silt (N=>100)
22.00m
Weathered rock

NICMAR SANJAY BHOYAR


 Coefficient of consolidation
 Cr = 2 Cv
 Design load = 6.8 t/m2
 Load of fill = 3.8 t/m2
 Structural load = 3.0 t/m2
 Preload: Expected to take > 3 yrs
 Conventional sand drains
 More construction time
 Large amount of labour
NICMAR SANJAY BHOYAR
Solution:
PVDs & Pre-loading:
 Pre-fabricated band drains
 For 95% consolidation within 60 days
 Triangular pattern @ 0.9m c/c
 Preload: 3.0m
 Estimated settlement: 0.9 – 1.2m
 Observed settlement: 0.78 – 0.85m
(90%)

NICMAR SANJAY BHOYAR


NICMAR SANJAY BHOYAR
 Construction of 2 buildings :6 months
 Settlement after construction
 145mm & 80mm
 Acceptable settlement = 40mm
 Settlement stabilized within 15 days
 Uniform settlement due to RCC strip
footing

NICMAR SANJAY BHOYAR


Defect & rectification in GI:
 Settlement = 0.8m
 Effective preload = 2 to 2.2m
 Further increase in finished GL by
0.8m
 Preload removed : 1.4m
 Owner conducted plate load test on
compacted soil at foundation level
 Less settlement

NICMAR SANJAY BHOYAR


 Deficiency in preload: 1.5 t/m2

 Increased Pre-load for remaining


sections of the project
 Settlement during preloading
 0.9 m – 1.0 m
 Settlement after construction
 30 mm

NICMAR SANJAY BHOYAR


Case -3:
 Project: Culverts along Saket- Balkum Road,
Thane
 Size of culvert: 6m x 30m (6 no.)
 Traffic: Heavy
 Design load : 80 kPa
 Site location: Along Thane creek
 Ground profile:
 Top 1m : Filling
 1- 2.5m : Soft clay
 2.5- 6m : Moderately stiff clay
 Below 6m : Weathered rock

NICMAR SANJAY BHOYAR


Solution:
Rammed stone columns:
 Ground Improvement: Stone Columns
 No of SCs: 45
 Diameter: 0.9m
 Depth: 9.0m
 Spacing: 2.0m ; Pattern: Triangular
 Open mandrel driving
 Gravel with 20% sand
 Rammed with 2 ton falling through 1.5m ht
 Top of column is rammed by 4 ton hammer

 Result:
 SBC = 117 kPa (from 48 kPa)

NICMAR SANJAY BHOYAR


Case -4:
Kansai International Airport

NICMAR SANJAY BHOYAR


Key Features
 Located on a biggest man-made islands in
Osaka Bay, Japan
 Constructed cost over $15 billion
 The island of 4 X 1 km, constructed in
around 18m of water, entirely from landfill
 Project Started in 1986
 Opened for flights in 1994
 ASCE named KIA the #2 civil engineering
project of the 20th century, second only to
the Panama Canal

NICMAR SANJAY BHOYAR


Construction of Airport

Stage Activity Time


I Subsurface 1 year
Investigation
II Sea Wall 2 years
Construction
III Landfilling 4 years
IV Terminal 2 years
Construction

NICMAR SANJAY BHOYAR


Subsurface of the Kansai Airport
Foundation

NICMAR SANJAY BHOYAR


Seawall Construction
 Up to 40 ft. above sea level
 Tripod blocks on seaward side for
dissipation of wave energy

NICMAR SANJAY BHOYAR


Seawall After Completion
Seawall
Construction

NICMAR SANJAY BHOYAR


Mechanism of Sand Drains

NICMAR SANJAY BHOYAR


Mechanism of Sand Drains

NICMAR SANJAY BHOYAR


Application of One Million Sand
Drain at KIA

NICMAR SANJAY BHOYAR


Settlement Predictions
 Lack of experience with construction
on deep deposit of clay
 Expected settlement = 6-8 m
 Actual settlement = 9 m (by the end
of island construction in 1990)
 It continued at the rate of 50cm/year

NICMAR SANJAY BHOYAR


What Went Wrong in Predictions?
 Un-conservative estimation of
consolidation settlement
 Wrong estimate of the time required
for completion of consolidation
settlement
 Ineffectiveness of the sand drains in
achieving the required success-100%

NICMAR SANJAY BHOYAR


Coping With The Problem of
Continued Settlement
 Basement of the terminal was lined
with a quarter of a million tons of iron
ore.
 Result: Island sank faster than the
building it is trying to hold
 Installation of hydraulic jacks under
the columns
 Result: No differential settlement
between the columns of entire building
NICMAR SANJAY BHOYAR
NICMAR SANJAY BHOYAR
Learning From Mistakes

 Using actual settlement data obtained


from 1st phase of project
 Analysis of 400-m-deep boring
exploration
 State-of-the-art soil test methods
 Expected Settlement = 18 m

NICMAR SANJAY BHOYAR


Case -5:
Brisbane Inner City Bypass:
 Soil strata:
 1.5- 2m : stiff clay
 10- 12m : marine clay
 Beneath: bedrock

 Phase – I
 Wick drains
 1.5 m spacing
 Grid pattern

NICMAR SANJAY BHOYAR


 Phase-II
 Dynamic replacement stone column
 700mm Diameter ; 5m spacing
 5-7m deep
 Bailer & ramming method
 Material:
 Demolished concrete & rock fill (1m)
 Phase-III
 Granular blanket: 1m
 Dynamic compaction by 10T ponder
 Surcharge material added
 6 months

NICMAR SANJAY BHOYAR

You might also like