Professional Documents
Culture Documents
Sop New Product and Process Development v3 - 1
Sop New Product and Process Development v3 - 1
Sop New Product and Process Development v3 - 1
Date: 16.01.24
Major outline provided by ISO 9001:2015
Inputs are required to adequate, complete and unambiguous for the design and
development process undertaken and any conflicting inputs must be resolved.
Duration
2
Typical Standard Design Process 4- 8 Weeks
Pricing 2 Weeks
Segmental retaining wall
• rapid construction
• horizontal and vertical curvatures
• easy grade changes
• a wide variety of colors, sizes and textures
• no need for a concrete footing
•Some segmental systems use steel or fiberglass pins, clips or
integral lips to create a continuous facing system. Some blocks are
hollow, some are solid. Just about all block systems permit backfill
drainage through the face joints.
Disadvantages of •Segmental block retaining walls can be quite labor-
Segmental retaining intensive. For a wall to be done correctly and be as sturdy
as possible, the contractor needs to possess the proper
wall skills.
• Reduced installation
time and non odorous
operation
PRECAST Building
Precast is fast adopting itself into the construction
sector, as skilled labor availability is diminishing
day by day in India, and the construction demand
is on the rise in the country. Builders and
Developers are looking at ways of adopting the
precast into the construction and achieve speeds
and quality.
Precast Advantages
• Factory condition production, all weather working, better quality,
finish and accuracy.
• Less labor requirement, less wastage and less cost based on
repeatability of items.
• Faster cycle time, scalability and repeatability.
• Offsite working and parallel working, standardization of design,
engineering and execution.
Types Of Precast Systems
• Large-panel systems,
• frame systems,
• slab-column systems with walls and mixed systems.
Large-Panel Systems
What is Post-Tensioning?
Post-tensioned concrete means that the concrete is poured and then the tension is applied to
the high strength Steel, but it is still stressed before the loads are applied so it is still
prestressed.
Advantages & Applications of Post-Tensioning
• Unbonded Post-Tensioning
It is typically used in new construction for elevated slabs, slabs-on-grade, beams, and
transfer girders, joists, shear walls, and mat foundations. Light and flexible, the
unbonded mono strand can be easily and rapidly installed – providing an economical
solution.
Thickness or Depth of Section
Some design complication like precast member typical size not fitting in the
project, any special load may come than usual load design, support system
differ than usual like, low sbc or soil stabilization required.
Some shape complication than usual shape may lead to have expert help.
complex Project:
Emerging concept. Advanced tools and testing is required
Full building designed as per all codal guideline need to be full filled for
EQ, Wind, Gravity and all loads.
Chaotic Project:
Timebound and totally new. Advanced tools and testing may not be available
Safety Regulations
Maintainability Traceability
Design and Development Inputs
Functionality
• Document everything
To ensure product safety during R&D is to document everything you do, from the planning to the execution.
Review depends on
Check Progress of Review timeline or customer requirement,
Assess Results Check Progress of Cost
design activities milestone risk involved, size,
complexity
Verification
Validation
Evaluate impact of change (process, resource, product character, budget, schedule etc.)
Change authorization
Designer • Review
Introduction
4. External Sources: Customers | Competitors | Distributors | Suppliers | Outsourcing firms | Design Firms | Product Consultancies | Online Collaborative Communities | Online Opinions
New product ideas are derived from either one or more of the following groups:
• Customer requirements
Design & Development Planning: Executive Director Technical [EDT] prepares Design and Development Plan for the project indicating the
design phases, departmental interfaces during the design process, tentative planned duration of each design phase, etc. The tentative durations
are only minimum projected durations and may vary depending on the availability of resources and personnel. The plan is forwarded to
Manager Product Development along with the Project Initiation Form for execution.
4. Time of consumption
1. Target Market
3. Product Positioning
4. Sales
5. Market share
6. Profit Goals
7. Planned price
8. Distribution
9. Marketing Budget
Literature survey of available methods, similar applications, similar products, related testing, etc. with references if prepared by Manager
Product Development and submitted to EDT.
Manager Product Development checks innovator / competitor’s product or technology and submits report to EDT.
Product Development Team (PD Team) under the supervision of Head/Manager - Product Development starts working on the tentative design
of the intended product with 3D Concept/Visuals and required inputs for Design and Development.
1. Material properties
2. Loading criteria
3. Environmental criteria
7. Formwork criteria
NPTC approves design inputs from Product Development Team and supports in necessary data capturing.
Design and Development
Product Development Team (PD Team) shall consider the following and prepare a design report:
2. duration required,
3. nature of complexity,
9. design controls,
13. level of control expected from other departments, customers and other interested parties
Advanced Production and Quality Planning
Once the product design is reviewed, verified and validated, the NPTC takes decision on order of formwork and proceeds for the Advanced
Production and Quality Planning (APQP Process).
Once the formwork is ordered, the item code is opened in SAP.
Prototype item
Inspection method, Inspection/Control Plan Design – Drawing and Confirmation of
Quality Planning production and
equipment and tools for prototype specification manufacturing feasibility
inspection
Logistic Concept
Process flow chart and Inspection equipment Preproduction/ Pre
Process FMEA Process instructions including packaging
mass production layout capability release control Plan
material
1. Design
2. Specifications
3. Raw material
2. Stability study may be carried out and reported every 6 months. Any deviations/failures may be recorded and the results maybe intimidated to EDT.
3. EDT holds a Design Review Meeting with Team where probable causes of deviation / failures are discussed and modification in the product are proposed and
approved.
4. The decisions / modifications in the intended product are implemented through Process revision Form.
Design and Development Reviews
Minimum 3 reviews:
(INDIA + JAPAN)
Technology (optional) Chemicals
Reinforcement Anchors/ Pre or post tensioning
MOCK WITH APPLICABLE TESTING, VALIDATION MANUF. TEAM + DISPATCH TEAM + QUALITY TEAM + DD TEAM
Joint Review – DD / Manuf & Dispatch/ Installation SOP, ITP etc.
STABILITY STUDY – 3 MONTH MONITORING LED BY MANAGEMENT FAILURE MODE EFFECT ANALYSIS (FMEA) (IF APPLICABLE) DD TEAM
Joint Reviews – DD / Manuf & Dispatch/ S&M / Installation /Management