MINUS DELIVERY (25/1/24) : Kebutuhan Single Part
MINUS DELIVERY (25/1/24) : Kebutuhan Single Part
STRATEGY PLAN
1. Bpk Gugun dan Teguh visit to IJPC, to discuss with IJPC related this material problem
2. Target Incoming from IJPC ( Night Shift )
3. Recovery plan at PT ITI – Paralel production asyy ( III ) Night Shift
OPENING SERIES
INCOMING OUTPUT WIP BY ACTUAL WIP BY NOW
No MODEL PART NAME PART NO. PART NO. FG USAGE STOCK GAP S/R & RHD
SINGLE PART PDN DATA WIP SIMULATION
WIP OUTPUT
71201-I7000 1 1560
EXTN-FR
1 SU2ID PILLAR 71252-I7000 71201-I7900 1 456 2050 190 946 20 926 850 96
UPR,LH
71201-I7950 1 660
71202-I7000 1 1690
EXTN-FR
2 SU2ID PILLAR 71262-BW000 71202-I7050 1 601 2100 100 1065 20 1045 920 91
UPR,RH
71202-I7900 1 820
Note : PADA SIMULASI WIP STOCK, ITEM SERIES TIDAK DIMASUKKAN KEDALAM FAKTOR PENGURANG
MONITORING BOARD PT.ITI
Note : Akan di buatkan monitoring board ( PIC : PDN & member PT.ITI )