For UG 19.04.2024

You might also like

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 46

MOMINPUR(Excl.

)-
ESPLANADE SECTION
OF
JOKA-ESPLANADE METRO
CORRIDOR

14/05/2024
UNDERGROUND ALIGNMENT
ESPLANADE

PARK STREET
VICTORIA

KHIDDERPORE

UNDERGROUND SECTION

MOMINPUR Ramp

ELEVATED SECTION
MAJERHAT ALIGNMENT
2
14/05/2024 METRO RAILWAY KOLKATA
Brief Details of Contract of Construction Work of Mominpur(Excl.)-Esplanade Section:

Name of Work : Design and Construction of the Ramp and Underground Metro Railway
Works from Mominpur (Excl.) to Esplanade, 5.05 Km (from Chainage
9063.00m to 14113.00m) including four underground Stations (viz.
Khidderpore, Victoria, Park Street and Esplanade), Tunnels by Tunnel
Boring Machine and Cut & Cover method, Architectural Finishing Works,
Track Works, etc. in connection with Joka – Esplanade Metro Corridor in
the City of Kolkata, State of West Bengal, India.”
GC cum PMC : Yuksel Proje India – TUMAS India JV
Contractor : M/s Larsen & Toubro Limited
Contract Value : INR 2447.91 Crores
Date of Award : 25.07.2023
Date of Commencement 06.09.2023
(DoC)
Contractual end date : 01.09.2027
Period of Completion : 48 Months
Nos. of UG stations : 04 (Four)- Khidderpore, Victoria, Park Street & Esplanade (Total:1275m)
Length of TBM Tunneling : 2645 m (Twin tube)
Length of Cut & Cover : 893m
Open Ramp : 237m
Mobilization Advance : INR 61.19 Crores (Gross)
3
Brief Description of the Section

 The alignment starts with an elevated ramp section for twin track accommodation from start
of package at chainage 9+063 to chainage 9+300. The underground box start from chainage
9+300 to 9703.326. The corridor goes underground beyond Mominpur to Esplanade.

CHAINAGE
RAMP/CUT &
SL.NO. Length (m)
Start End COVER/TUNNEL/STATION
1 9063.000 9300.000 237 Ramp
2 9300 9703.326 403.326 Cut & Cover
3 9703.326 10028.333 325.007 Khidderpore Station
4 10028.333 10118.000 89.667 Cut & Cover
6 10118.000 10161.000 43 TBM Launching/Retrieval Shaft
7 10161.000 11884.417 1723.417 TBM Tunnel
8 11884.417 12209.417 325 Victoria Station
9 12209.417 13123.028 913.611 TBM Tunnel
10 13123.028 13448.028 325 Park Street Station
11 13448.028 13791.809 343.781 Cut & Cover
Esplanade Station (300m) and Cut &
12
14/05/2024 13791.809 14113.000 321.191 Cover Beyond
Key Plan

14/05/2024
HANDING OVER OF
LAND/SITE

6
Handing over of Land/Site:

Chainage Chainage Section Length Section Handed


Sl. Sections Type of structure Remarks
(from) (to) (m) Over (m)

1 Overground Ramp 9063.00 9180.00 117.00 117.00 Command Hospital


2 9180.00 9406.00 226.00 Nil CMRI & CGN
3 9406.00 9446.00 40.00 40.00 City Properties & Road
KAP (379m ) & Marry
4 9446.00 9830.00 384 Nil
Cooper (5m)
5 Section-1 9830.00 9875.00 45.00 45.00
6 Chainage 9875.00 9893.00 18.00 Nil Marry cooper
7 9063.00m to 9893.00 9916.00 23.00 23.00
Cut & Cover Box and
8 10118.00m 9916.00 9955.00 39.00 Nil St. Thomas
Khidderpore Station
9 9955.00 10016.00 61 61
Diocesan Association
Nil
10016.00 10078.00 62 and St. Thomas
10
11 St. Thomas
10078.00 10089.00 11
11
12 10089.00 10118.00 29 29
43
13 TBM launching shaft 10118.000 10161.000 43.000
Section-2 1723 TBM Tunnel
14 Chainage TBM TUNNEL 10161.000 1723.417
11884.417
15 10118.00m to Victoria station 11884.417 12209.417 325 325 Victoria
13448.00m
16 TBM TUNNEL 12209.417 13123.028 913.611 914 TBM Tunnel
17 Park street station 13123.028 7 13448.028 325 325 Park Street
Handing over of Land/Site:

Section
Chainage Chainage Section
Sl. Sections Type of structure Handed
(from) (to) Length (m)
Over (m)
18 13448.028 13637.00 189.00 189.00 Open ground with tree
Cut & Cover Box
19 13637.00 13766.00 129 129 Manohardas Tarag
20 Section-3 13766.00 13792.00 26.00 26.00 Road
21 Chainage 13792.00 13876.00 84.00 84.00 KM Paddock
22 13448.00m 13876.00 13908.00 32.00 32.00 Kidderpore Club
to Esplanade station Nil
23 14113.00m 13908.00 14006.00 98.00 B C Roy Market
24 1406.00 14036.00 30.00 30.00 Dufferin Road
Nil
25 14036.00 14113.00 77 L 20 Bus stand
TOTAL 5050.00 4146.00

8
LAND ACQUISITION
BY RVNL

9
Land Acquisition

 Land is required to be acquired from different stake holders as per following:

Chainage Nature of Land involved Purpose

Permanent diversion of Diamond


7 nos. of Private land, 3 nos. of State
9063 – 10400 Harbour Road and underground
Government land, 1 no. of Defence
(1337 m) utilities, Construction of permanent
Land (Command Hospital), and 1 no.
(A2 to Turf View) overground structures of Khidderpore
of Sovereign Land
Station

10400 – 14113
Construction of permanent
(3713 m)
Defence Land (Maidan Area) overground structures of Victoria,
(Turf View –
Park Street and Esplanade Station
Esplanade)

Defence Land (Curzon Park – Maidan


- Relocation of Dr. B C Roy Market
Area)
14/05/2024
Details of required land (Chainage 9063 – 10400)

1. Permanent Acqsn. of Private Land (Total required area = 4656.448 sqm from 7 nos. of premises)
(Total Required strip length = 430 m, Awarded = 235m, Possession taken over = 147 m, Handing over pending = 88m)
Required Area Required Strip Length
Sl. No.1 Name of Owner Premises No. & Address Remarks / Status
(sqm) (m)

827.539 Pending at CA Court. Authorities have


Calcutta Medical Research 7/2, D.H Road, Kolkata -
1 164 appealed in Hon’ble Calcutta High Court for
Institute 700027 40.825 compensation claim

105.326 18 m Awarded & Possession Taken over.

1, National Library Avenue, Awarded. Handing over pending due to


2 City Properties Pvt. Ltd. 18
Kolkata - 700027 encroachment by tenants. Tenants have filed
532.634
petition at Hon’ble Calcutta High Court
challenging the acquisition
Awarded. Handing over pending from Metro
219.475
4/2, D. H. Road, Kolkata - Railway.
3 Mary Cooper Home 91
700023 68 m length Awarded and Possession taken
233.767
over
13 m length Awarded. Handing over pending
160.304
4 St. Thomas School 4, D.H. Road, Kolkata - 700023 39 from Metro Railway..
80.608 Award Pending at CA Court

61 m length Awarded and Possession taken


2,054.771
The Calcutta Diocesan over
5 5, D.H. Road, Kolkata - 700023 83
Association Awarded. Handing over pending from Metro
79.546
Railway.
70/2, D.H. Road, Kolkata - Claimant didn't file any claim yet. To be
6 Garden Guest House 6.653 5
700023 awarded by Ld. CA Court.
Awarded. Handing over pending from Metro
7 St. Teresa School 72, D.H. Road, Kolkata -700023 315.000 30
Railway.
14/05/2024
Details of required land (Chainage 9063 – 10400)
2. State Government Land (Total required area = 3,233.562 sqm from 3 nos. of Govt. premises)
(Total Required strip length = 400 m, Handed over = 0)

Required Strip
Sl. No. Name of Owner Premises No. & Address Required Area (sqm) Length Remarks / Status
(m)

1092
(Permanent transfer) Handing over of land is pending with Govt.
1 Kolkata Armed Police 7, D.H Road, Kolkata - 700027 380
1702 of West Bengal
(Temporary transfer)
Office of Executive Handing over of land is pending with Govt.
72, D. H. Road, Kolkata -
2 Engineer (Electrical), 427.808 15 of West Bengal
700027
PWDte

70/1A, D. H. Road, Kolkata - Handing over of land is pending with Thika


3 Thika Tenancy 11.754 5
700027 Board

3. Defence Land (Command Hospital) (Total required area = 2147.289 sqm from 1 nos. of Defence premises)
(Total Required strip length = 435 m, Handed over = 435 m)

Required Strip
Sl. No. Name of Owner Premises No. & Address Required Area (sqm) Length Remarks / Status
(m)

Handed over on 16.06.2023. Relocation


Command works of existing structures including
1 17/1E, Alipore Rd, Kolkata - 700027 2147.289 435
Hospital boundary wall in progress(80% relocating
work done).

14/05/2024
Details of required land (Chainage 9063 – 10400)

4. Sovereign Land (Total Required Area = 409.538 sqm from 1 no. of premises)
(Total Required length = 62 m, Handed over = 0)

Required Area Required Strip Length


Sl. No. Name of Owner Premises No. & Address Remarks / Status
(sqm) (m)
Proposal for transfer of land has
been concurred by Ministry of
External Affairs and has been
Consulate General 7/1, D. H. Road, Kolkata -
1 409.538 62 forwarded to Embassy of Nepal,
of Nepal, Kolkata 700027
New Delhi for concurrence.
Approval is pending from Govt. of
Nepal

5. Temporary Land Acquisition required for St. Thomas School & Diocesan Association. Further agreements for
acquisition temporary land for Diocesan Association (143.14 Sqm.) and St. Thomas School (82.570 sqm) are under
finalization.

14/05/2024
Details of required land (Chainage 10400-14113)

1. Defence Land (Maidan Area)


Premises No.
Sl. No. Name of Owner Required Area (sqm) Remarks / Status
& Address
4279.140
Land handed over on
1 Ministry of Defence Maidan (Victoria + Park Street + Esplanade
16.06.2023
permanent overground structures)

• Land at Maidan Area has been handed over to RVNL by Defence Authorities on 16.06.2023.
• Infringing Clubs in Maidan Area namely, Calcutta Police Club, Calcutta Kennel Club, Rajasthan Club
and Kidderpore Sporting Club will be required to be relocated. 5 containers out of 10 have been
received.
• Kolkata Mounted Police Paddock & Riding School will be required to be relocated to facilitate
construction of Esplanade Station.- NOC from Defence Authorities has been received on
12.04.2024.
2. Defence Land (Curzon Park - Maidan Area)- For relocation of B C Roy Market (Area required:
4720 sqm)
• As informed by MoD in PMG Portal, the land at Curzon Park cannot be transferred.
• Alternate options for temporary relocation of the B.C. Roy Market are currently being explored.

14/05/2024
COURT CASES

15
Court Cases at Hon’ble Calcutta High Court
 3 nos. of Court Cases have been filed at Hon’ble Calcutta High Court as per following:

1. WPA(P)/20081/2022
Affecting ramp work between Mominpore and Khidderpore

Filed by: Jagannath Prasad Gupta (Tenants of City Properties )


Plea by Petitioner: Quashing the Gazette Notification for Acquisition of 532.634 sqm of City Properties Pvt. Ltd. and the
orders passed by Ld. CA Court, and imposing injunction restraining RVNL/Metro Railway from taking
any steps towards acquisition of City Properties.

Status of hearings: As on date, 14 nos. of hearings have been held at Hon’ble Court, the last being on 09.04.2024. Next
hearing will be held on 09.05.2024.

2. WPA(P)/569/2023:

Affecting construction of all 03 Metro Stations i.e. Victoria, Park Street and Esplanade and 340m of Tunnel
portion( cut and cover)

Filed by: People United for Better Living in Calcutta (PUBLIC)

Plea by Petitioner: Setting up of Expert Committee to examine the feasibility of transplantation in Maidan Area.
Prohibiting RVNL from proceeding with the plan of construction of Victoria Station. Transmit all
records pertaining to construction of Victoria station. Change of Alignment.

Status of hearings: As on date, 3 nos. of hearings have been held at Hon’ble Court, the last being on 04.01.2024.
Next hearing will be held shortly. Hon’ble High Court had imposed injunction on transplantation of
trees in Maidan Area upto 09.11.2023
14/05/2024
Court Cases at Hon’ble Calcutta High Court

Hon’ble High Court ordered RVNL to obtain necessary clearances for uprooting of trees in Maidan
area from Defence, Forest etc department. Permission for transplantation of trees in Victoria has
been accorded by Defence on 19.12.2023. Permission is awaited from K Forest Department of
West Bengal. Court has permitted to execute other work except uprooting of trees till NOC granted
by court.

3. WPA/1993/2024:

Filed by: Calcutta Medical Research Institute (CMRI Hospital)

Plea by Petitioner: Furnish the technical data to CMRI as sought vide letter dated 14.12.2021 addressed to RVNL.
Commanding the Ld. CA Court not to proceed with claim compensation till data as sought on
14.12.2021 is furnished to CMRI.

Status of hearings: As on date, 4 nos. Of hearings have been held in the court of Justice Suvra Ghosh. Last hearing
held on 28.03.2024 , wherein the Interim Stay on award of claim cases of CMRI JB 645 of 2022
and JB 657 of 2022 has been extended upto 31.05.2024. Next date of hearing has been scheduled
on 25.04.2024. Replies of observations raised by CMRI vide letter dated 14.12.2021 have been
made on 15.02.2024. Further observations received from CMRI on 09.03.2024 and 27.03.2024,
replies of which has been given on 13.03.2024 and 05.04.2024 respectively.

14/05/2024
DESIGN SUBMISSION
STATUS

18
As on 15.04.2024
Major Submissions Status

Submission 1st Subm. 1st Resp. 2nd Subm. 2nd Resp. 3rd Subm. 3rd. Resp. Remarks
Initially NOWC given with Major, Moderate &
Minor Comments then NONO at 28/02/2024
but on 08/03/2024 NONO withdrawn
28.02.2024 & 08-
D-wall at Victoria 28-12-2023 13-01-2024 20-02-2024
03-2024

Preliminary Design Submission

For complete Project (DBR, Dwg etc) 09-01-2024 30-01-2024 20-03-2024 27-03-2024 NOWC with Major, Minor & Moderate
comments. Pending with L&T
NOWC with Major, Minor & Moderate
D-wall at Cut & Cover, UG Ramp & 19-03-2024 05-04-2024
comments. Pending with L&T
Cross Over
Tunnel Temporary Segments 06-03-2024 19-03-2024 21-03-2024 26-03-2024 28-03-2024 29-03-2024
NONO has been granted
Definitive Design Submission
Tunnel Permanent Segments &
Cross Passages and Sump 29-03-2024 05-04-2024 Rejected with Comments. Pending with L&T
For complete project 02-04-2024 Under Review
G-Wall (for D-Wall) Layout DWGs of
Victoria Station ON HOLD status due to missing IIT and
27-01-2024 16-02-2024 19-02-2024 15-03-2024 Shifting Issue Confirmations
G-Wall (for Barrettes) Layout DWGs
of Victoria Station
27-03-2024 12-04-2024 Rejected with Comments. Pending with L&T
G-Wall (for D-Wall) Layout DWGs of
Layout Submission
Launching Shaft 13-02-2024 19-02-2024 27-02-2024 29-02-2024 NOWC has been granted with conditions
D-Wall Layout DWGs of Victoria
Station ON HOLD status due to missing IIT and
27-01-2024 15-02-2024 19-02-2024 16-03-2024 Shifting Issue Confirmations
D-Wall Layout DWGs of Park Street
Station Rejected due to Missing PD or DD
09-02-2024 17-02-2024 19-02-2024 26-02-2024 Submissions of Park Street Station
Khidderpore Station 30-03-2024 Under Review
Victoria Station 15-03-2024 18-03-2024 20-03-2024 26-03-2024 Pending with L&T
Geotechnical Factual Report Park Street Station 04-04-2024 Under Review
Launching Shaft 15-03-2024 18-03-2024 20-03-2024 26-03-2024 Pending with L&T
TBM-I Section 22-03-2024 04-04-2024 08-04-2024 Under Review
NOWC with comments. Pending with L&T.
Victoria Station 2nd subm. Withdrawn by 3rd subm.
23-03-2024 04-04-2024 06-04-2024 08-04-2024
Geotechnical Interpretative Report
Launching Shaft NOWC with comments. Pending with L&T
29-03-2024 05-04-2024
TBM-I Section 04-04-2024 Under Review

14/05/2024 19
STATUS OF UG WORK

20
Status of Work: Casting Yard
1. Casting Yard:

• Erection and commissioning of batching plant :Out of total min. 2 nos of batching plant of capacity 60
cum/hr, establishment of 01 no. batching plant (Aggregate bin, Control cabin, Cement silo, Fly ash silo,
Micro silica silo) erection done & commissioning is completed.
• 1st Labor colony foundation work completed & 2nd labour colony foundation work is in progress.
• Weighing bridge installed and hard barricading work done around the weigh bridge.
• QA/QC lab finishing work completed. Lab equipment’s placement & third-party calibration work
completed. 3rd party report awaited.
• Electrical room: Brick work completed. - Room inside plastering and Electrical transformer & panels
fixing work is in progress.
• 10T EOT Crain rail erection & alignment work is in progress.

21
Status of Work: Casting Yard

22
Status of Work: Casting Yard

23
Status of Work: Ramp to Launching Shaft

2. Open/U-shape Ramp Chainage 9063.000m to 9300.000m:

i. Total Length: 237.00m, land handed over: 117.00 m

3. Cut & Cover Chainage 9300.000m to 9703.32m


i. Total Length: 403.326m, land handed over: 40.00 m

4. Khidderpore Station from Chainage 9703.32m to 10028.33m


ii. Total Length: 325.00m, land handed over: 129 m for Ancillary Building of Khidderpore Station has
been handed over to L&T.

5. Launching shaft at Khidderpore from chainage 10028.33.00m to chainage 10161.00m


i. Total Length: 132.67m, Available land: 82.72 m
iii. Dewatering of pond at St. Thomas and Backfilling is completed. Guide Wall Construction is
ongoing and 95 meters out of 109 meters have been completed.

24
Status of Work– Launching shaft

Kaveri
Mahavir

Dharani
Dhatri

25
Procurement of TBM

Sl No. Activity Time Schedule Current Status


1 Submission of PO for KD-02: 10 weeks which Submitted copy of LOA on
purchase of 02 Nos. TBM to includes 02 weeks for review 06.01.2024.
employer of engineers from date of Submitted the technical
commencement i.e. details of TBM for review on
15.11.2023 20.01.2024.

2 Completion of Civil Work of KD-08: 50 weeks from date 1. Work of D-wall has not
TBM Launching Shaft and of commencement i.e. yet started.
ready for TBM No.1 & TBM 20.08.2024 2. Guide Wall is in
No.2 progress.

3. Manufacturing of TBM DWP: TBM1 - 22.11.2024


including FAT TBM2 - 17.12.2024
4. TBM Delivery to the site DWP: TBM1 - 22.12.2024
Kaveri TBM2 - 18.01.2025
Mahavir
5. Start of Initial drive for TBM- KD-9: 74 weeks from date of
1 Dharani commencement .i.e.
Dhatri 04.02.2025

26
Hindrance Photos – Launching shaft

Kaveri
Mahavir

Dharani
Garage of St.Thomas school quarters Waiting hall at St.Thomas school
Dhatri

27
Status of Work: Victoria Station

6. Victoria station:
i. Barricading work has been fixed 910m out of 910m.completed work is 100%.
ii. Guide wall casting completed 550.5m out of 709m. Completion of work is 77%. Entry/Exit
has been not started yet.
iii. 40.5m length portion is hindered by the Trees.
iv. Fountain of Joy demolition work has been completed 100%. (Area filling and compacting
completed).
v. Diaphragm wall back-up system mobilization going on. (2 nos Rig machine, 16 nos.
Polymer tank, stoppers reached at site)
vi. M/s KAMAR has been approved for execution of D-wall work.
vii. Trench has been done for utility identification, coordination with authorities in progress.
viii. TFC Crane reached at site for diaphragm wall Works.
ix. 1 no. Tyre Mounted Crane reached at site for diaphragm wall Works.

28
Status of Work: Victoria Station

29
Status of Work: Victoria Station

30
Status of Work: Park Street Station

7. Park Street Station:


i. Park Street Station Total Length: 325.00m, Available land: 325.00m
ii. Barricading work has been fixed 334m out of 918m. completed work is 36%.
iii. Guide wall casting completed 144m out of 701m. Completion of work is 20.5%. Entry/Exit has been
not started yet.

Placing of Porta type Container:


iv. Calcutta police club: 4 no’s containers fixing completed including water supply, drainage system etc.
v. Rajasthan Club: 2/3 foundation work completed. Containers still not arrived.
vi. Kennel Club: Foundation work completed. 1/1 Container has arrived on 4th April 2024.
vii. Khidderpore Club: Foundation work completed. Container still not arrived.

31
Status of Work: Park Street Station

7. Park Street Station/Club Area:

32
Status of Work: Park Street Station

33
Status of Work: Esplanade Station

8. EsplanadeStation:
Chainages Length Premises Status
13792.000 –
84 m Mounted Police Paddock Unilaterally handed over to L&T.
13876.000
13876.000 –
32 m Kidderpore Sporting Club & Walkway Unilaterally handed over to L&T.
13908.000
13908.000 –
98 m Dr. B C Roy Market Not Handed Over
14006.000
14006.000 –
30 m Dufferin Road Unilaterally handed over to L&T.
14036.000
14036.000 –
56 m L-20 Bus Stand (WBTC) & Dufferin Road Not Handed Over
14092.000
14092.000 –
21 m L-20 Bus Stand (WBTC) & Dufferin Road Not Handed Over
14113.000

i. Esplanade Station Total Length: 325.00m, Available land: 137.00m


ii. NOC for Shifting of Paddock club has been obtained on 12.04.2024.
iii. L&T has been advised to start the preparatory work for shifting of Paddock club on 15.04.2024.
iv. Container fixing for Khidderpore club has already been advised to L&T and Memorandum has also
been issued.
34
TREE
TRANSPLANTATION
STATUS

35
TREE TRANSPLANTATION STATUS

WITHIN STATION BOX WITHIN TEMPORARY WORK AREA STATUS OF DRAWING


STATUS OF NOC
STATUS OF
FROM KMC STATUS OF NOC
TRANSPLANTATI PLANTATION NOC FROM STATUS OF NOC ONLINE APPLICATION TO
SL NO AREA TOTAL SCOPE (KOLKATA FROM FOREST
ON LOCATION LOCATION PRIVATE FROM DEFENCE WB FOREST
MUNICIPAL DEPARTMENT
AGENCIES
NAME OF STATION NOS OF TREE NAME OF STATION NOS OF TREE TRANSPLNATATION PLANTATION CORPORATION)

Only St
Thomas NOC
Drawing for 84 no Drawing for 420 have been Only St Thomas form
Form 1 ( C )
From Ramp to From Ramp to trees nos. trees received from 1 ( C )have been
1 Private Land 134 96 230 Kamardanga Joka Not applicable sumbitted to DFO on Applied on 16.12.2023
Launching Shaft Launching Shaft transplantation has plantation has concerned received dated
dated 06.03.2024
prepared prepared authority (St. 06.03.2024
Thomas) on
08.11.2023

Clearence Certificate
Drawing for 140
Received from Form 1 ( C )have been obtained on
nos. trees
2 Victoria 14 Victoria 14 28 Prepared Kamardanga Joka Defence on received dated 12.04.20244..Clearan Applied on 02.11.2023
plantation has
19.12.23 27.02.2024 ce certificate
prepared
received from DFO

Drawing for 930


Received from Form 1 ( C )have been Form 1 ( C )
nos. trees
3 Parkstreet 112 Parkstreet 72 184 Prepared Kamardanga Halisahar Defence on received dated sumbitted to DFO on Applied on 14.11.2023
plantation has
02.03.2024 02.04.2024 dated 02.04.2024
prepared

Defence Land Pending due to Web Site of


Crossover (in Crossover (in Between Partly
Forest Department not
4 Between Parkstreet 337 Parkstreet & 117 454 Prepared Pending Kamardanga & Halisahar Pending Pending Pending
Working as on date 15-04-
& Esplanade) Esplanade) partly Goragacha
2024

Applied vidde letter


Drawing for no -
Received from
1305 nos. trees RVNL/KOL/Metro/MJ
5 Esplanade 210 Esplanade 51 261 Prepared Kamardanga Halisahar Defence on Pending Applied on 09.12.2023
plantation has T-MMN/Utility/Trees/
02.03.2024
prepared 1005, dated
03.04.2024

Total 705 348 1053

36
DEPLOYMENT STATUS OF KEY
PERSONNEL OF L&T

37
Status of Work: STATUS OF KEY PERSONNEL

Deployment of Key Personnel:


i. Project Manager is not yet deployed within 30 days of LOA. Delayed till 31st of March 2024 is of 220
days.
ii. Construction Manager (Civil & Geotechnical) has also not been deployed even after multiple instruction
issued by the Engineer.
iii. L&T has stated that Expert Agency M/s Green morning is deployed for the transplantation works.
iv. Out of total 50 Nos of Key Personnel, 15 Nos have been approved & deployed.

38
Status of Work: STATUS OF KEY PERSONNEL
Sl. No. Discipline Numbers Deployment Status
1 Project Manager (Civil Engineer) 1 Not Deployed
2 Construction Manager (Cut and Cover Tunnel) 1 Deployed
3 Construction Manager (TBM Tunnel) 1 Not Deployed
4 Construction Manager (Civil and Geotechnical) 1 Not Deployed
5 Construction Manager (Stations) 1 Deployed
6 Construction Manager (Facilities) 1 Not Deployed
7 Engineering Manager ( Design and Technical Support) 1 Not Deployed
8 Engineering Manager( Planning and billing) 1 Deployed
9 Station In-charge (One for each station) 4 2 nos. Deployed
10 Chief Track works Engineer 1 Not Deployed
11 Chief Safety Manager 1 Deployed
12 Chief Quality Manager 1 Deployed
13 Chief Architect 1 Not Deployed
14 Chief Interface Engineer 1 Not Deployed
15 Chief Surveyor 1 Deployed
16 Chief Environment Specialist 1 Deployed
17 Traffic and Utility diversion Engineer 1 Deployed
18 Senior Engineer
a Stations 4 Not Deployed
b Tunnel(Cut and Cover) 2 2 nos Deployed
c Tunnel(TBM) 2 Not Deployed
d Civil and Geotechnical 2 Not Deployed
e Planning and Billing 1 Deployed
39
Status of Work: STATUS OF KEY PERSONNEL

Sl. No. Discipline Numbers Deployment Status


f Quality Control 2 1 nos. Deployed
g Track works 2 Not Deployed
h Safety and Health (SHE) 2 1 nos. Deployed
i Mechanical engineer 2 Not Deployed
g Traffic diversion and Utility 2 1 nos Deployed
19 Surveyor for setting out Lines and levels periodically 2 Not Deployed
20. Draftsman with Knowledge of AutoCAD
a Civil engineering 4 1 nos. deployed
21 Liaison Manager for liaison with Govt. Dept. and local bodies 2 Not Deployed
22 BIM Operator 2 Not Deployed
23 Project Platform Co-ordinator 1 Not Deployed

40
Status of Work: Geotechnical work and Health Minitoring

Additional bore hole/Geo Technical Investigation:


i. M/s CEG has been engaged by L&T for Geotechtechnical activities.
ii. Total 53 Nos. of additional bore holes have been completed. GFR & GIR for Victoria and Launching shaft
is received..
Building Health Monitoring:
iii. M/s SS Geotech Instrumentation has been engaged by L&T for Building Health study.
iv. Building Health Monitoring of Victoria Memorial is started. Recording of existing condition of Victoria
Memorial is under progress.
v. Health Monitoring of Turf View Complexes is being planned to commence shortly.
Implementation of PMIS software for project management and documentation:
vi. M/s WRENCH has been proposed by L&T on 10.04.2024 for Web based GIS/real time data
management, implementation of BIM project management etc. The same is under review with GC.

41
KEY DATE STATUS
Propose Equival Days Left Difference
Contractu
d ent before Actual (Days)
Key al Status as on
SL Description Weeks Days Contractual Completion between Remarks
Date Completio date
from from Completion Date Contractual
n Date
DOC DOC Elapses and Actual

Submission of Detailed Works Programme


1 KD1 4 28 03-Oct-23 03-Oct-23 0 Submitted on time
with all activities for Entire Work
Submission of the copy of the Agreement/
LOA/ Purchase Order for purchase of TBMs
Submitted on 20.01.24.
or a proof of availability of TBMs Ready for
2 KD2 10 70 14-Nov-23 20-Jan-24 67 Delay in achievement
Deployment or Combination Thereof. This
by 67 days.
Period includes 2 weeks for Design Review
by Engineer
Final Submission of Detailed Works
Programme Incorporating all Comments of
3 KD3 12 84 28-Nov-23 28-Nov-23 0 Submitted on time
Engineer, if any, including 2 weeks for Review
by Engineer
Submitted on
08.01.2024. The Key Date concerns
PMC issued submission. As per
NOWC on their first submission it
Preliminary Design Submission & Preliminary
29.01.2024. is on time.
4 KD4 Report of Station Structures, Tunnels, Ramps 18 126 09-Jan-24 08-Jan-24 -1
Compliance However, if we
(incl. Temporary Works)
submitted on consider their final
19.03.2024 submission it will be
which are under considered as delayed.
review of PMC.
KEY DATE STATUS
Differenc
Propose Equival Days Left
Contractu e (Days)
d ent before Actual
Key al between
SL Description Weeks Days Contractual Completion Status as on date Remarks
Date Completio Contract
from from Completion Date
n Date ual and
DOC DOC Elapses
Actual
Achieved but Delayed.
Establishment of Site Office and
Batching plant is
5 KD5 Commissioning of Batching Plant (Production 18 126 09-Jan-24 11-Mar-24 62
commissioned on
of 1st Batch of Concrete)
11.03.2024
Submission of Definitive Design & Final Submitted on time.
6 KD6 Detailed Report of Whole of the Works (incl. 30 210 02-Apr-24 02-Apr-24 0 Contents still not fully
Temporary Works) verified.
Still in Progress.
Establishing Casting Yard for Segment
Land handed over on
7 KD7 Production and Start of Production of First 30 210 02-Apr-24 -13
13.01.2024 as per Joint
TBM Ring
Handover Document.
CONSTRUCTION EQUIPMENT AND MACHINERY

Minimum
S.L. Age of the Equipment
Equipment Type Number
No
Required
1 Tunnel Boring Machine (EPB_Type) 2 New

Fully Automatic and Computerized Batching


Plant-02 Nos. (Two of 60 cum./hr. and other one
of 30 Cum/hr. for Stand-by) minimum or
equivalent capacity in different configuration at
casting yard with RO of suitable capacity for each
plant for proper quality of water. 2 + 1 (stand- New
2
Note: by)
i) consent to establish and consent to operate is
to be taken by contractor
ii) Arrangement of water for production of
concrete & curing at batching plant and at site to
be made by contractor

3 Concrete Pumps with Boom Placers 4 Maximum 3 years


4 Stationary Concrete Pumps with sufficient pipes 8 Maximum 3 years
As per Appendix-16 of Safety &
5 D-wall Hydraulic Rig machine 6 Health and Environment
As per yard As per Appendix-16 of Safety &
6 Gantry of suitable capacity in casting yard Health and Environment
layout
44
CONSTRUCTION EQUIPMENT AND MACHINERY

S.L. Minimum Number Age of the Equipment


Equipment Type
No Required
As per launching As per Appendix-16 of Safety &
retrieval scheme Health and Environment
7 Gantry of suitable capacity at station
and excavation
scheme at stations
Crane in casting yard & station location of As per Appendix-16 of Safety &
8 14 Health and Environment
suitable capacity
Portable Road Trailer Mounted Flash Butt Max. 3 years
9 1
Welding Plant
2nd generation pick and carry hydraulic As per Appendix-16 of Safety &
10 10 Health and Environment
crane
As per Appendix-16 of Safety &
11 Transit mixtures 20 Health and Environment
Trailers for carrying segments- 50T As per Appendix-16 of Safety &
12 10 Health and Environment
capacity
As per Appendix-16 of Safety &
13 Tipper trucks 35 Health and Environment
As per Appendix-16 of Safety &
14 Rock/soil excavator 15 Health and Environment

45
THANK YOU

14/05/2024