Professional Documents
Culture Documents
For UG 19.04.2024
For UG 19.04.2024
For UG 19.04.2024
)-
ESPLANADE SECTION
OF
JOKA-ESPLANADE METRO
CORRIDOR
14/05/2024
UNDERGROUND ALIGNMENT
ESPLANADE
PARK STREET
VICTORIA
KHIDDERPORE
UNDERGROUND SECTION
MOMINPUR Ramp
ELEVATED SECTION
MAJERHAT ALIGNMENT
2
14/05/2024 METRO RAILWAY KOLKATA
Brief Details of Contract of Construction Work of Mominpur(Excl.)-Esplanade Section:
Name of Work : Design and Construction of the Ramp and Underground Metro Railway
Works from Mominpur (Excl.) to Esplanade, 5.05 Km (from Chainage
9063.00m to 14113.00m) including four underground Stations (viz.
Khidderpore, Victoria, Park Street and Esplanade), Tunnels by Tunnel
Boring Machine and Cut & Cover method, Architectural Finishing Works,
Track Works, etc. in connection with Joka – Esplanade Metro Corridor in
the City of Kolkata, State of West Bengal, India.”
GC cum PMC : Yuksel Proje India – TUMAS India JV
Contractor : M/s Larsen & Toubro Limited
Contract Value : INR 2447.91 Crores
Date of Award : 25.07.2023
Date of Commencement 06.09.2023
(DoC)
Contractual end date : 01.09.2027
Period of Completion : 48 Months
Nos. of UG stations : 04 (Four)- Khidderpore, Victoria, Park Street & Esplanade (Total:1275m)
Length of TBM Tunneling : 2645 m (Twin tube)
Length of Cut & Cover : 893m
Open Ramp : 237m
Mobilization Advance : INR 61.19 Crores (Gross)
3
Brief Description of the Section
The alignment starts with an elevated ramp section for twin track accommodation from start
of package at chainage 9+063 to chainage 9+300. The underground box start from chainage
9+300 to 9703.326. The corridor goes underground beyond Mominpur to Esplanade.
CHAINAGE
RAMP/CUT &
SL.NO. Length (m)
Start End COVER/TUNNEL/STATION
1 9063.000 9300.000 237 Ramp
2 9300 9703.326 403.326 Cut & Cover
3 9703.326 10028.333 325.007 Khidderpore Station
4 10028.333 10118.000 89.667 Cut & Cover
6 10118.000 10161.000 43 TBM Launching/Retrieval Shaft
7 10161.000 11884.417 1723.417 TBM Tunnel
8 11884.417 12209.417 325 Victoria Station
9 12209.417 13123.028 913.611 TBM Tunnel
10 13123.028 13448.028 325 Park Street Station
11 13448.028 13791.809 343.781 Cut & Cover
Esplanade Station (300m) and Cut &
12
14/05/2024 13791.809 14113.000 321.191 Cover Beyond
Key Plan
14/05/2024
HANDING OVER OF
LAND/SITE
6
Handing over of Land/Site:
Section
Chainage Chainage Section
Sl. Sections Type of structure Handed
(from) (to) Length (m)
Over (m)
18 13448.028 13637.00 189.00 189.00 Open ground with tree
Cut & Cover Box
19 13637.00 13766.00 129 129 Manohardas Tarag
20 Section-3 13766.00 13792.00 26.00 26.00 Road
21 Chainage 13792.00 13876.00 84.00 84.00 KM Paddock
22 13448.00m 13876.00 13908.00 32.00 32.00 Kidderpore Club
to Esplanade station Nil
23 14113.00m 13908.00 14006.00 98.00 B C Roy Market
24 1406.00 14036.00 30.00 30.00 Dufferin Road
Nil
25 14036.00 14113.00 77 L 20 Bus stand
TOTAL 5050.00 4146.00
8
LAND ACQUISITION
BY RVNL
9
Land Acquisition
10400 – 14113
Construction of permanent
(3713 m)
Defence Land (Maidan Area) overground structures of Victoria,
(Turf View –
Park Street and Esplanade Station
Esplanade)
1. Permanent Acqsn. of Private Land (Total required area = 4656.448 sqm from 7 nos. of premises)
(Total Required strip length = 430 m, Awarded = 235m, Possession taken over = 147 m, Handing over pending = 88m)
Required Area Required Strip Length
Sl. No.1 Name of Owner Premises No. & Address Remarks / Status
(sqm) (m)
Required Strip
Sl. No. Name of Owner Premises No. & Address Required Area (sqm) Length Remarks / Status
(m)
1092
(Permanent transfer) Handing over of land is pending with Govt.
1 Kolkata Armed Police 7, D.H Road, Kolkata - 700027 380
1702 of West Bengal
(Temporary transfer)
Office of Executive Handing over of land is pending with Govt.
72, D. H. Road, Kolkata -
2 Engineer (Electrical), 427.808 15 of West Bengal
700027
PWDte
3. Defence Land (Command Hospital) (Total required area = 2147.289 sqm from 1 nos. of Defence premises)
(Total Required strip length = 435 m, Handed over = 435 m)
Required Strip
Sl. No. Name of Owner Premises No. & Address Required Area (sqm) Length Remarks / Status
(m)
14/05/2024
Details of required land (Chainage 9063 – 10400)
4. Sovereign Land (Total Required Area = 409.538 sqm from 1 no. of premises)
(Total Required length = 62 m, Handed over = 0)
5. Temporary Land Acquisition required for St. Thomas School & Diocesan Association. Further agreements for
acquisition temporary land for Diocesan Association (143.14 Sqm.) and St. Thomas School (82.570 sqm) are under
finalization.
14/05/2024
Details of required land (Chainage 10400-14113)
• Land at Maidan Area has been handed over to RVNL by Defence Authorities on 16.06.2023.
• Infringing Clubs in Maidan Area namely, Calcutta Police Club, Calcutta Kennel Club, Rajasthan Club
and Kidderpore Sporting Club will be required to be relocated. 5 containers out of 10 have been
received.
• Kolkata Mounted Police Paddock & Riding School will be required to be relocated to facilitate
construction of Esplanade Station.- NOC from Defence Authorities has been received on
12.04.2024.
2. Defence Land (Curzon Park - Maidan Area)- For relocation of B C Roy Market (Area required:
4720 sqm)
• As informed by MoD in PMG Portal, the land at Curzon Park cannot be transferred.
• Alternate options for temporary relocation of the B.C. Roy Market are currently being explored.
14/05/2024
COURT CASES
15
Court Cases at Hon’ble Calcutta High Court
3 nos. of Court Cases have been filed at Hon’ble Calcutta High Court as per following:
1. WPA(P)/20081/2022
Affecting ramp work between Mominpore and Khidderpore
Status of hearings: As on date, 14 nos. of hearings have been held at Hon’ble Court, the last being on 09.04.2024. Next
hearing will be held on 09.05.2024.
2. WPA(P)/569/2023:
Affecting construction of all 03 Metro Stations i.e. Victoria, Park Street and Esplanade and 340m of Tunnel
portion( cut and cover)
Plea by Petitioner: Setting up of Expert Committee to examine the feasibility of transplantation in Maidan Area.
Prohibiting RVNL from proceeding with the plan of construction of Victoria Station. Transmit all
records pertaining to construction of Victoria station. Change of Alignment.
Status of hearings: As on date, 3 nos. of hearings have been held at Hon’ble Court, the last being on 04.01.2024.
Next hearing will be held shortly. Hon’ble High Court had imposed injunction on transplantation of
trees in Maidan Area upto 09.11.2023
14/05/2024
Court Cases at Hon’ble Calcutta High Court
Hon’ble High Court ordered RVNL to obtain necessary clearances for uprooting of trees in Maidan
area from Defence, Forest etc department. Permission for transplantation of trees in Victoria has
been accorded by Defence on 19.12.2023. Permission is awaited from K Forest Department of
West Bengal. Court has permitted to execute other work except uprooting of trees till NOC granted
by court.
3. WPA/1993/2024:
Plea by Petitioner: Furnish the technical data to CMRI as sought vide letter dated 14.12.2021 addressed to RVNL.
Commanding the Ld. CA Court not to proceed with claim compensation till data as sought on
14.12.2021 is furnished to CMRI.
Status of hearings: As on date, 4 nos. Of hearings have been held in the court of Justice Suvra Ghosh. Last hearing
held on 28.03.2024 , wherein the Interim Stay on award of claim cases of CMRI JB 645 of 2022
and JB 657 of 2022 has been extended upto 31.05.2024. Next date of hearing has been scheduled
on 25.04.2024. Replies of observations raised by CMRI vide letter dated 14.12.2021 have been
made on 15.02.2024. Further observations received from CMRI on 09.03.2024 and 27.03.2024,
replies of which has been given on 13.03.2024 and 05.04.2024 respectively.
14/05/2024
DESIGN SUBMISSION
STATUS
18
As on 15.04.2024
Major Submissions Status
Submission 1st Subm. 1st Resp. 2nd Subm. 2nd Resp. 3rd Subm. 3rd. Resp. Remarks
Initially NOWC given with Major, Moderate &
Minor Comments then NONO at 28/02/2024
but on 08/03/2024 NONO withdrawn
28.02.2024 & 08-
D-wall at Victoria 28-12-2023 13-01-2024 20-02-2024
03-2024
For complete Project (DBR, Dwg etc) 09-01-2024 30-01-2024 20-03-2024 27-03-2024 NOWC with Major, Minor & Moderate
comments. Pending with L&T
NOWC with Major, Minor & Moderate
D-wall at Cut & Cover, UG Ramp & 19-03-2024 05-04-2024
comments. Pending with L&T
Cross Over
Tunnel Temporary Segments 06-03-2024 19-03-2024 21-03-2024 26-03-2024 28-03-2024 29-03-2024
NONO has been granted
Definitive Design Submission
Tunnel Permanent Segments &
Cross Passages and Sump 29-03-2024 05-04-2024 Rejected with Comments. Pending with L&T
For complete project 02-04-2024 Under Review
G-Wall (for D-Wall) Layout DWGs of
Victoria Station ON HOLD status due to missing IIT and
27-01-2024 16-02-2024 19-02-2024 15-03-2024 Shifting Issue Confirmations
G-Wall (for Barrettes) Layout DWGs
of Victoria Station
27-03-2024 12-04-2024 Rejected with Comments. Pending with L&T
G-Wall (for D-Wall) Layout DWGs of
Layout Submission
Launching Shaft 13-02-2024 19-02-2024 27-02-2024 29-02-2024 NOWC has been granted with conditions
D-Wall Layout DWGs of Victoria
Station ON HOLD status due to missing IIT and
27-01-2024 15-02-2024 19-02-2024 16-03-2024 Shifting Issue Confirmations
D-Wall Layout DWGs of Park Street
Station Rejected due to Missing PD or DD
09-02-2024 17-02-2024 19-02-2024 26-02-2024 Submissions of Park Street Station
Khidderpore Station 30-03-2024 Under Review
Victoria Station 15-03-2024 18-03-2024 20-03-2024 26-03-2024 Pending with L&T
Geotechnical Factual Report Park Street Station 04-04-2024 Under Review
Launching Shaft 15-03-2024 18-03-2024 20-03-2024 26-03-2024 Pending with L&T
TBM-I Section 22-03-2024 04-04-2024 08-04-2024 Under Review
NOWC with comments. Pending with L&T.
Victoria Station 2nd subm. Withdrawn by 3rd subm.
23-03-2024 04-04-2024 06-04-2024 08-04-2024
Geotechnical Interpretative Report
Launching Shaft NOWC with comments. Pending with L&T
29-03-2024 05-04-2024
TBM-I Section 04-04-2024 Under Review
14/05/2024 19
STATUS OF UG WORK
20
Status of Work: Casting Yard
1. Casting Yard:
• Erection and commissioning of batching plant :Out of total min. 2 nos of batching plant of capacity 60
cum/hr, establishment of 01 no. batching plant (Aggregate bin, Control cabin, Cement silo, Fly ash silo,
Micro silica silo) erection done & commissioning is completed.
• 1st Labor colony foundation work completed & 2nd labour colony foundation work is in progress.
• Weighing bridge installed and hard barricading work done around the weigh bridge.
• QA/QC lab finishing work completed. Lab equipment’s placement & third-party calibration work
completed. 3rd party report awaited.
• Electrical room: Brick work completed. - Room inside plastering and Electrical transformer & panels
fixing work is in progress.
• 10T EOT Crain rail erection & alignment work is in progress.
21
Status of Work: Casting Yard
22
Status of Work: Casting Yard
23
Status of Work: Ramp to Launching Shaft
24
Status of Work– Launching shaft
Kaveri
Mahavir
Dharani
Dhatri
25
Procurement of TBM
2 Completion of Civil Work of KD-08: 50 weeks from date 1. Work of D-wall has not
TBM Launching Shaft and of commencement i.e. yet started.
ready for TBM No.1 & TBM 20.08.2024 2. Guide Wall is in
No.2 progress.
26
Hindrance Photos – Launching shaft
Kaveri
Mahavir
Dharani
Garage of St.Thomas school quarters Waiting hall at St.Thomas school
Dhatri
27
Status of Work: Victoria Station
6. Victoria station:
i. Barricading work has been fixed 910m out of 910m.completed work is 100%.
ii. Guide wall casting completed 550.5m out of 709m. Completion of work is 77%. Entry/Exit
has been not started yet.
iii. 40.5m length portion is hindered by the Trees.
iv. Fountain of Joy demolition work has been completed 100%. (Area filling and compacting
completed).
v. Diaphragm wall back-up system mobilization going on. (2 nos Rig machine, 16 nos.
Polymer tank, stoppers reached at site)
vi. M/s KAMAR has been approved for execution of D-wall work.
vii. Trench has been done for utility identification, coordination with authorities in progress.
viii. TFC Crane reached at site for diaphragm wall Works.
ix. 1 no. Tyre Mounted Crane reached at site for diaphragm wall Works.
28
Status of Work: Victoria Station
29
Status of Work: Victoria Station
30
Status of Work: Park Street Station
31
Status of Work: Park Street Station
32
Status of Work: Park Street Station
33
Status of Work: Esplanade Station
8. EsplanadeStation:
Chainages Length Premises Status
13792.000 –
84 m Mounted Police Paddock Unilaterally handed over to L&T.
13876.000
13876.000 –
32 m Kidderpore Sporting Club & Walkway Unilaterally handed over to L&T.
13908.000
13908.000 –
98 m Dr. B C Roy Market Not Handed Over
14006.000
14006.000 –
30 m Dufferin Road Unilaterally handed over to L&T.
14036.000
14036.000 –
56 m L-20 Bus Stand (WBTC) & Dufferin Road Not Handed Over
14092.000
14092.000 –
21 m L-20 Bus Stand (WBTC) & Dufferin Road Not Handed Over
14113.000
35
TREE TRANSPLANTATION STATUS
Only St
Thomas NOC
Drawing for 84 no Drawing for 420 have been Only St Thomas form
Form 1 ( C )
From Ramp to From Ramp to trees nos. trees received from 1 ( C )have been
1 Private Land 134 96 230 Kamardanga Joka Not applicable sumbitted to DFO on Applied on 16.12.2023
Launching Shaft Launching Shaft transplantation has plantation has concerned received dated
dated 06.03.2024
prepared prepared authority (St. 06.03.2024
Thomas) on
08.11.2023
Clearence Certificate
Drawing for 140
Received from Form 1 ( C )have been obtained on
nos. trees
2 Victoria 14 Victoria 14 28 Prepared Kamardanga Joka Defence on received dated 12.04.20244..Clearan Applied on 02.11.2023
plantation has
19.12.23 27.02.2024 ce certificate
prepared
received from DFO
36
DEPLOYMENT STATUS OF KEY
PERSONNEL OF L&T
37
Status of Work: STATUS OF KEY PERSONNEL
38
Status of Work: STATUS OF KEY PERSONNEL
Sl. No. Discipline Numbers Deployment Status
1 Project Manager (Civil Engineer) 1 Not Deployed
2 Construction Manager (Cut and Cover Tunnel) 1 Deployed
3 Construction Manager (TBM Tunnel) 1 Not Deployed
4 Construction Manager (Civil and Geotechnical) 1 Not Deployed
5 Construction Manager (Stations) 1 Deployed
6 Construction Manager (Facilities) 1 Not Deployed
7 Engineering Manager ( Design and Technical Support) 1 Not Deployed
8 Engineering Manager( Planning and billing) 1 Deployed
9 Station In-charge (One for each station) 4 2 nos. Deployed
10 Chief Track works Engineer 1 Not Deployed
11 Chief Safety Manager 1 Deployed
12 Chief Quality Manager 1 Deployed
13 Chief Architect 1 Not Deployed
14 Chief Interface Engineer 1 Not Deployed
15 Chief Surveyor 1 Deployed
16 Chief Environment Specialist 1 Deployed
17 Traffic and Utility diversion Engineer 1 Deployed
18 Senior Engineer
a Stations 4 Not Deployed
b Tunnel(Cut and Cover) 2 2 nos Deployed
c Tunnel(TBM) 2 Not Deployed
d Civil and Geotechnical 2 Not Deployed
e Planning and Billing 1 Deployed
39
Status of Work: STATUS OF KEY PERSONNEL
40
Status of Work: Geotechnical work and Health Minitoring
41
KEY DATE STATUS
Propose Equival Days Left Difference
Contractu
d ent before Actual (Days)
Key al Status as on
SL Description Weeks Days Contractual Completion between Remarks
Date Completio date
from from Completion Date Contractual
n Date
DOC DOC Elapses and Actual
Minimum
S.L. Age of the Equipment
Equipment Type Number
No
Required
1 Tunnel Boring Machine (EPB_Type) 2 New
45
THANK YOU
14/05/2024