CE (WWM-East) Zone Progress

As on 19-02-2024

1
Upgradation of 248 MLD STP at K&C Valley- Project Details
Drawing approval status and Physical Progress as on 19-02-2024

Last week
Total Already Next week
Particulars Cumulative
Quantity Achieved target
Target Achieved

Drawings 372 161 0 0 161 0

Earthwork in
180613 75884 1500 1500 77384 300
cum

PCC in cum 5268 1323 180 158.5 1481.5 150

RCC in cum 54000 2826 69 13 2839 450


2
SITE PHOTOS

Thickened Sludge Pump House Sludge treatment building PCC


SITE PHOTOS
Anaerobic Digester B Anaerobic Digester C
SITE PHOTOS
Thickener Feed Sump & Pump WAS Filtrate Sump
SITE PHOTOS
Bioreactor Primary sludge sump & pump house PCC