1-04-2024 CE (WWM) - East Progress

You might also like

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 8

CE (WWM-East) Zone Progress

As on 1-04-2024

1
Upgradation of 248 MLD STP at K&C Valley- Project Details
Drawing approval status and Physical Progress as on 1-04-2024

Last week
Total Already Next week
Particulars Cumulative
Quantity Achieved target
Target Achieved

Drawings 372 170 0 0 170 0

Earthwork in
180613 79874 0 0 79874 0
cum

PCC in cum 5268 1830.5 10 10 1840.5 10

RCC in cum 54000 7746.2 1000 1705 9451.2 1500


2
SITE PHOTOS

Anaerobic Digester C Anaerobic Digester B


SITE PHOTOS
Anaerobic Digester A Thickener Sludge pump hose
SITE PHOTOS

Bioreactor Sludge treatment building


SITE PHOTOS

Anammox Reactor A Anammox Reactor B


SITE PHOTOS

Inlet Chamber
THANK YOU

You might also like