Professional Documents
Culture Documents
ACF 503 Lec - 5 Project Budgeting
ACF 503 Lec - 5 Project Budgeting
ACF 503 Lec - 5 Project Budgeting
Direct costs are shown with a downward slope, reflecting the fact that costs will rapidly
ramp up as the schedule shrinks (the time–cost trade-off effect). However, if we also
allow liquidated damage penalties to emerge after the 50-day schedule deadline, we see
that the project team is facing a choice of paying extra money for a crashed schedule at
the front end, versus paying out extra penalties for delivering the project delivery past
the scheduled delivery date. The goal here is to minimize total project cost, represented
as a balancing act between competing cost drivers—crashing costs and the cost of
liquidated damages.
Numerical :
The network and durations given below shows the normal schedule for
a project. You can decrease (crash) the durations at an additional
expense. The Table given below summarizes the time-cost information
for the activities. The owner wants you to you to finish the project in
120 days. Find the minimum possible cost for the project if you want to
finish it on 120 days. (Assume that for each activity there is a single
linear, continuous function between the crash duration and normal
duration points). The activities on the critical path is B-C-D-E
ACTIVITY BASED BUDGETING
Definition of Activity Based Budgeting System
Activity based budgeting is an approach to the budgeting process
that focuses on identifying the costs of activities that take place
in every area of an organization, and determining how those
activities relate to one another.
The data regarding those activities and how they relate to one
another is used to establish goals that allow the organization to
move forward.
Activity based budgeting is more concerned with what is being
done within the organization, how those actions or activities
work together, and then allocating funds to each activity based
on how much it will cost to successfully complete those activities.
Features and Advantages of an ABB System
More realistic - involves looking inward at activities and costs rather
than basing the budget on line items;
Creates financial forecasts that are more accurate;
Prompts the organization to make the most efficient use of its
resources;
Minimizes wasteful spending within an organization - the analysis of
each activity and its contribution to the ongoing success of the
organization means that any activities that do not appear to relate to
other activities within the organization structure may in fact be
unnecessary;
Changes the way in which costs are counted;
It is easier to align with the organization’s Strategic Plan
Provides more flexibility in reallocation of funds than with line
budgeting systems
It helps in setting performance targets and hence suitable for
monitoring
Understanding the concept
Total Budget = Total Excavation Cost + Total Framing Cost+ Total Finishing
Cost
Understanding the concept
Let's consider a simplified scenario for constructing a building with three major activities:
Excavation, Framing, and Finishing.
1. Excavation Activity:
1. Excavation Volume: 500 cubic meters
2. Excavation Cost per cubic meter: $10
3. Total Excavation Cost = Excavation Volume * Excavation Cost per cubic meter
Total Excavation Cost = 500 * $10 = $5000
2. Framing Activity:
1. Number of Frames: 10
2. Framing Cost per frame: $2000
3. Total Framing Cost = Number of Frames * Framing Cost per frame
Total Framing Cost = 10 * $2000 = $20,000
3. Finishing Activity:
1. Square footage to be finished: 1000 sq. ft.
2. Finishing Cost per sq. ft.: $15
3. Total Finishing Cost = Square footage * Finishing Cost per sq. ft.
Total Finishing Cost = 1000 * $15 = $15,000
Total Budget = Total Excavation Cost + Total Framing Cost+ Total Finishing Cost
= $5000 + $20,000 + $15,000 = $40,000
To sum up….
Along with project cost estimation, project budgeting provides
the basis for establishing sound project control and
profitability.
To create an accurate budget for a project, we need to
understand the difference between top-down and bottom-up
budgeting, including their advantages and disadvantages.
Finally, the budget baseline must work in relation to the project
schedule. This necessitates the creation of a time-phased
budget that recognizes the sequencing of project activities and
allows the project team to identify their budget, including
assessing its status on an ongoing basis.
When properly managed, the budget, along with the schedule,
offers the project team the opportunity to apply maximum
control over the project.