Professional Documents
Culture Documents
Schedule & Cost MGT
Schedule & Cost MGT
Management
Lesson Outlines
Project Time Management
progress
ADM
Also called Activity – on - Arrow (AOA) network
diagrams
Activities are represented by arrows
Nodes or circles are the starting and ending
points of activities
Only Finish-to-Start dependencies can be
shown
Where:
◦ The letters A through J represent activities with dependencies that
are required to complete the project
◦ The arrows represent the activity sequencing or relationships
between tasks
Three-Point Estimates
Instead of providing activity estimates as a discrete
number, such as four weeks, it’s often helpful to create
a three-point estimate
Optimistic time
◦ It is based on a best-case scenario
◦ It is an estimate of the minimum time required for an
activity if exceptionally good luck is experienced
The most likely time
◦ It is based on a most likely or expected scenario.
◦ It is the longer duration for the activity
The pessimistic time
◦ It is based on a worst-case scenario.
◦ It is the longest duration for the activity
May 22, 2024 17
Seble E.
Developing the Schedule
Involves analyzing activity sequences, activity
resource estimates, and activity duration
estimates to create the project schedule
Uses results of the other time management
processes to determine the start and end date of
the project
Ultimate goal is to create a realistic project
schedule that provides a basis for monitoring
project progress for the time dimension of the
project
Important tools and techniques include Gantt
charts, Critical Path Analysis, and critical
chain scheduling, and PERT analysis
C A 5
D B 4
E C 7
F D, E 6
G C 6 minimum project
H E 10 completion time?
I D 3
J F, G 4
K H, I 2