Professional Documents
Culture Documents
Kudgi - Boiler Erection Sequence (R0 - 120227)
Kudgi - Boiler Erection Sequence (R0 - 120227)
Kudgi - Boiler Erection Sequence (R0 - 120227)
This erection sequence is intended to guide the installation procedure for Boiler proper and
other part so that works can be performed in accordance with the contract and applicable code,
and the management methods for them can be established.
The erection company must use this as a guide that the method and sequence of erection of
boiler and other part explained in this document.
Therefore this erection sequence must be modified by the erector corresponding
to the site conditions before applying this to the site erection
Only information :
Description in “Boiler Erection Sequence” is information for
erection of whole Boiler parts and details are described
in erection manual or work procedure of each part.
3
Contents of Boiler Erection Sequence
1 BOILER LAYOUT
STEEL STRUCTURE
2
PART
3 FURNACE PART
4 BACKPASS PART
5 EQUIPMENT
6 PIPING
3
1. BOILER LAYOUT
1 BOILER LAYOUT
STEEL STRUCTURE
2
PART
3 FURNACE PART
4 BACKPASS PART
5 EQUIPMENT
6 PIPING
6
2. STEEL STRUCTURE PART_Quantity of Boiler Steel Structure (per Unit)
COLUMN BEAM & MISC STEEL GRATING $ BOLTS
DESCRIPTION WEIGHT UNIT WEIGHT PIECES WEIGHT UNIT WEIGHT PIECES WEIGHT
(TON) (TON/ EA) (EA) (TON) (TON/ EA) (EA) (TON)
Tie r 1 450 14.063 32 947 0.986 960 110
Tie r 2 280 8.750 32 548 0.571 960 69
Tie r 3 451 14.083 32 971 0.971 1,000 110
Boile r Zone Tie r 4 374 11.698 32 806 0.823 980 92
Tie r 5 317 9.902 32 683 0.656 1,040 78
Tie r 6 430 13.438 32 996 0.958 1,040 105
Sub- Tota l 2,302 11.989 192 4,950 0.828 5,980 564
Tie r 1 160 4.717 34 267 0.685 390 39
Tie r 2 116 3.412 34 173 0.407 425 28
AP Zone
Tie r 3 85 3.400 25 180 0.480 375 21
Sub- Tota l 361 3.886 93 620 0.521 1,190 88
Tie r 1 185 6.609 28 296 1.184 250 45
Tie r 2 98 3.494 28 189 0.591 320 24
Mill Zone Tie r 3 173 6.190 28 231 0.722 320 42
Tie r 4 144 5.142 28 192 0.738 260 35
Sub- Tota l 600 5.359 112 908 0.790 1,150 146
7
2. STEEL STRUCTURE PART_Steel Erection (Phase 1)
Foundations ready.
1 BOILER LAYOUT
STEEL STRUCTURE
2
PART
3 FURNACE PART
4 BACKPASS PART
5 EQUIPMENT
6 PIPING
13
3. FURNACE PART_Erection Sequence Overview
Hanger
HangerRods
Rods Links
Links Furnace
Furnace Upper
UpperHeader
Header Separators
Separators
Furn
FurnVertical
Vertical Water
WaterWall
Wall
Reheater
ReheaterHeader
Header Buckstay
Buckstay Furnace
Furnace Roof
RoofPanel
Panel
PNL
PNL
Furnace
Furnace Reheater
ReheaterTube
Tube Division
DivisionSH
SHCoils
Coils Final
Final SH
SHCoils
Coils Arch
ArchPanel
Panel
Furn
FurnINT
INTHDR
HDR&& Burner
Burnerblock
block Spiral
Spiral Panel
Panel Hopper
HopperPanel
Panel
Transition
TransitionPNL
PNL
Ring
RingHeader
Header
14
3. FURNACE PART_Hanger Rods Erection
Erection by winch
15
3. FURNACE PART_Links Erection
Erection by winch
16
3. FURNACE PART_Upper Header Erection
Erection by winch
17
3. FURNACE PART_Separators Erection
18
3. FURNACE PART_Reheater Header Lifting
19
3. FURNACE PART_Buckstay Erection
20
3. FURNACE PART_Vertical Water wall Panel erection
The upper end of the panel shall be directly lifted by means of the
device used for lifting, up to its final position.
The upper end of the panel shall be directly lifted by means of the
device used for lifting, up to its final position.
The upper end of the panel shall be directly lifted by means of the
device used for lifting, up to its final position.
The upper end of the panel shall be directly lifted by means of the
device used for lifting, up to its final position.
The upper end of the panel shall be directly lifted by means of the
device used for lifting, up to its final position.
1 BOILER LAYOUT
STEEL STRUCTURE
2
PART
3 FURNACE PART
4 BACKPASS PART
5 EQUIPMENT
6 PIPING
32
4. BACKPASS PART_Erection Sequence Overview
Hanger
HangerRods
Rods Links
Links Backpass
Backpass Headers
Headers Buckstay
Buckstay
BP
BPRoof
RoofPNL
PNLwith
withECO
ECO BP
BPScreen
ScreenHeader
Headerwith
with
Backpass
Backpass Rear
RearSide
Side PNL
PNL LTRH
LTRHCoils
Coils
Hanger Tubes
Hanger Tubes Screen Tubes
Screen Tubes
BP
BPRing
RingHeader
Header ECO
ECO Outlet
OutletHeader
Header Economiser
EconomiserBundles
Bundles Economiser
EconomiserInlet
InletHeader
Header
Boiler
BoilerPressure
Pressure Parts
Parts Boiler
BoilerPressure
Pressure Part
Part
Economiser
EconomiserCasing
Casing Hydro Test Boundary
Hydro Test Boundary Hydro Test
Hydro Test
33
4. BACKPASS PART_Hanger Rods Erection
Erection by winch
34
4. BACKPASS PART_Links Lifting
Erection by winch
35
4. BACKPASS PART_Headers
Erection by winch
36
4. BACKPASS PART_Buckstay Lifting
37
4. BACKPASS PART_Rear Side Panels
38
4. BACKPASS PART_Rear Side Panels
The upper end of the panel shall be directly lifted by means of the
device used for lifting, up to its final position.
Economizer tube bundles shall be install from left side or right side
in sequence by using the installed trolley.
Hydro test
- The hydrostatic Test is a way of checking leaks which has to give
pressure up to the setting point to inspect of leaks about the shop and
the site welding
Lime silo
point after the boiler erection according to the Code
and regulation
Fly ash Hydro test boundary
conveyor
s - High Pressure Part
(Feed water Pipe + Boiler Pressure Part + Main steam Pipe)
- Intermediate Pressure Part
(Cold Reheater Pipe+ Reheater + Hot Reheater Pipe)
Hydro test
Fuel
presser
conveyors
1ST FILLING
YES
FLUSHING INSPECTION
PRESSURIZING
REPAIR
NO
INSPECTION DRAIN
YES
DE-PRESSURIZING
DRAIN
FINISH
49
4. BACKPASS PART_Boiler Pressure Parts Hydro test
1 BOILER LAYOUT
STEEL STRUCTURE
2
PART
3 FURNACE PART
4 BACKPASS PART
5 EQUIPMENT
6 PIPING
51
5. EQUIPMENT_Air Preheater System
Support
SupportErection
Erection Cold
ColdCenter
CenterSection
Section Main
MainPedestal
PedestalAss'y
Ass'y Support
SupportBearing
BearingAss'y
Ass'y
Rotor
RotorPost
PostAss'y
Ass'y Hot
HotCenter
CenterSection
Section Guide
Guide Bearing
BearingAss'y
Ass'y Side
Side Pedestal
PedestalAss'y
Ass'y
Cold
ColdPri.
Pri. Center
CenterSection,
Section, Primary
Primary Pedestal
PedestalAss'y,
Ass'y, Cold
ColdEnd
EndConnecting
Connecting
Hot
HotPri.
Pri. Center
CenterSection
Section
Cold
Cold EndPocket
End PocketRing
Ring Rotor
Rotor Drive Pedestal
Drive Pedestal Plates
Plates &&Duct
DuctCorners
Corners
Rotor
RotorHousing
Housing&& Hot
HotEnd
EndConnecting
Connecting Rotor
RotorModules
Modules Basket
BasketElements
Elements
Basket
BasketRemoval
Removal Door
Door Plates
Plates & DuctCorners
& Duct Corners
Pin
PinRack
RackAss'y
Ass'y &&
Expansion
ExpansionBlocks
Blocks A/H
A/HLifting
Lifting Seal
Seal Plates
Plates
Rotor
Rotor Drive Unit
Drive Unit
Auxiliary
Auxiliary EQUIPMENT
EQUIPMENT Final
Final Check
Check
53
5. EQUIPMENT_Air Preheater_Centering of Foundation & Support Frame
5. EQUIPMENT_Air Preheater_Lower (Cold) Side Center Section & Setting 54
of Support Bearing
55
5. EQUIPMENT_Air Preheater_Main Pedestals & Rotor Post
5. EQUIPMENT_Air Preheater_Upper (Hot) Side Center Section & Guide 56
Bearing
57
5. EQUIPMENT_Air Preheater_Side Pedestals (Gas Side only)
58
5. EQUIPMENT_Air Preheater_Assembly of Rotor
59
5. EQUIPMENT_Air Preheater_Side Pedestals (Air Side only)
60
5. EQUIPMENT_Air Preheater_Pocket Rings
61
5. EQUIPMENT_Air Preheater_Rotor Housing Panels
62
5. EQUIPMENT_Air Preheater_Lower (Cold) Side Connecting Duct
63
5. EQUIPMENT_Air Preheater_Upper (Hot) Side Connecting Duct
64
5. EQUIPMENT_Air Preheater_Pin Rack Segments
65
5. EQUIPMENT_Air Preheater_Installation of Elements
66
5. EQUIPMENT_Air Preheater_Hot Sector Drive Unit
67
5. EQUIPMENT_Pulverizer
Pulverizer is one of major devices in coal fired boiler. In order to achieve proper combustion, coal
may be grinded, dried and classified.
Raw coal will be fed by Coal Feeder into bowl, which is rotating in the pulverizer, and equally
distributed to Grinding Ring by its centrifugal force, then grinded by Grinding Roll.
Pulverized coal will be mixed and classified with hot air for proper combustion, then transferred to
the Furnace.
68
5. EQUIPMENT_Pulverizer
Separator Body
Grinding Roller
Mill
Mill Base
Base Foundation
Foundation Foundation
FoundationFrame
Frame && Mill
Mill Stand
Stand Mill
Mill Stand
Stand(Ring
(RingDuct,
Duct,
(Concrete)
(Concrete) Gearbox
Gearbox Base Plate
Base Plate (Pedestal
(Pedestal &&Bridges)
Bridges) Gas
Gas Duct &Grouting)
Duct & Grouting)
Classifier
Classifier(Grit
(GritFunnel
Funnel &&
Gear
GearBox
Box &&Motor
Motor Table
TableAssembly
Assembly Mill
Mill Body
BodyAssembly
Assembly Lower
LowerHousing)
Housing)
Rocker
RockerArm
Arm&&Spring
Spring
Classifier
ClassifierAssembly
Assembly Grinding
GrindingRoller
Roller Final
FinalAssembly
Assembly
Assembly
Assembly
70
5. EQUIPMENT_Pulverizer Erection Sequence
Mill Base Foundation (Concrete) Foundation Frame & Gearbox Base Plate
Mill Stand (Ring Duct, Gas Duct & Grouting) Gear Box & Motor
72
5. EQUIPMENT_Pulverizer Erection Sequence
Table Assembly
73
5. EQUIPMENT_Pulverizer Erection Sequence
Final Assembly
78
5. EQUIPMENT_Fan Erection
PA Fan
Supply primary air to the Boiler
FD Fan
Supply secondary air to the
Boiler
ID Fan
Discharging combustion gas
passed EP to stack.
79
5. EQUIPMENT_Installation Sequence Overview of Fan
Positioning
Positioningofofsole
sole
Foundation
Foundationfor
forfan
fan Travel
Travel rail
rail Lower
Lowerpart
partof
ofinlet
inletbox
box
plates
plates
Diffuser
Diffuserplaced
placedon
on
Inlet
InletBox
Box Diffuser
Diffuserparts
parts Bearing
Bearingassembly
assembly
foundation
foundation
Installed
Installedblades
blades Blades
Blades assembly
assembly Motor
Motorin
inposition
position Internal
Internal hub
hubassembly
assembly
Hydro
HydroOil
Oil Unit
Unit&&Oil
Oil Pipe
Pipe Sealing
Sealingair
airunit
unit Vibration
Vibrationcontrol
control
80
5. EQUIPMENT_Fan Single-stage axial flow fan
Impeller
Diffuser casing Inlet box
Coupling
Single stage fan – general overview
Blades Main motor
Main bearing
assembly
80
81
5. EQUIPMENT_Fan Two-stage axial flow fan
Blades
92
5. EQUIPMENT_Fan Motor in position
93
5. EQUIPMENT_Fan Internal hub assembly
Actuator Oil pipes, flow and return lines Hydraulic and lubricating cabinets
95
5. EQUIPMENT_Fan Sealing air unit
96
5. EQUIPMENT_Fan Vibration control
Gas duct :
It’s a duct which carries hot gas up to the Stack via Air Pre-
heater and ID Fan.
98
5. EQUIPMENT_Installation Sequence Overview of Duct
Welding
Welding&&Installing
Installing Secondary
Secondary overfire
overfire air
air
Preparation
Preparation Onsite
Onsite Material
Material Lifting
LiftingLug
Lug duct Lifting
duct Lifting
Duct
Ductto
towindbox
windbox Windbox
Windbox connection
connection Common
Commonair
airSuction
Suction Hot
Hotair
airduct
ductto
tomills
mills
connection
connection
Economizer
Economizerhopper
hoppergas
gas
Cold
Coldair
airduct
duct Gas
Gas duct
ductto
toSCR
SCR SCR
SCRHopper
Hoppergas
gas duct
duct
duct
duct
A.H
A.Hgas
gas outlet
outletduct
duct Gas
Gas duct
ductto
toE.P
E.P Gas
Gas duct
ductto
toI/D
I/D
99
5. EQUIPMENT_Duct Erection
4. Duct to windbox 5. Windbox connection 6. Common air suction
connection lifting air duct lifting duct lifting
102
5. EQUIPMENT_Duct Erection
7. Hot air duct to Mills lifting 8. Econ. Hopper gas duct lifting 9. Gas duct to SCR lifting
10. Gas duct to E.P lifting 11. Fit-up & Welding 12. Duct leak test
5. EQUIPMENT_Sootblowers Arrangement & Erection 103
Profile
- Facility to removal soot on the boiler heating surface
which was accumulated .
- It should be installed through the furnace panel(Water Wall)
- Type : Long & Short Retracing Soot Blower.
Function
Short Soot Blower
- It will be installed on water wall and eliminate attached
particles.
- Motor operating , Rotate 360 degree, Mounted Lance Tube.
Install the Rear Side Eye Bolts enabling it to absorb the thermal ex-
pansion of Front Suspension when the Boiler starts.
1 BOILER LAYOUT
STEEL STRUCTURE
2
PART
3 FURNACE PART
4 BACKPASS PART
5 EQUIPMENT
6 PIPING
106
6. PIPING_Boiler Top Area Internal HP Piping Erection
Lime silo
Fly ash
conveyor
s
Fuel
conveyors
Bottom
ash silo
Fly ash
conveyor
s
Fuel
conveyors
Bottom
ash silo
Fly ash
conveyor
s
Fuel
conveyors
Bottom
ash silo