WASHOUT FAILURE
UNPLANNED EVENT REPORT (UER) # RIG-GERD
DESCRIPTION:
- WHILST DRILLING THE 8.5” SECTION ON 5-1/2” G 105 DP & 5-1/2” HWDP W/FH DSTJ
CONN, OBSERVED PRESSURE DROP IN THE STRING & UPON POOH OBSERVED 1 JT
OF 5-1/2” G105 DP WASHED OUT ON THE RECESS AREA. ALSO OBSERVED THE
ARNCO 350XT HARDBAND ON THE 5-1/2”HWDP ERODED/FAILED.
CAUSE:
- RECALL THE WASHED OUT 5.5” DP & HWDP (HARDBAND FAILED) BACK TO
CONTRACTORS BASE - DONE.
CAT 3-5 INSPECTION WAS PERFORMED ON THE HWDP & DP (CAT-5) TUBULARS
PRIOR TO SENDING TO THE RIG SITE ON BOTH 5-1/2“ DP & 5-1/2" HWDP
“WHILST DRILLING THE 8.5” SECTION ON 5-1/2” G 105 DP & 5-1/2” HWDP W/FHDSTJ
CONN, OBSERVED PRESSURE DROP IN THE STRING & UPON POOH OBSERVED 1 JT
OF 5-1/2” G105 DP WASHED OUT ON THE RECESS AREA. ALSO OBSERVED THE
ARNCO 350XT HARDBAND ON THE 5-1/2”HWDP ERODED/FAILED.
NOTE: DDR-DAILY DRILLING REPORT FOR THE DAY OF THE INCIDENT IS YET
TO RECEIVE FROM THE CLIENT
INTERNAL INVESTIGATION & NCR DETAILS
SEQUENCE OF EVENTS :
- BASED ON THE CALL OUT RECEIVED FROM CLIENT-BORR AS PER RENTAL CONTRACT OGI-RC-
0823- 0194, 3RD PARTY INSPECTION (TUBESTAR) PERFORMED ON THE PIPE ON 24TH OCT 2023
INITIAL VISUAL INSPECTION FINDING RESPONSE CONVEYED TO THE CLIENT ON FEB 6TH
2024
AT THIS STAGE, IT IS IDENTIFIED THAT THE PRIMARY CAUSE FOR THE HARDBAND
FAILURE IS ABRASIVE WEAR DUE THE FRICTION BETWEEN THE PIPE BODY & THE
OPEN HOLE FORMATION.
- THE DRILL STRING IS SUBJECTED TO SEVERE STRESS & ABRASION IN OPEN HOLE
FORMATIONS. DOWNHOLE DRAG, TORQUE & DOG LEG/INCLINATION PLAYS A VITAL
ROLE IN STRESSING THE PIPE BODY, AS THE PIPE CONTINUOUSLY WORKS AGAINST
THE WALL OF THE FORMATION (ECCENTRIC ROTATION & VIBRATION).
- DOGLEGS & HIGH INCLINATION ZONES INDUCE SEVERE CYCLIC LOADS, BENDING OF
THE PIPES THROUGH BOREHOLE FORMATIONS. THE ALTERNATING TENSION AND
COMPRESSION CYCLES SEVERELY IMPACT THE PIPE LIFE AND CAN LEAD TO
PREMATURE FAILURE, THE HOLE INCLINATION ON THIS CASE BEING 73DEG.
INTERNAL INVESTIGATION & NCR DETAILS
- WEAR AT THE TAPER IS CAUSED BY EROSION AND ABRASION FROM DRILLING IN HIGH
ANGLE/DOG LEG ZONES, HARD FORMATIONS, CUTTINGS AND/OR SAND IN THE
ANNULUS IMPINGING UPON THE EXTERNAL UPSET OF THE TOOL JOINT. THE
CUTTINGS IN THE ANNULUS ARE TRANSPORTED TO THE SURFACE BY THE MUD. THE
VELOCITY OF THE MUD MUST BE SUFFICIENTLY HIGH TO ADEQUATELY TRANSPORT
THE CUTTINGS. THE HIGH VELOCITY OF THE CUTTINGS STRIKING THE BOTTOM OF
THE TOOL JOINT CAUSES EROSION OF THE METAL.
INTERNAL INVESTIGATION & NCR DETAILS
- MAJORITY OF WASHOUT FAILURES OCCUR NEAR THE SLIP AREA I.E THE CASE ON
THIS OCCASION, MOREOVER-DIE MARKS FROM SLIPS & TONGS ARE ALSO CAPABLE
OF GENERATING STRESS CONCENTRATION ON THE TRANSITION/DIFFUSION ZONE (I.E
BETWEEN THE TJ TO SLIP AREA) LEADING TO FRACTURE/WASHOUT.
CORRECTIVE PREVENTIVE ACTIONS
OGI WILL SEND THESE TUBULARS FOR DETAILED TESTING & ANALYSIS. MAKING SURE
ALL RELEVANT DOCUMENTS SUCH AS INVESTIGATION REPORTS & COC AVAILABLE
WITH PROPER TEST RECORD AS PER INDUSTRY STANDARD TO AVOID ANY POSSIBLE
REOCCURRENCE.
1) ELEMENTAL ANALYSIS
12
Damaged Beyond Repair (DBR) 01 Box Recut
Conn’
BENT Nil
Total Joints Inspected. 25 Joints
Forward Plan
120 joints of 5 ½” have been inspected at Tuboscope to DS-1 Cat -5 and ready to be mobilized to the rig.
192 joints of 5 ½” were back loaded and are currently being inspected. We should receive summary for first
batch of 60 joints later today.
225 joints (75 stands ) of 5 ½” will be kept in the derrick for spud and top hole section on EB-56.
54 joints of 5 ½” backloaded to be sent for inspection at Tuboscope.
320 joints of 5 ½” ( brand new ) will be in UAE on 10th April.
With 120 inspected joints, 320 new joints and additional 46 joints from drill pipes being currently inspected
we will have required 486 joints of 5 ½” drill pipes with FH DSTJ connections.
25 joints of HWDPs were inspected, 7 joints with hardband issues will be replaced.