Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 29

W-421 Improvement of various roads in CC/CC

Passage, Side strips in CC Passage and Junctions in


Mastic in H/E, H/W, & K/E ward of Zone – III in W.S.

Date Calibri 16pt


Meeting – Progress Review DEC 2023
Date : 23-12-2023 at RO-Mumbai
PROJECT DETAILS
W-421: Improvement of various roads in cement concrete/cement
concrete passage, side strips in cement concrete passage and
Name of Work : junctions in mastic in H/East, H/West and K/East ward of Zone –III
in Western Suburbs Division

Client Detail : BMC


Name of the Contractor : M/s NCC Limited
Quality Monitoring Agency
(QMA) : M/s Femstruct Consulting Engineers LLP
LOA Details : LoA No: Dy. Ch. Eng./SR/10/Roads/WS, Dated: 18.01.2023
Original Project Cost : Rs. 1223.84 Crores (Exclusive of GST)
Bid Number : 7200040339
Commencement Date : 17.02.2023
Contract Duration : 24 Months (Excluding Monsoon)
Original Completion Date : 16.02.2026
Expected completion Date : 16.02.2026

2
W-421 Work Status

Ward
SL No. Description Total
H-East H-West K-East

1 Number Of Roads 43 65 83 191

2 Total Length (m) 19950 29596 32644 82190

3 NOC Received 36 34 63 133

4 Number of Road Started 20 24 28 72

5 Number Of Roads PQC Started 6 8 11 25

3
W-421 Labour Status As On 21.12.2023

SL. No. Ward No. Of Labour Remarks

1 K-East 304

2 H-East 250

3 H-West 247

Total Number Of Labour 801

4
W-421 Resources Status As On 21-12-2023
K-East H-East H-West Total
SL No Resources Unit Remarks
Asset Hire Asset Hire Asset Hire Asset Hire
1 JCB With Breaker Nos. 0 11 0 7 0 5 0 23
2 JCB With Bucket Nos. 0 6 0 8 0 8 0 22
3 Excavator Nos. 0 5 1 2 0 2 1 9
4 Baby Compactor Nos. 0 0 1 1 0 1 1 2
5 Tandem labour Nos. 1 1 1 0 1 1 3 2
6 Dumpers Nos. 4 0 4 0 4 0 12 0
7 Dewatering Pump Nos. 0 5 0 5 0 5 0 15
8 Transit Mixer Nos. 2 2 2 2 2 1 6 5
9 Diesel Generator Nos. 0 2 0 3 0 2 0 7
10 Tempo Nos. 0 1 0 2 0 2 0 5
11 Executive Vehicle Nos. 0 2 0 1 0 1 0 4
12 Utility Nos. 0 2 0 2 0 5 0 9
Total 23 103
5
W-421 Summary of Work progress As on 21-12-2023

SL.NO. Ward Drain UD PQC Remarks

1 H-East 1667.65 1211 557

2 H-West 3053.83 986.60 675.70

3 K-East 2558 1250 452.25

4 Previous 1057 557 558.5


Season

Total 8336.5 4004.6 2243.45

6
W-421 H-East Progress Report
Sr. Ward Name of Road Length Unit Status Drain - (in Rmt.) Sr. Duct - (in Rmt.) C/Way (in Rmt.) Remarks
No. Scope Compl. Balance Scope Compl. Balance Scope Compl. Balance
1 H-Eas t Mahalaxmi Mandir Road 110.00 Rmt In progres s 220.00 135.00 85.00 284.00 70.00 214.00 110.00 40.00 70.00
2 H-Eas t Chetana College Road 190.00 Rmt In progres s 380.00 130.00 250.00 380.00 40.00 340.00 190.00 190.00
3 H-Eas t Manipada Road 200.00 Rmt In progres s 400.00 110.00 290.00 400.00 30.00 370.00 200.00 200.00 31-12-2023
4 H-Eas t S under Nagar Road no. 01 150.00 Rmt In progres s 300.00 130.00 170.00 300.00 110.00 190.00 150.00 150.00
5 H-Eas t Ramanath P arkar Marg 220.00 Rmt In progres s 440.00 100.00 340.00 440.00 70.00 370.00 220.00 220.00
To ta l 870.00 1740.00 605.00 1135.00 1804.00 320.00 1484.00 870.00 40.00 830.00

1 H-Eas t S ant Mary's Road 250.00 Rmt In progres s 500.00 210.00 290.00 500.00 100.00 400.00 250.00 40.00 210.00
2 H-Eas t New Englis h S chool Marg 185.00 Rmt Exc P rogres s 370.00 370.00 370.00 370.00 185.00 185.00
3 H-Eas t Road No. 04 TP S III 260.00 Rmt Exc P rogres s 520.00 0.00 520.00 520.00 0.00 520.00 260.00 0.00 260.00
31-01-2024
4 H-Eas t Vijay Nagar Road 300.00 Rmt Exc P rogres s 600.00 600.00 600.00 600.00 300.00 300.00
5 H-Eas t Chhatrapati S hivaji 250.00 Rmt In progres s 500.00 12.00 488.00 500.00 500.00 250.00 250.00
6 H-Eas t Maharaj
S RoaMarg
hardadevi 190.00 Rmt Exc P rogres s 380.00 380.00 380.00 380.00 190.00 190.00
To ta l 1435.00 2870.00 222.00 2648.00 2870.00 100.00 2770.00 1435.00 40.00 1395.00

1 H-Eas t S ide s trip of CS T Road 450.00 Rmt Exc P rogres s 900.00 900.00 900.00 900.00 450.00 450.00
2 H-Eas t Road no. 11 TP S V 375.00 Rmt Exc P rogres s 750.00 750.00 750.00 750.00 375.00 375.00
15-02-2024
3 H-Eas t Khernagar Road no. 08 320.00 Rmt Exc P rogres s 640.00 640.00 640.00 640.00 320.00 320.00
4 H-Eas t Khernagar Road no. 06 250.00 Rmt In progres s 500.00 85.00 415.00 500.00 0.00 500.00 250.00 0.00 250.00
To ta l 1395.00 2790.00 85.00 2705.00 2790.00 0.00 2790.00 1395.00 0.00 1395.00

1 H-Eas t S ide s trip of Kalina Kurla 1100.00 Rmt In progres s 2200.00 0.00 2200.00 2200.00 250.00 1950.00 1100.00 175.00 925.00
2 H-Eas t Road
S t Anthony Road 1200.00 Rmt In progres s 2400.00 110.00 2290.00 2400.00 127.00 2273.00 1200.00 101.00 1099.00
3 H-Eas t Rajendra Kamble Road 610.00 Rmt Exc P rogres s 1220.00 1220.00 1220.00 1220.00 610.00 610.00
4 H-Eas t J L S hirs hekar Marg 740.00 Rmt In progres s 1480.00 35.50 1444.50 1480.00 85.00 1395.00 740.00 73.00 667.00
5 H-Eas t Aaram S ociety Road 400.00 Rmt In progres s 800.00 800.00 800.00 139.00 661.00 400.00 400.00
6 H-Eas t S ide s trips of Jawaharlal 1800.00 Rmt In progres s 3600.00 190.00 3410.00 3600.00 190.00 3410.00 1800.00 128.00 1672.00
7 H-Eas t Nehru
P R Road
ars hiwadi 475.00 Rmt In progres s 950.00 53.00 897.00 950.00 0.00 950.00 475.00 0.00 475.00 31-05-2024
8 H-Eas t Road from Nanas aheb 400.00 Rmt In progres s 800.00 130.00 670.00 800.00 0.00 800.00 400.00 0.00 400.00
9 H-Eas t Dharmad
Abas aheb S hinde Marg 580.00 Rmt In progres s 1160.00 47.15 1112.85 1160.00 1160.00 580.00 580.00
10 H-Eas t Khernagar Road no. 04 540.00 Rmt In progres s 1080.00 190.00 890.00 1080.00 0.00 1080.00 540.00 0.00 540.00
11 H-Eas t Bhai Tambe Marg 200.00 Rmt Exc P rogres s 400.00 0.00 400.00 400.00 0.00 400.00 200.00 0.00 200.00
12 H-Eas t Road no. 8 TP S III 265.00 Rmt Exc P rogres s 530.00 0.00 530.00 530.00 0.00 530.00 265.00 0.00 265.00
13 H-Eas t S under Nagar Road no. 02 280.00 Rmt Exc P rogres s 1120.00 1120.00 1120.00 1120.00 280.00 280.00
To ta l 8590.00 17740.00 755.65 16984.35 17740.00 791.00 16949.00 8590.00 477.00 8113.00

Cummulative 12290.00 25140.00 1667.65 23472.35 25204.00 1211.00 23993.00 12290.00 557.00 11733.00 7
W-421 H-West Progress Report
Sr. Ward Name of Road Drain - (in Rmt.) Sr. Duct - (in Rmt.) C/Way (in Rmt.)
Length Unit Status Remarks
No. Scope Compl. Balance Scope Compl. Balance Scope Compl. Balance
1 H-Wes t Na tional Library Road 100.00 Rmt In progres s 100.00 87.00 13.00 100.00 100.00 100.00 100.00
2 H-Wes t Road No 5 Riz vi comple x 260.00 Rmt In progres s 486.00 180.00 306.00 486.00 170.00 316.00 260.00 120.00 140.00
31-12-2023
3 H-Wes t S a ibaba Marg 185.00 Rmt Exc Progress 370.00 370.00 370.00 370.00 185.00 185.00
4 H-Wes t Anthony Road 150.00 Rmt In progres s 260.00 64.30 195.70 260.00 32.00 228.00 150.00 101.70 48.30
To ta l 695.00 1216.00 331.30 884.70 1216.00 202.00 1014.00 695.00 221.70 473.30
1 H-Wes t Juhu Road Link Road 18.00 Rmt Exc Progress 0.00 0.00 36.00 36.00 0.00 0.00
2 H-Wes t Junction
5th Rd(Kha r) 230.00 Rmt In progres s 460.00 460.00 460.00 230.00 230.00 230.00 90.00 140.00
3 H-Wes t V M Bhargav Cros s roa d 89.00 Rmt Exc Progress 0.00 0.00 178.00 178.00 89.00 89.00 31-01-2023
4 H-Wes t S ides trip of Juhu Road 400.00 Rmt In progres s 800.00 800.00 800.00 133.00 667.00 400.00 126.00 274.00
5 H-Wes t 14th B Roa d Khar(W) 115.00 Rmt In progres s 230.00 96.00 134.00 230.00 230.00 115.00 115.00
To ta l 852.00 1490.00 96.00 1394.00 1704.00 363.00 1341.00 834.00 216.00 618.00
1 H-Wes t P a li Mala Road 729.00 Rmt In progres s 1458.00 135.00 1323.00 1458.00 0 1458.00 729.00 0 729.00
2 H-Wes t Ta lmiki Road 680.00 Rmt Exc Progress 670.00 670.00 1340.00 1340.00 680.00 680.00
3 H-Wes t P M Road 250.00 Rmt In progres s 500.00 80 420.00 500.00 500.00 250.00 250.00
4 H-Wes t S t. Andrews Road Exte ntion 370.00 Rmt In progres s 700.00 110.00 590.00 700.00 97.00 603.00 370.00 104.00 266.00 15-02-2024
5 H-Wes t 3rd roa d (Y S hape) 560.00 Rmt In progres s 1120.00 1120.00 1120.00 140.00 980.00 560.00 560.00
6 H-Wes t S ide S trip of Manue l 466.00 Rmt In progres s 920.00 58.50 861.50 920.00 57.60 862.40 466.00 42.00 424.00
7 H-Wes t GonsRoad
14th a lves Kha r 690.00 Rmt In progres s 1394.00 300.00 1094.00 1394.00 1394.00 690.00 690.00
To ta l 3745.00 6762.00 683.50 6078.50 7432.00 294.60 7137.40 3745.00 146.00 3599.00
1 H-Wes t Wes t Avenue 340.00 Rmt Exc Progress 680.00 680.00 680.00 680.00 340.00 340.00
2 H-Wes t S t Martin road 340.00 Rmt In progres s 680.00 45.00 635.00 680.00 35 645.00 340.00 0 340.00
3 H-Wes t Ea s t Avenue 340.00 Rmt Exc Progress 680.00 680.00 680.00 680.00 340.00 340.00
4 H-Wes t 11th Road Kha r We s t 1010.00 Rmt In progres s 2020.00 280.00 1740.00 2020.00 2020.00 1010.00 1010.00
5 H-Wes t inc luding
Guruga Ms hwar Road
nge 270.00 Rmt In progres s 540.00 400.00 140.00 540.00 540.00 270.00 270.00
6 H-Wes t 10th Road 130.00 Rmt In progres s 260.00 40.00 220.00 260.00 260.00 130.00 130.00
7 H-Wes t S ide S trip C D Roa d 355.00 Rmt In progres s 710.00 200.00 510.00 710.00 710.00 355.00 355.00
8 H-Wes t 10th Road 677.00 Rmt In progres s 1354.00 300.00 1054.00 1354.00 1354.00 677.00 677.00
9 H-Wes t 17th Road (S antac ruz) 550.00 Rmt In progres s 1100.00 500.00 600.00 1100.00 1100.00 550.00 550.00
10 H-Wes t M G Road 280.00 Rmt In progres s 760.00 83.00 677.00 760.00 760.00 280.00 280.00 31-05-2024
11 H-Wes t S ide s trip Relife Road 770.00 Rmt In progres s 800.00 60.00 740.00 800.00 800.00 770.00 770.00
12 H-Wes t 16th Road Kha r We s t 1010.00 Rmt In progres s 2020.00 35 1985.00 2020.00 0 2020.00 1010.00 0 1010.00
13 H-Wes t Ja ri Ma ri Road 314.00 Rmt Exc Progress 628.00 628.00 628.00 628.00 314.00 314.00
14 H-Wes t S ide s trip of K C Marg 1510.00 Rmt In progres s 1540.00 0 1540.00 1540.00 92 1448.00 1510.00 92 1418.00
15 H-Wes t R K Mis s ion Road 150.00 Rmt Exc Progress 1550.00 1550.00 1550.00 1550.00 150.00 150.00
16 H-Wes t Dr. P e ter Dias Roa d 515.00 Rmt Exc Progress 1030.00 1030.00 1030.00 1030.00 515.00 515.00
17 H-Wes t 30th Road 680.00 Rmt Exc Progress 3020.00 3020.00 3020.00 3020.00 680.00 680.00
18 H-Wes t S ide s trip Kanubha i De s ai 335.00 Rmt Exc Progress 300.00 300.00 300.00 300.00 335.00 335.00
Mata
To rgl 9576.00 19672.00 1943.00 17729.00 19672.00 127.00 19545.00 9576.00 92.00 9484.00
Cummulative 14868.00 29140.00 3053.80 26086.20 30024.00 986.60 29037.40 14850.00 675.70 14174.30 8
W-421 K-East Work Progress Report
Sr. Ward Name of Road Length Unit Status Drain - (in Rmt.) Sr. Duct - (in Rmt.) C/Way (in Rmt.) Remarks
No. Scope Compl. Balance Scope Compl. Balance Scope Compl. Balance
1 K-East MIDC B X Road 445.00 Rmt In progress 890.00 170.00 720.00 890.00 283.00 607.00 445.00 105.00 340.00
2 K-East Prarthana Samaj Cross 120.00 Rmt In progress 240.00 32.00 208.00 240.00 0.00 240.00 120.00 0.00 120.00
3 Road
K-East Dayaldas Main Road ( 110.00 Rmt In progress 220.00 20.00 200.00 220.00 0.00 220.00 110.00 0.00 110.00
4 K-East Part
MIDC 2)A Cross Road 200.00 Rmt In progress 400.00 138.00 262.00 200.00 0.00 200.00 200.00 46.25 153.75
31-12-2023
5 K-East T ejpal Scheme Road no 290.00 Rmt In progress 290.00 290.00 580.00 85.00 495.00 290.00 13.00 277.00
6 2
K-East Bima Nagar Road 225.00 Rmt In progress 450.00 100.00 350.00 450.00 85.00 365.00 225.00 225.00
7 K-East MIDC Road no 14 200.00 Rmt In progress 400.00 167.00 233.00 400.00 74.00 326.00 200.00 74.00 126.00
8 K-East Shivneri Vasahat cross 100.00 Rmt In progress 200.00 80.00 120.00 200.00 70.00 130.00 100.00 100.00
Road
T o ta l 1690.00 3090.00 707.00 2383.00 3180.00 597.00 2583.00 1690.00 238.25 1451.75

1 K-East Dixit Road 385.00 Rmt In progress 770.00 320.00 450.00 770.00 100.00 670.00 385.00 22.00 363.00
2 K-East Baji Prabhu Deshpande 360.00 Rmt In progress 720.00 90.00 630.00 720.00 60.00 660.00 360.00 16.00 344.00
3 K-East Marg
T ejpal Scheme Road no 250.00 Rmt In progress 250.00 250.00 500.00 95.00 405.00 250.00 60.00 190.00
4 K-East 3
T hanawala lane 360.00 Rmt In progress 720.00 130.00 590.00 720.00 100.00 620.00 360.00 98.00 262.00 31-01-2024
5 K-East Natwar Nagar Road no 5 550.00 Rmt In progress 1100.00 132.00 968.00 1100.00 40.00 1060.00 550.00 550.00
6 K-East Natwar nagar Road no 1 400.00 Rmt In progress 800.00 75.00 725.00 800.00 800.00 400.00 400.00
7 K-East New Nagardas Road 290.00 Rmt Exc Progres s 580.00 580.00 580.00 580.00 290.00 290.00
T o ta l 2595.00 4940.00 747.00 4193.00 5190.00 395.00 4795.00 2595.00 196.00 2399.00

1 K-East Sant Mukta Bai Road 590.00 Rmt In progress 1180.00 152.00 1028.00 1180.00 80.00 1100.00 590.00 18.00 572.00
2 K-East N P T hakkar Road 350.00 Rmt In progress 700.00 180.00 520.00 700.00 700.00 350.00 350.00
3 K-East Jeevan Vikas Kendra 500.00 Rmt In progress 1000.00 50.00 950.00 1000.00 1000.00 500.00 500.00
4 K-East Marg
MIDC Road no 7 270.00 Rmt In progress 540.00 50.00 490.00 540.00 540.00 270.00 270.00
5 K-East Sadbhakiti road 470.00 Rmt In progress 470.00 150.00 320.00 940.00 138.00 802.00 470.00 470.00
6 K-East Subhash Nagar 13.40 m 130.00 Rmt Exc Progres s 260.00 260.00 260.00 260.00 130.00 130.00 15-02-2024
7 K-East D.P.Roa
Dattaram Waikar Marg 150.00 Rmt Exc Progres s 150.00 150.00 300.00 300.00 150.00 150.00
8 K-East Guru Govind Singh Road ( 300.00 Rmt In progress 600.00 32.00 568.00 600.00 600.00 300.00 300.00
9 Roof
K-East Sarvodaya nagar Road 470.00 Rmt Exc Progres s 940.00 940.00 940.00 940.00 470.00 470.00
10 GuruRounak
K-East Lok Go Road Marol 200.00 Rmt In progress 400.00 29.00 371.00 400.00 400.00 200.00 200.00
11 K-East S.R. Mahadik Road 570.00 Rmt In progress 1140.00 40.00 1100.00 1140.00 1140.00 570.00 570.00
T o ta l 4000.00 7380.00 683.00 6697.00 8000.00 218.00 7782.00 4000.00 18.00 3982.00

1 K-East T arun Bharat Road 550.00 Rmt In progress 1030.00 131.00 899.00 1030.00 1030.00 550.00 550.00
2 K-East Manjrekar wadi Road 380.00 Rmt In progress 406.00 80.00 326.00 406.00 20.00 386.00 380.00 380.00
3 K-East Mogra Service Road 400.00 Rmt In progress 670.00 130.00 540.00 670.00 0.00 670.00 400.00 0.00 400.00
4 K-East MIDC Road No. 11 500.00 Rmt Exc Progres s 1000.00 1000.00 1000.00 1000.00 500.00 500.00
5 K-East Amartaru Road 470.00 Rmt In progress 940.00 0.00 940.00 940.00 20.00 920.00 470.00 0.00 470.00
6 K-East MIDC Road No. 23 500.00 Rmt In progress 1000.00 50.00 950.00 1000.00 1000.00 500.00 500.00 31-05-2024
7 K-East Kanoji Angre Marg 180.00 Rmt Exc Progres s 360.00 360.00 360.00 360.00 180.00 180.00
8 K-East Veer Makarand Ghanekar 550.00 Rmt Exc Progres s 1100.00 1100.00 1100.00 1100.00 550.00 550.00
9 Marg
K-East Wadarwada Road 200.00 Rmt Exc Progres s 400.00 400.00 400.00 400.00 200.00 200.00
10 K-East T elly Gully Cross Road 325.00 Rmt Exc Progres s 650.00 650.00 650.00 650.00 325.00 325.00
11 K-East Gaonthan Road Marol 500.00 Rmt In progress 1000.00 30.00 970.00 1000.00 1000.00 500.00 500.00
T o ta l 4555.00 8556.00 421.00 8135.00 8556.00 40.00 8516.00 4555.00 0.00 4555.00
Cummulative 12840.00 23966.00 2558.00 21408.00 24926.00 1250.00 23676.00 12840.00 452.25 12387.75 9
PCC Work For SWD At Dixit Road

10
W-421 PCC Curing work

11
W-421 Soling Work For SWD

12
W-421 Shuttering Work For SWD Wall

13
W421- Wall Distribution Bar Binding

14
W-421 PQC Work

15
W-421 Curing Work For PQC

16
W-421 Curing Work For PQC

17
W-421 M-40 Slump Test

18
W-421 Hume Pipe Laying & Ready For Encasement

19
W-421 Utility Duct Curing Work

20
W-421 SWD Slab Casting Work

21
W-421 SWD Raft Casting

22
W-421 Rolling of WMM

23
W-421 DLC Laying Work

24
W-421 Utility Duct Chamber

25
W-421 WMM Spreading & Levelling Work

26
W-421 Groove Cutting Work

27
W-421:-Point to be Discuss
Points to be Discuss
Execution of Soak pits
Stamping Activity to be complete before starting drain side PQC Bay
Cleaning of Drain Vent Before start the slab bottom shuttering
Proper cover should be maintain.
Safe guard of trees
cross bars to be provided at RCC Frames.
Maintain Line & Level
Joint cutting should be complete with in 24 hrs. from PQC slab Casted
Maintainance of Documentation for RA Bills
Maintain Saftey measures
Maintain Pollution control measures
28
Thank You

29

You might also like