Professional Documents
Culture Documents
CHAPTER THREE OMpptz
CHAPTER THREE OMpptz
2 4 40
3 3 43
4 2 40
5 1 41
X=
x 18
= =3 Y=
Y 15
= = 2.5
6 6 6 6
XY n xy = 51.5 632.5 =0.25
b=
x nx
2 2
80 6 3
2 a = b = 2.5-(0.25)(3) = 1.75
The estimated regression equation, therefore, is
= mean
MAD =
e 2 3 1 4 2 5 1 4 22
= = =2.75
n 8 8
MSE =
e 2
=
76
10.86 76/(n-1) = 76 (8-1) = 76/7 = 10.86
n 1 8 1
Safety stock (.25 x Demand forecast) 450 375 275 225 275 400
Ending inventory :( Beginning Inv.+ 450 375 275 225 275 400
production Requirement - demand
forecast)
Safety stock (from the… 450 375 275 225 275 400 From
Straight time cost $26752 $23104 $25536 $25536 $26752 $24320 $152000
(Prdn hrs avail x $4)
Layoff 7,000 0 0 0
inventory 0 1,540 0 0
Shortage 0 0 60,000 0
Subcontract 0 0 0 12,210
.
By: Zenebe El. 2023/24.
The following is called product structure tree,
Note that E appears in three separate places; its total requirements can be
determined by summing the separate amounts, which gives 28.
b) In order to assemble 100 units of X, quantities of each component must be
multiplied by 100:. 100(2) = 200Bs, 100(6) = 600 Ds, 100(28) = 2800 Es, &
100(2) = 200Fs.
By: Zenebe El. 2023/24.
MRP Processing
The essence of MRP is to determined & achieve the
quantity & timing of end items in master schedule.
The process then begins with master schedule.
End Items: MRP-- Master schedule -- BOM file.
Quantities that are generated by exploding the bill
of materials are gross requirements: not include on
hand inventory b/c it is received.
Materials that must actually be required to meet the
demand generated by the master schedule are the
net requirements.
Net requirements in period t = Gross requirements in period t-
project inventory in periodBy:t.Zenebe El. 2023/24.
Cont.…..
Timing & sizes of orders determined by planned-
order releases. Place order.
Timing of receipts these quantities is indicated by
planned-order receipts. Receive order.
Gross requirements: are total expected demand for
an item or raw material during each time
period/production plan.
It include dd not accounted, dd for replacement parts
for units already sold.
Schedule receipts/Open orders are orders that have
been placed but not yet completed or scheduled to
arrive from vendors or elsewhere in the pipeline.
By: Zenebe El. 2023/24.
Cont.….
Project on hand: Expected amount of inventory that will
be on hand at beginning of each time period:
Scheduled receipt + available from last period.
Net requirements: actual amount needed in each T/ period.
Planned order receipt: is a new order not yet released to
the shop or the supplier.
It is the quantity expected to be received.
Planned-order-releases: is indicates when an order for a
specified quantity of an item is to be issued.
When an order is executed, it is removed from the
“planned-order receipts” and “planned-order release”
rows and entered in the “scheduled receipts” row.
Job sequence Processing Time (days) Due Date (Days hence) Flow time (days)
E 1 2 0+1=1
C 2 7 1+2=3
A 3 5 3+3=6
B 4 6 6 + 4 = 10
D 6 9 10 + 6 = 16
T/ flow time 36 Days
Mean flow T. 7.2 Days
SOT results in a lower average flow time than the FCFS rule.
Jobs E and C will be ready before the due date.
job A is late by only one day.
Average a job will be late by (0+ 0+ 1+4+7)/5 = 2.4 days.
By: Zenebe El. 2023/24.
DUE DATE schedule:
Job sequence Processing Time (days) Due Date (Days hence) Flow time (days)
E 1 2 0+1=1
A 3 5 1+3=4
B 4 6 4+4=8
C 2 7 8 + 2 = 10
D 6 9 10 + 6 = 16
T/completion T 39 Days
E 1 2 0+1=1
D 6 9 1+6=7
C 2 7 7+2=9
B 4 6 9 + 4 = 13
A 3 5 13 + 3 = 16
T/completion T 46 days
D 6 9 0+6=6
C 2 7 6+2=8
A 3 5 8 + 3 = 11
E 1 2 11 + 1 = 12
B 4 6 12 + 4 = 16
T/completion T 53 days
A 3 5 1+3=4
B 4 6 4+4=8
D 6 9 8 + 6 = 14
C 2 7 14 + 2 = 16
T/completion T 43 days
FCFS 50 10 4.6
0 5 11 18 21 24
1 6 3 0 0 1 6 3 0 0
2 0 0 5 4 2 0 0 5 2
3 0 2 4 3 3 0 1 4 1
4 0 5 7 4 4 0 4 7 2
1 6+1=7 3 0 0 1 7 3 0 0
2 0+1=1 0 5 2 2 1 0 5 2
3 0 0 3 0 3 0 0 3 0
4 0 3 6 1 4 0 3 6 1