Professional Documents
Culture Documents
Lecture 14
Lecture 14
• It is very important to carefully plan and analyse this critical phase of the project cycle, because
deviations from the original plans and budgets could easily endanger the entire project.
• A primary objective is therefore to determine the technical and financial implications of the
various stages of project implementation, with a view to securing sufficient finance to float the
project until and beyond the start of production.
• A series of simultaneous and interrelated activities taking place during the implementation phase
have to be identified, including the financial implications they might have for the project.
• When preparing the implementation plan for the feasibility study it should also be borne in mind
that, at a later stage, this plan will be the basis for monitoring and controlling the actual project
implementation.
• The implementation schedule must present the costs of project implementation as well as the
schedule for the complete cash outflows (for all initial investments), in order to allow the
determination of the corresponding inflows of funds, as required for financing the investments.
Objectives of implementation planning
• To implement a project means to execute all the on- and off-site work tasks
necessary to bring a project from the feasibility study stage to its operational
stage.
• A realistic schedule should be drawn up for the various stages of the project
implementation phase. This is an essential part of the feasibility study, as the
implementation of every project must be related to a time schedule.
June 2, 2024 4
Objectives of implementation planning
• The implementation plan should then establish a time schedule that combines
the various stages into a consistent pattern of activities that join together into
each other.
• If a construction period of two, three or more years follows, the cost data used
for the investment decision may be several years old by the time of the start-
up.
• Thus it is vital that all cost data are updated and documented to allow for a
continuous cost monitoring by way of both projections and gathering actual
data.
• By comparing the actual data growing during the construction stage with the
data provided in the feasibility study, it will be possible to detect the effects any
cost overruns may have on the financing requirements and overall profitability
of the project.
Objectives of implementation planning
• Implementation planning and budgeting includes the following major tasks:
Determination of the type of work tasks, on- and off-site, that are necessary to implement
the project
Determination of the resources needed to complete the individual tasks and the taking out
of the corresponding costs
Preparation of an implementation budget and cash flow that will ensure the availability of
adequate funds throughout the implementation phase
Documentation of all implementation data allowing the implementation plan and budget,
as well as the forecasts made in the feasibility study, to be updated.
Critical path in project schedule
• Training activities, for example, may start very early when key personnel from
the company participate in out-of-the country training for a long period, while
the training of maintenance technicians and operators is undertaken later
during construction and start-up.
• The team may undertake the entire work or only a part of it. Particularly in the
case of large projects some of the tasks, for example detailed engineering or
supervision of construction and installation works, are often subcontracted.
• The main objective in the appointment of a project team is to ensure that the
execution of all works comply with the implementation plan and budget, and
that proper countermeasures can be enforced in case the actual
implementation work and costs deviate from the plan.
Governmental approvals
• The import of materials, parts and components, may also require the sanction
of governmental agencies at the production stage.
• In all these cases, adequate time should be provided to obtain the necessary
approvals and to avoid creating bottlenecks. It is difficult to specify a fixed time-
frame, as conditions differ from country to country, but in those countries in
which approvals have to be obtained, from 1 to 6 months is necessary in most
cases.
Financial planning
• After the decision to invest has been taken and once the total investment
costs and their scheduling are known, detailed arrangements for project
financing need to be initiated in line with the financial requirements of
project implementation.
• The team should have the necessary authority regarding contractors and
consultants to ensure the efficient and timely implementation of the
project. It would also be an asset if the team members have an intimate
knowledge of local conditions.
The team should not only remain active during the implementation period,
but should ideally form the nucleus of the managerial, technical and
operational staff that is to be put in charge of operating the plant.
Project management and organization
Organizational build-up
• During the stage of organizational build-up the recruitment of human
resources is initiated. The recruitment schedule outlining when personnel in
the various categories is needed depends on the type of manufacture, and the
availability of labour and staff. Training of new employees may begin at a very
early stage, and might require that some of the key people be trained abroad.
• Consequently, the training plan that has been prepared earlier in the feasibility
study is an important planning tool for the implementation team.
Recruitment is too often left to a very late stage, and training programmes are
initiated only when the plant is ready to commence production, leading to
unnecessarily poor capacity utilization in the early production stages
Technology acquisition and transfer
• The acquisition of technology is a key element of the implementation phase.
The selected technology has many legal, financial and technical aspects, and
negotiations with technology suppliers may take considerable time in certain
cases.
• The feasibility study should contain a projection of the time schedule and the
costs related to the acquisition and transfer of the technology chosen for the
project.
• Moreover, the time allocated for the detailed engineering design will depend
on the kind and complexity of the technology.
Detailed engineering and contracting
Detailed engineering
• The final plant layout and design as prepared in the feasibility study will be the point of
departure for detailed engineering.
During the implementation phase the entire documentation for site preparation, ordering of
machinery and equipment, civil works and plant erection will be elaborated.
• An important aspect usually not receiving proper attention is the provision of operating and
maintenance manuals.
In case of different suppliers the manuals should be arranged in such a way that the text,
drawings and diagrams can be easily utilized by the future operators and maintenance
personnel
Detailed engineering and contracting
Tendering, negotiations and award of contracts
• The phase of tendering, negotiations and contract awards includes;
prequalification of contractors, consultants and suppliers
preparation of tender documents
Tendering
evaluation of tenders
contract negotiations and award of contracts.
• The time elapsing until equipment is delivered may also be very long. It ranges
normally from a few months for relatively simple plant and equipment to two
years or more for more complex installations.
Detailed engineering and contracting
• When ordering the equipment, the delivery time should be planned according to the
progress of the erection work on site and the requirements for the various construction
stages, to ensure that the equipment arrives in a sequence that is optimal from both the
delivery and construction points of view.
• All problems related to the transfer of construction and plant equipment must be solved
before delivery to avoid undue delays.
The feasibility study should identify any such problem areas that could be critical for the
feasibility of the project. It may, for example, be necessary to simulate all transport stages
for critical supply items, such as very bulky or heavy machinery and equipment.
• The outcome of the performance test is critical to both suppliers and purchasers
because it has contractual effects.
• The approval of the test by the purchaser is normally the condition for the release of
a retention money to the supplier.
• The test is equally critical for the investors, inasmuch as an unsuccessful performance
test inevitably means a delayed start-up of plant operation and production.
• Although suppliers or contractors will normally have to issue a performance bond, its
value may only be marginal compared with the production loss suffered by the
investors.
Detailed engineering and contracting
• It is a common experience that a badly specified performance test, without a
clear statement of objectives, plant operation and testing procedures, as
well as of the obligations of all parties concerned, often leads to delays and
legal problems.
• The cost estimates are based on the implementation activities and tasks
determined for the project.
Projecting the implementation budget
• For various cost items, standard costs can be found in publicly available reference
material.
• Other cost items such as housing, transport, legal fees and duties may require local
surveys.
• Price and cost estimates should include contingencies for probable price increases,
projected for the most likely starting date of project implementation.
In case the actual starting date is delayed, it will be necessary to update all cost and
income projections and recompute the schedules required for project financial
analysis.