TRANSFORMER
BY
Dr. DURGA SHARMA
EE DEPARTMENT
DR. C. V. RAMAN UNIVERSITY,BILASPUR
• The most common process of drying out a power
transformer is by using a streamlined filter machine
connected across the inlet and outlet oil hose. The
vacuum chamber and oil heater incorporated in the
filter machine are mainly utilized for this purpose.
Before using the filter machine it should be ensured
that the oil previously filled in the machine, must be
drained out and the machine is refilled with the
transformer oil supplied by the manufacturer.
This oil first circulated inside the machine itself for
several times and tested again and again for achieving
required result. If the required result is achieved then
the machine should be connected across inlets and
outlet hose of the transformer and the entire oil should
be circulated through the transformer and filter machine
several times and the oil sample is to be tested during a
specified interval normally after each one hour.
Fig: Transformer drying out curve
The vacuum pump of the filter machine should have the capacity of creating
vacuum as high as possible, but not less than 710 mm of mercury. Where
the tank to keep the oil in the tank under vacuum consistently. This
additional vacuum pump may accelerate the drying out process of the
transformer.
Although, the oil was filled in the transformer under vacuum from the
bottom of the tank, but during drying out process oil is drawn out from the
bottom and fed into the top of the transformer tank. This helps to remove
present inside.
Once the moisture is removed, the IR value will start rising and then
becomes steady. In addition to the drying out process by filter machine,
the transformer can also be heated up by short-circuiting the LV
winding and supplying a reduced voltage at the high voltage terminals.
The value of the applied voltage is so maintained that the
current through the short-circuited winding should be
under 70% of the rated current.
It must also be of observed during heating up the
transformer winding by applying reduced voltage, the
temperature of the oil must not exceed 75oC. At the same
time temperature of the winding must not exceed 90oC.