Competitive Bidding
Competitive Bidding
Competitive Bidding
BIDDING
LEARNING OBJECTIVE/S:
• Become familiar with the steps in
competitive bidding
COMPETITIVE BIDDING
• It is a method of procurement that is open to all interested
and qualified parties.
STEP 1:
STEP 2:
Advertise/Post STEP 3: Short STEP 4: Issue
Submission of
Request for List Eligible Bidding
Eligibility
Expression of Consultants Documents
Requirements
Interest
Step1: Advertise/Post REI
STEP 1:
STEP 2:
Advertise/Post STEP 3: Short STEP 4: Issue
Submission of
Request for List Eligible Bidding
Eligibility
Expression of Consultants Documents
Requirements
Interest
Step1: Advertise/Post REI
Place of
Duration
Posting
Premises of the Seven (7) calendar
Procuring Entity days
Newspaper of
general nationwide One (1) publication • The prescribed modes of
circulation advertising and posting refer to the
PhilGEPS and Seven (7) calendar bare minimum requirements.
Procuring Entity days from date of
(DOH) Website advertisement • Procuring Entity may ensure
widespread dissemination by
resorting to other available modes
of information dissemination.
STEP 1:
STEP 2:
Advertise/Post STEP 3: Short STEP 4: Issue
Submission of
Request for List Eligible Bidding
Eligibility
Expression of Consultants Documents
Requirements
Interest
STEP 2:
Post Eligibility Requirements
Step2: Submit Eligibility Requirements
Period: Eligibility envelopes shall be submitted on or
before the deadline specified in the REI.
STEP 1:
STEP 2:
Advertise/Post STEP 3: Short STEP 4: Issue
Submission of
Request for List Eligible Bidding
Eligibility
Expression of Consultants Documents
Requirements
Interest
Step2: Submit Eligibility Requirements
Conduct
Eligibility
Receive Check
Eligibility
Post/ Envelopes
Advertise
REI
STEP 1:
STEP 2:
Advertise/Post STEP 3: Short STEP 4: Issue
Submission of
Request for List Eligible Bidding
Eligibility
Expression of Consultants Documents
Requirements
Interest
Step2: Submit Eligibility Requirements
Eligibility Check Open Eligilbility envelopes
to determine if a prospective
bidder is qualified to participate in Classify bidders: Eligible/Ineligible
the bidding at hand.
STEP 1:
STEP 2:
Advertise/Post STEP 3: Short STEP 4: Issue
Submission of
Request for List Eligible Bidding
Eligibility
Expression of Consultants Documents
Requirements
Interest
Step3: Shortlist Eligible Consultants
HOPE to
approve
Recommend shortlist
shortlist to
Determine HOPE
shortlisted
Rate consultants
consultants
Eligible based on
Consultants criteria
determined
STEP 1:
STEP 2:
Advertise/Post STEP 3: Short STEP 4: Issue
Submission of
Request for List Eligible Bidding
Eligibility
Expression of Consultants Documents
Requirements
Interest
Step3: Shortlist Eligible Consultants
Rate Eligible Consultants
based on Criteria
Shortlisting
• Consider only those consultants Draw Short list from Eligible
whose contracts are similar in Consultants
nature and complexity to the
contract to be bid, based on the
Recommend Short List to
REI. HOPE
STEP 1:
STEP 2:
Advertise/Post STEP 3: Short STEP 4: Issue
Submission of
Request for List Eligible Bidding
Eligibility
Expression of Consultants Documents
Requirements
Interest
Step3: Shortlist Eligible Consultants
Specify in the REI the set of
criteria and rating system for Shortlist Criteria
short listing of consultants to
be used for the particular Among the factors to be considered are:
contract to be bid.
1. Applicable experience of the
consultant
STEP 5: STEP 6:
Pre-Bid
STEP STEP
Receive
Conferen
and
7: Bid 8: Post-
ce/ Issue Qualific
Bid Open Evalu
Bulletins Bids ation ation
Step5A: Conduct Pre-Bid Conference
Period: (1) The pre-bid conference must be held at least twelve (12)
calendar days before the deadline for the submission and
receipt of bids.
(2) The pre-bid conference shall be held at least thirty (30)
calendar days before the deadline for the submission and
receipt of bids, if a longer period for the preparation of bids is
necessary.
Participant/s: BAC, BAC Secretariat, TWG members, Observers,
End-user/PMO, Technical experts, Shortlisted consultants
Requisites: Prepared TOR and other bidding documents, Bidding docs,
eligibility documents issued, Shortlisted consultants, Conditions
for the conduct of pre-bid conference
STEP 5: STEP 6:
Pre-Bid
STEP STEP
Receive
Conferen
and
7: Bid 8: Post-
ce/ Issue Qualific
Bid Open Evalu
Bulletins Bids ation ation
Step5A: Conduct Pre-Bid Conference
Type of
Conditions
Conference
Mandatory ABC of at least 1M PhP
Discretionary ABC of less than 1M PhP
Requested Approval of the BAC
STEP 5: STEP 6:
Pre-Bid
STEP STEP
Receive
Conferen
and
7: Bid 8: Post-
ce/ Issue Qualific
Bid Open Evalu
Bulletins Bids ation ation
Step5B: Issue Bid Bulletins
Period: At least seven (7) calendar days before submission and
receipt of bids
STEP 5: STEP 6:
Pre-Bid
STEP STEP
Receive
Conferen
and
7: Bid 8: Post-
ce/ Issue Qualific
Bid Open Evalu
Bulletins Bids ation ation
Step5B: Issue Bid Bulletins
Requested Procuring Entity’s Initiative
Eligible bidders may file request for Procuring Entity at its own initiative may
clarifications on any bidding document – issue supplemental/ bid bulletins to
(1) in writing, (2) made at least 10 days clarify or modify provisions of the
before deadline for bids bidding documents
Issued at least 7 days before deadline Issued 7days before the deadline for
for bids bids
STEP 5: STEP 6:
Pre-Bid
STEP STEP
Receive
Conferen
and
7: Bid 8: Post-
ce/ Issue Qualific
Bid Open Evalu
Bulletins Bids ation ation
STEP 6:
Receive and Open Bids
Step6: Receive and Open Bids
Period: Completed in one (1) calendar day
[maximum of 75 days from the last day of
posting of the REI]
Participant/s: BAC, BAC Secretariat, Observers, COA
Representative, Short listed Consultants
STEP 5: STEP 6:
Pre-Bid
STEP STEP
Receive
Conferen
and
7: Bid 8: Post-
ce/ Issue Qualific
Bid Open Evalu
Bulletins Bids ation ation
Step6: Receive and Open Bids
STEP 5: STEP 6:
Pre-Bid
STEP STEP
Receive
Conferen
and
7: Bid 8: Post-
ce/ Issue Qualific
Bid Open Evalu
Bulletins Bids ation ation
F
i
n
STEP 5: STEP 6:
Pre-Bid
STEP STEP
Receive
Conferen
and
7: Bid 8: Post-
ce/ Issue Qualific
Bid Open Evalu
Bulletins Bids ation ation
Step6: Receive and Open Bids
Bidding Scenarios
Only one shortlisted
Bidding proceeds
consultant submits bid
STEP 5: STEP 6:
Pre-Bid
STEP STEP
Receive
Conferen
and
7: Bid 8: Post-
ce/ Issue Qualific
Bid Open Evalu
Bulletins Bids ation ation
STEP 7:
Evaluation of Bids
Step7: Evaluation of Bids
Period: Completed in not more than 21 days after
deadline for receipt of proposals
STEP 5: STEP 6:
Pre-Bid
STEP STEP
Receive
Conferen
and
7: Bid 8: Post-
ce/ Issue Qualific
Bid Open Evalu
Bulletins Bids ation ation
Step7: Evaluation of Bids
Recommend HRB
Negotiate
to HOPEwith HRB
Open envelopes
Evaluate Bids
STEP 5: STEP 6:
Pre-Bid
STEP STEP
Receive
Conferen
and
7: Bid 8: Post-
ce/ Issue Qualific
Bid Open Evalu
Bulletins Bids ation ation
Step7: Evaluation of Bids
Ways of Rating Bids
Individual Evaluation Collegial Evaluation
STEP 5: STEP 6:
Pre-Bid
STEP STEP
Receive
Conferen
and
7: Bid 8: Post-
ce/ Issue Qualific
Bid Open Evalu
Bulletins Bids ation ation
Step7: Evaluation of Bids
Modes of Evaluation
Quality-Based Evaluation Quality-Cost-Based Evaluation
(QBE) (QCBE)
1. Complex or highly specialized
assignments – difficult to precisely
define the TOR and the required
inputs from the consultants
In other cases, the QCBE
procedure shall apply.
2. Assignment can be carried out in
substantially different ways, such
that the proposals are not
comparable
STEP 5: STEP 6:
Pre-Bid
STEP STEP
Receive
Conferen
and
7: Bid 8: Post-
ce/ Issue Qualific
Bid Open Evalu
Bulletins Bids ation ation
Step7: Evaluation of Bids
Expe Qual
HIGH- Plan/
RATED rienc ity of
TECHNI Meth
CAL e/ Pers
PROPO odol
Capa onne
SAL ogy
bility l
STEP 5: STEP 6:
Pre-Bid
STEP STEP
Receive
Conferen
and
7: Bid 8: Post-
ce/ Issue Qualific
Bid Open Evalu
Bulletins Bids ation ation
Step7: Evaluation of Bids
QBE Procedure
A two-stage procedure shall be
adopted whereby each consultant
shall be required to submit his
technical and financial proposals
simultaneously in separate sealed
envelopes.
STEP 5: STEP 6:
Pre-Bid
STEP STEP
Receive
Conferen
and
7: Bid 8: Post-
ce/ Issue Qualific
Bid Open Evalu
Bulletins Bids ation ation
Step7: Evaluation of Bids
QCBE Procedure
The technical proposal together
with the financial proposal shall be
considered in the evaluation of
consultants.
STEP 5: STEP 6:
Pre-Bid
STEP STEP
Receive
Conferen
and
7: Bid 8: Post-
ce/ Issue Qualific
Bid Open Evalu
Bulletins Bids ation ation
STEP 8:
Conduct Post-Qualification
Step8: Post-Qualification
Period: Completed in not more than 7 days from the determination of the
HRB
May be extended by HOPE, but in no case exceed 30 calendar
days
STEP 5: STEP 6:
Pre-Bid
STEP STEP
Receive
Conferen
and
7: Bid 8: Post-
ce/ Issue Qualific
Bid Open Evalu
Bulletins Bids ation ation
Step8: Post-Qualification
Criteria for Post-Qualification
Technical Financial
Legal Requirements
Requirements Requirements
STEP 5: STEP 6:
Pre-Bid
STEP STEP
Receive
Conferen
and
7: Bid 8: Post-
ce/ Issue Qualific
Bid Open Evalu
Bulletins Bids ation ation
Step8: Post-Qualification
Declare HRRB
Notify HRRB of post-qualification
Send request
Verify
to HRB
documents
for
Prepare
additional
and
Post-qualification
check past report
requirements
performance
STEP 5: STEP 6:
Pre-Bid
STEP STEP
Receive
Conferen
and
7: Bid 8: Post-
ce/ Issue Qualific
Bid Open Evalu
Bulletins Bids ation ation
Step8: Post-Qualification
Disqualified Bidders
1. A bidder that has been blacklisted by any
government agency or instrumentality.
STEP 5: STEP 6:
Pre-Bid
STEP STEP
Receive
Conferen
and
7: Bid 8: Post-
ce/ Issue Qualific
Bid Open Evalu
Bulletins Bids ation ation
Step8: Post-Qualification
2 or more
bids
1 bid
submitted HRB
STEP 5: STEP 6:
Pre-Bid
STEP STEP
Receive
Conferen
and
7: Bid 8: Post-
ce/ Issue Qualific
Bid Open Evalu
Bulletins Bids ation ation
Step8: Post-Qualification
Scenarios
HRB fails criteria
Post-qualification
for post
done on 2nd HRB
qualification
No bidder post-
BIDDING FAILURE
qualifies
STEP 5: STEP 6:
Pre-Bid
STEP STEP
Receive
Conferen
and
7: Bid 8: Post-
ce/ Issue Qualific
Bid Open Evalu
Bulletins Bids ation ation
STEP 9:
Award Contract
Issue Notice of Award (NOA)
Step9: Award Contract, Issue NOA
Period: Recommendation for award should be approved within 7
days from the date of receipt
Contract award should be made within bid validity period
Participant/s: HOPE, BAC, Procurement Office, BAC Secretariat,
HRRB/SRRB Consultant, Observers, COA Representative
Requisites: Post-qualified HRB has been declared HRRB/SRRB
Purpose: To finally decide on awarding the contract to the most
qualified bidder, based on the prescribed criteria and
procurement rules, and inform bidder of such fact
Tasks: Issue resolution to recommend award of contract
Approve/disapprove contract award
Determine compliance with additional requirements
Contract signing
STEP 9:
Award
STEP 10:
Contract
STEP Imple
Contract, 11: Issue
Issue
Signing
Notice to ment
and
Notice of
Award
Approval
Proceed ation
Step9: Award Contract, Issue NOA
Compliance with
Contract
requirements
signing
Post-qualified
BAC
HRB
recommend
declared
HOPEasaward
approval
HRRBof contract
of contract award
STEP 9:
Award
STEP 10:
Contract
STEP Imple
Contract, 11: Issue
Issue
Signing
Notice to ment
and
Notice of
Award
Approval
Proceed ation
Step9: Award Contract, Issue NOA
Contract Agreement
Bidding Documents
Winning bidder’s bid
Performance Security
CONTRACT Credit line, if applicable
Notice of Award (NOA) of Contract
Other contract documents required
by existing laws and/or the procuring
entity.
STEP 9:
Award
STEP 10:
Contract
STEP Imple
Contract, 11: Issue
Issue
Signing
Notice to ment
and
Notice of
Award
Approval
Proceed ation
STEP 10:
Contract Signing and Approval
Step10: Contract Signing, Approval
Period: Contract must be signed by the parties within 10
days from receipt by the winning bidder of the
NOA
Participant/s: Procurement Office/End-user, HOPE/approving
authority, Winning bidder
STEP 9:
Award
STEP 10:
Contract
STEP Imple
Contract, 11: Issue
Issue
Signing
Notice to ment
and
Notice of
Award
Approval
Proceed ation
Step10: Contract Signing, Approval
Contract Signing Approval by authority
NOA, ProcurementContract
Securitypreparation
and other Requirements
STEP 9:
Award
STEP 10:
Contract
STEP Imple
Contract, 11: Issue
Issue
Signing
Notice to ment
and
Notice of
Award
Approval
Proceed ation
Step10: Contract Signing, Approval
Contract Signing Guidelines
STEP 9:
Award
STEP 10:
Contract
STEP Imple
Contract, 11: Issue
Issue
Signing
Notice to ment
and
Notice of
Award
Approval
Proceed ation
Step10: Contract Signing, Approval
Contract Signing Guidelines
STEP 9:
Award
STEP 10:
Contract
STEP Imple
Contract, 11: Issue
Issue
Signing
Notice to ment
and
Notice of
Award
Approval
Proceed ation
Step10: Contract Signing, Approval
What is the Performance Security
STEP 10:
STEP 9: Award STEP 11: Issue
Contract
Contract, Issue Notice to Implementation
Signing and
Notice of Award Proceed
Approval
STEP 11:
Issue the Notice to Proceed
(NTP)
Step11: Issue Notice to Proceed
Period: Within 3 days from the date of approval of
contract
Participant/s: Procurement Office/End-user,
HOPE/approving authority, Winning bidder
STEP 10:
STEP 9: Award STEP 11: Issue
Contract
Contract, Issue Notice to Implementation
Signing and
Notice of Award Proceed
Approval
Step11: Issue Notice to Proceed
Post Notice
to Proceed
Issue Notice in PhilGEPs/
to Proceed Website
Contract
Signed and
Approved
STEP 10:
STEP 9: Award STEP 11: Issue
Contract
Contract, Issue Notice to Implementation
Signing and
Notice of Award Proceed
Approval
Step11: Issue Notice to Proceed
Notice to Proceed
STEP 10:
STEP 9: Award STEP 11: Issue
Contract
Contract, Issue Notice to Implementation
Signing and
Notice of Award Proceed
Approval
Step11: Issue Notice to Proceed
Issuance of the NTP
• NTP shall be issued together with copies of the approved
contract to the successful bidder within 3 days from the
date of approval of the contract.
• The contract effectivity date shall be provided in NTP. It
should nt be later than 7 days form NTP issuance.
• BAC Secretariat, shall post a copy of the NTP and the
signed contract within 15 days from the issuance of the
NTP. STEP 10:
STEP 9: Award STEP 11: Issue
Contract
Contract, Issue Notice to Implementation
Signing and
Notice of Award Proceed
Approval
END OF PROCUREMENT
PROCESS.
START OF
IMPLEMENTATION.