PS Network Design Solution Training Material
PS Network Design Solution Training Material
PS Network Design
Solution Training
Material
ISSUE1.0
www.huawei.com
Internal More engineers are needed, and more skills are needed.
Requirement No deep communication with customer, can not focus on
requirement of operator.
ATM
More packet switch technology is used by PS network
STP A/B
STP1H/2H
More complex because of bigger network
STP C/D Need to consider the whole network because network structure
VMSC GMSC
MSS1H MSS2H MSS4H MSS5H MSS6H MSS7H MSS10H MSS11H MSS13H MSS14H MSS15H
MSC
MSS3H MSS8H MSS9H GMSS1H GMSS2H
is more complex
Server
Need to deal with the risk maybe existed to ensure the deliver
Provide the best target Provide Provide uniform data Provide data
network plan and interconnection configuration for the configuration script
evolution solution for scheme of target whole network, require of single site,
more than two years network and service the key interconnection according to LLD
development, according implementation to parameters, and guide data configuration
to existing network, operator. to make DD, according criterion and
number of subscribers to HLD scheme and scheme provided
Require reasonable configuration criterion
forecast, service analysis by HLD.
resource from of device products.
and the direction of
operator.
future network.
Training material guides to deliver HLD/LLD, and provides function: network design training.
The output of research information template is the input of HLD/LLD template and bandwidth
calculation template, needing cooperation of operator.
HLD/LLD referrence guide guides delivery engineer to design network according to HLD/LLD
template, and export design document.
DD referrence guide guides delivery engineer to configure script according DD tool.
HL When the target network and network evolution strategy is clear, then design the core network scheme and
peripheral interface scheme, finally design the feasible core network.
D
LLD guides the project implement, it must describe the details of network
LL interworking, service deploy and data configuration.
D
HUAWEI TECHNOLOGIES CO., LTD. HUAWEI Confidential Page 11
Question
Project Startup
4.DD DD Service
Project Implement, Cutover
C Participate in discussing
u Confirm HLD Confirm
s plan Information supply Acceptance &
to P08-0303 scheme
m P08-0203 Participate in discussing P08-0403
affirmance
e P08-0102
r LLD P08-0404
g P08-0304
u d R
te a e a e
a ra ve n se
m n
te lo d a
rc P08-0305
p h
e
Output
Network Existing Network Confirm
and Target Design HLD LLD Item Item
Design Summarize
Network Requirement Check
Project Plan
Information of Operator
Input Project
Information Contract BoQ Equipment Service Technology
Technology Proposal Proposal
Method of Network
Design Project Criterion of Referrence Template Bandwidth Calculation
Project Flow Guide Template and Referrence
Guide
Carrier
W W W W
Start Information collect phase Design phase Consummate phase Acceptance phase
meeting
Huawei
W Workshop
In charge of outputting network design deliver document. Clarify information research of network design in early days.
Network design Technical support is the responsibility main body in network design delivering.
deliver team Research and develop maybe support delivering project according to the particular project requirement. Deliver team
compose of GTS and General Headquarters staff .
Assist role in work flow , in charge of confirming and reviewing network design work plan, pushing and coordinating that
Project Manager
what network design require resource, arranging and coordinating carrier’s resource, pushing acceptance.
(PM)
Assist role in work flow , in charge of providing technical proposal, BOQ and result of Dimension, network scheme, or
network scheme after network planning, service and function list, RFQ.
Pushing sign secret protocol and coordinating relationship with customer.
Sales Manager
Help delivering HLD document (function requirement and confirm scheme change).
Generally , relate to product manager and customer manager.
Assist role in work flow , provide requirement confirm document, clarify the conclusion of requirement confirm
MKT Manager document, inform the requirement change to network design staff opportunely.
In charge of providing information, confirming network plan and design scheme, discussing scheme, reviewing scheme joint
Customer and checking before acceptance.
Research Assist role in work flow , participate in deliver document reviewing, ensure the quality of deliver document.
guarantee team Analysis and confirm potential requirement of discussing with customer in network design process.
Network HLD Network design TSD and High Level Design is one of the network design deliver
design phase deliver team customer documents. The responsibility main body of network plan
and design is TSD, research and develop staff support
delivering HLD according to actual project.
LLD Network design TSD and Low Level Design is one of the network design deliver
deliver team customer documents. TSD in charge of delivering LLD.
DD Network design TSD and Deploy Design is one of the network design deliver
deliver team customer documents. TSD in charge of delivering DD.
Bandwidth Network design Network design One of the documents in preparing phase, part of network
calculation deliver team deliver team design.
document , TSD
Day report Person in charge Project leader, One of the documents in process in information research
for project of network design network design phase, report project progress so that make sure related
deliver deliver team people understand situation and take rescue step.
Deliver and Acceptance Person in charge Project Deliver document of network design for delivering and
check upon check report of network design manager, checking upon delivery.
deliver phase customer
Start working Huawei Introduce Network Design contents, process and Planning, ensure both side interface information.
meeting
Operator 1. Ensure Network Design delivery Planning; 2. Advice other requirements; 3. Supply operator cooperation interface
information.
Initial Huawei 1. Be ready to output HLD/LLD initial document; 2. Organize internal review, then modify.
document
Solution Huawei 1 、 Booking operator interface engineers to communicate for key technology; (could be discuss based on initial
review document) 2. Discuss and clarify HLD/LLD question; 3. Complete design document update according to
communication and review information in time.
Operator 1. Communicate solution and clarify correlated information cooperating with Huawei engineers. 2.Review design
document internal based on planning.
Review with Huawei 1. Review and update HLD/LLD with HQ experts together.
Huawei HQ
together
Acceptance Huawei 1.Review document one chapter by one chapter with operator ,to reach the consistency finally; 2. Update the document
according to operator’s opinions; 3. Drive customers to check and accept ,signature; 4. Collect customers opinion
and suggestion about design process and contents.
Operator 1. Manager specify interface colleague to review one chapter by one chapter cooperating ,to reach the consistency finally;
2. After finish all contents affirm , to check and accept ,signature;
3. Feed back or suggest.
Filter information through information research template , pre-RFP ( requirements suggestion report), RFQ (requirements
quotation bill), BOQ( including the list of device function ,License bill), research of requirements and so on.
Must communicate to market abundantly, ensure just one question never enquire customers twice.
Network design delivery colleague clear up proper information research template of xxx project ,according actual situation
of xxx project ,combine to existing information research template and anciently delivery experience.
Pickup useful information from existing documents. fill it in template, quire information by chapter as composing , to
grasp the entire information.
List the not related to information with easy and simple form, send it to customers to collect. Minimize the pending time
to collect information as soon as possible ,could monitor it by question tract form.
For fed information ,obviously or no routine information ,to list it to customers ,invite the customers to affirm. After the
affirm by customers ,it doesn’t make sense , to mark it during the compose ,to alarm this information to customers.
Information research accompany the entire Network Design progress, to research and ensure it in time as information is not clear.
Review is passed in the internal compose team. Send the unsure information to review to NTS and market people, NTS
just emphasize the feasibility and correct of solution, market just check the description of delivery is consistency with their
market policy, or to check whether the solution is correct, avoid not consistency between market propagandize and network
design delivery.
Send delivery documents to customers for review ,after the review of market (meeting or Email is adopted to
communicate). If it is necessary, please apply NTS engineers to review. Must predate with customers ahead of
schedule ,ensure the place and schedule ,if meeting is adopted to review network design delivery. The summary of meeting
must be output, after the end of review meeting. to complete the modify and consummation of delivery ,according to the
review opinion of customer .submit the perfect delivery to customers, to mark the modify contents and result in the Email.
In order to review the modified contents for customers.
BoQ.
The requirements and research documents submit to customers (for example , during the process of first deployment, CDR
development document, business interface documents and so on are needed ).
Solution alteration
After new version is released, old versions will be deleted from network.
How to get CN design
Select installed packet Write application Approved Download
Core Network Design The Network Design service function install packet which Necessary
Tool(Mandatory).exe is integrated with the UniSTAR Designer NetworkDesign
V200R002
MBB Network Design Solution.exe Network Design service function install packet. Supporting Necessary
network design of GU PS, CDMA PS, WiMAX , SAE , UAG and
Convergence GUL domain.
Note: Network Design service function install packet contains all the documents and auto function of different domain,
including information research template, design template, design guide, bandwidth calculate template and guide, DD
Tool.
Type Introduce
Reference Picture Provide the pictures that can be edit, convenient for design delivery
project delivery Contains the templates that will be used during the network design
guide delivery, such as project delivery guide, daily report template,
project plan and task trace template, carrier review summary
template
The problems, suggestions or requirements of network design product discovered in using, are all in the
maintenance scope. These can be fed back through maintenance channel of network design.
Problems
Documents reviewing of
Maintenance project can be submit through
this channel.
Suggestions
or
Difficult
Requirement or Help
Note: The problems of devices are not in this scope. The mode of dealing with is that technology
service engineer submits to device (such as: MSOFTX 3000), then device maintenance
department engineer analyses problem. If the problem can be solved in network design, it will be
transferred to network design department.
Modification in version
The problem will be solved in new version.
Release Fore-alarm
If the problem in use or discovered by chick-list is grave, emergent and
solution-level, or grave problem of network may be caused, need to
release fore-alarm.
The fore-alarm will be cancelled in one month after solved in new
version.
Input directly
Adopted for: The area that can not used NOTES can input table by send Email to other person to help
he fill the table.
Adopted for: Must used the template that set in workflow and update the template periodic
Adopted for: apply for foreign nationality staff that in the area can not access NOTES.
Adopted for: Need person specially assigned for transfer the WEB input requirement to NOTES,
response not quick.
Representative Y
If resources suffice Send resources Start project
office
N
Headquarter
Headquarter
Headquarter NTS collects the recourse plan NTS PMO
The delivery project of network design must be CN network design service sailed
by region, including:
CN network design service sailed singly;
CN network design service sailed with devices.
Introduction of flow:
The gain of all CN network design project delivery resources are assigned by region first. If
the region can not suffice, please apply requirement to headquarter NTS through region NTS.
Headquarter NTS drives TSD to supply resources through Service Planning Committee.
Service Planning Committee of headquarter NTS accepts the requirement of global CN
network design service resources, and answers for minister of region NTS in principle. Region
NTS is the only interface of headquarter delivery resource requirement by representative office
or region.
Service Planning Committee of headquarter NTS audits every delivery resource
requirement, verifies delivery resources skill mode with region NTS. If the project needs the
support of headquarter expert, the resource will be arranged by the focal point of headquarter
NTS Delivery Management Dept. – baohuaping(00162420).
Y
10. R&D support
End
9. If it Compliance the support 1. If not have enter template and support requirement template, retune the workflow to the NTS. R&D unit focal point
condition?
2. If answer for support requirement, recode the support project and arrange the people to support Each domain focal point
the project.
10. R&D support 1. R&D interact the frontline by NTS when support the project. R&D support
2. R&D answer the project support by answer template when process the workflow.
I. Project deliverable review: commit answer after review complete.
II. Technology consultation : commit answer after solve the problem.
III. Project deliverable composed support by headquarter : commit answer after deliverable
composed complete.
IV. business trip to support the project : commit answer after complete the task of business
trip.
3. The workflow can not be closed before confirm the problem have been solved with the NTS
focal point .
11. Close transaction workflow 1. R&D closed the workflow after commit the answer to NTS and NTS confirm the task have R&D support
been solved.