Work Status - 11th BoD 09.12.2022
Work Status - 11th BoD 09.12.2022
3
Project Layout – Water conductor system
Project milestones as per Cabinet sanction
PROJECT SANCTION DATE : 11.02.2021
COMMISSIONING - SCHEDULE : 60 MONTHS FROM DATE OF PROJECT SANCTION
ANTICIPATED COMMISSIONING : FEB - 2026
Sl. No. MILESTONES SCHEDULED DATE
1 2 3
Formation of JV, transfer of clearances and 11th month from date of project sanction
1
Award of EPC Contract [10.01.2022 (Target) / 18.01.2022 (Actual)]
50th month from date of project sanction
2 Completion of Power House
(April’2025)
52th month from date of project sanction
3 Completion of Dam
(June’2025)
57th month from date of project sanction
4 Unit-1 ( 250 MW)
(Nov’2025)
5 Unit-II ( 205 MW) 58th month from date of project sanction (Dec’2025)
6 Unit-III ( 205 MW) 59th month from date of project sanction (Jan’2026)
7 Unit-IV ( 205 MW) 60th month from date of project sanction (Feb’2026)
8 Aux Unit (30 MW) 60th month from date of project sanction (Feb’2026)
Construction Milestones For Turnkey Execution of Ratle
HE Project
Target Dates from date of
Sl. No Description
commencement of work
Completion of excavation and lining of
Milestone 1 14th month
Diversion tunnel
Milestone 2 Completion of excavation of Power House 23rd month
Milestone 3 Availability of EOT crane in Power House
30th month
for machine erection
Milestone 4
Completion of Dam works 47th month
New work fronts are to be opened up for which M/s. MEIL / M/s. AFRY
Switzerland has been pursued regularly for early submission of design
drawings / documents which includes
(1) D/s Surge chamber excavation
(2) Transformer cavern excavation
(3) Dam abutment stripping
(4) Power Intake excavation
(5) Power House excavation
(6) TRT Excavation
(7) RCC Trial mix & additional geological investigation require.
(8) CWPRS hydraulic model study report etc.
Pending issues with GoJK