Professional Documents
Culture Documents
10 14092010 MRP
10 14092010 MRP
MRP
Structure of the MRP System
Master Production
BOM
Schedule
MRP by Period Report
Exception report
Lot-for-Lot
EOQ
Periodic Order Quantity
Fixed Order Quantity
Part Period Balancing
Calculation Sheet
Week
1 2 3 4 5
Gross Requirements
Scheduled Receipts
On Hand
Net Requirements
Planned Receipts
Planned order releases
MRP Example
Week
1 2 3 4 5 6
Gross Requirements 120 340 310 530 410 380
Scheduled Receipts 275
On Hand 650
Net Requirements
Planned Receipts
Planned order releases
Week
1 2 3 4 5 6
Gross Requirements 120 340 310 530 410 380
Scheduled Receipts 275 0 0 0 0 0
On Hand 650 805 465 155 0 0
Net Requirements 0 0 0 375 410 380
Planned Receipts
Planned order releases
Bal Inv
Week
0 1 2 3 4 5 6
Gross Requirements 120 340 310 530 410 380
Scheduled Receipts 275 0 0 0 0 0
On Hand 650 805 465 155 100 100
Net Requirements 0 0 0 375 310 280
Planned Receipts 0 0 0 475 410 380
Planned order releases
Bal Inv 805 465 155 100 100 100
Week
0 1 2 3 4 5 6
Gross Requirements 120 340 310 530 410 380
Scheduled Receipts 275 0 0 0 0 0
On Hand 650 805 465 155 100 100
Net Requirements 0 0 0 375 310 280
Planned Receipts 0 0 0 475 410 380
Planned order releases - - - 475 410 380 -
Bal Inv 805 465 155 100 100 100
Week
1 2 3 4 5 6
Gross Requirements 120 340 310 530 410 380
Scheduled Receipts 275
On Hand 650
Net Requirements
Planned Receipts
Planned order releases
Week
0 1 2 3 4 5 6
Gross Requirements 120 340 310 530 410 380
Scheduled Receipts 275 0 0 0 0 0
On Hand 650 805 465 155 100 100
Net Requirements 0 0 0 375 310 280
Planned Receipts 0 0 0 475 410 380
Planned order releases - - - 475 410 380 -
Bal Inv 805 465 155 100 100 100
Week
1 2 3 4 5 6 7 8 9 10
Gross
20 10 20 25 0 15 10 20 0 30
Req
Week 1 2 3 4 5 6 7 8 9 10
Gross Req 50 0 40 90 110 0 30 40
Co = 160/order
Ch = 1/unit/week
Part Period Balancing: Example
Week 1 2 3 4 5 6 7 8 9 10
Gross Req 50 0 40 90 110 0 30 40
Co = 160/order
Ch = 1/unit/week
Week 1 2 3 4 5 6 7 8 9 10
Gross Req 50 0 40 90 110 0 30 40
Co = 160/order
Ch = 1/unit/week
Week 1 2 3 4 5 6 7 8 9 10
Gross Req 50 0 40 90 110 0 30 40
Co = 160/order
Ch = 1/unit/week
Week
1 2 3 4 5 6 7 8 9 10
Gross
20 10 20 25 0 15 10 20 0 30
Req
Master production
RCCP schedule
Change master
Change requirements? production schedule?
MRP
Change capacity?
CRP
Realistic
No
Yes
Execute material plans
Scheduling
ERP