INDODE Maintenance

center
Mechanical workshop
3rd Week Of March Weekly
Report
Date: MAR 15-21/2024 G.C
INTRODUCTION

COMPLETED WORKS
CONTENTS
PLAN FOR NEXT WEEK

STUMBLING BLOCKS
INTRODUCTION

Mechanical Workshop is responsible for the maintenance


of machine, machineries and equipment's such as railcars,
tamping machines, stabilizer machine, ballast collector
machine, generators, pumps, Hydraulic track lining
machine, cranes, Internal combustion Track wrench and
Vehicles . Besides, it builds and maintains different
structures by welding.
INTRODUCTION

• Based On New organizational Structure Mechanical


Maintenance Workshop Has 3 Teams

1 Machinery Maintenance

2 Mechanical Maintenance

3 Large Machine Operation


STAFF SIZE
S/N Staff position Number of Remark
staffs

1 Mechanical workshop manager 1

2 Team leaders 3 1 vacant


3 Operator, Tamping Machine 6 3 vacant
4 Operator, Stabilizer Machine 1 1 vacant
5 Operator, Ballast distributor 1 1 vacant
6 Technician, Electrical 1
7 Welder 4 1 vacant
8 Electrical Mechanical Fitter 4
STAFF SIZE continued …

S/N Staff position Number Remark


of staffs
9 Assistant Technician, Mechanical 4

10 Technician, Vehicle Maintenance 2

11 Technician, Generator Maintenance 2 1 vacant

12 Technician, Pump Maintenance 2 2 vacant

13 Technician, Gantry Crane Maintenance 2 2 vacant

14 Technician, Mechanical 4 2 vacant

Total no of staffs 37 14 vacant


Mechanical maintenance workshop
Weekly Report in MAR. 2024
Completed works
S/N Equipment, User unit Maintenance highlight Quantity of Spares and
Vehicles or equipment/ materials used
machinery's vehicle/
name machinery
maintained

1 Isuzu tool car indode wheel cylinder came 1 0.5kg greases, 1


(plate no AA leakage and changed wheel cylinder
A66485) other old wheel cylinder
from other damaged car
and maintain stop light
2 civil rail car indode gear sanding b/c gear 1 sanding papers and
width small than gear gasoil(fuel)
shaft run

3 civil rail car mieso transmissions(gearbox) 1 two new ball


two ball bearing bearing
assembled but broken
Mechanical maintenance workshop
Weekly Report in MAR.2024
Completed works
S Equipment, Equipme Maintenance highlight No of Spare and
/ Vehicles or nt, equip material used
N machinery's name Vehicles ment/
or machi
machiner nery
y's name maint
Use unit ained

4 ETS rail car indode changed one new solenoid 1 used one new
because old solenoid is solenoid
loose air and back to normal

5 planting labu hanged spark plug and 1 spark plug


machine(push maintain carburettor
machine)

6 loader machine indode left and right(three hydraulic 1 three set new
piston) changed all old seal hydraulic piston
ready to assembled on the seal and five
loader machine gasoil fuel for
Mechanical maintenance workshop
Weekly Report in MAR.2024

Completed works
S/ Equipment, Equipment, Maintenance No of Spare and material
N Vehicles or Vehicles or highlight equipment used
machinery's machinery's /machiner
name name Use y
unit maintaine
d

7 isuzu tool matahara maintain oil engine 1 6L engine oil


car(plate no ET service, lubricant used,2kg grease
A22500) proper shaft and
steering system

8 iveco tool car matahara maintain handing 1 -


(plate no AA pump(manual
A64688) pump) back to
normal system

9 isuzu tool car indode changed steering 1 used one new


pump belt steering pump belt
Mechanical maintenance workshop
Weekly Report in MAR.2024

Completed works

S/ Equipment, Equipment, Maintenance No of Spare and material


N Vehicles or Vehicles or highlight equipment used
machinery's machinery's /machiner
name name Use y
unit maintaine
d

7 iveco tool indode connecting bolt 1 -


car(plate no AA proper shaft
A79682) tighten
Mechanical maintenance workshop
Weekly Report in MAR.2024

Planned vs completed
S.N Equipment/ machinery/ Requested Completed PERCENTAG
vehicle E

1 TRACK JACK YQB 4 - 0% (spare


parts issue)
2 ISUZU Light duty truck 3 3 100%

3 railcar 3 - 33.3%,
2spare case

4 Iveco tool car 2 100%


2
5 Heavy trucks 1 1 100%
Pictures during maintenance work
Pictures during maintenance work
Mechanical maintenance workshop.
Work Plan For The Next Week

1. Emergency maintenance of vehicles, generators and other


machines will be done according to the immediate necessity of
the Maintenance.
2. 1 Loader, 1 Excavator, Maintenance of one starter
motor ,Mieso and Indode rail cars and workshop junks
evacuation.
Mechanical maintenance workshop.
stumbling blocks
1. Delay of supply of spare parts is a serious issue. Most of the
time the delay is significantly too much.
2. Staff issue
• skill gaps
• staffs not recruited in some critical positions
Mechanical Maintenance
Workshop

Thanks
_____The End_____