Professional Documents
Culture Documents
DSM Regulations - RMAKS - 2
DSM Regulations - RMAKS - 2
DEVIATION SETTLEMENT
MECHANISM
Ritesh Mokhade Dy.EE (POG)
Amit Kumar Saxena AE (POG)
2
2. For the first four months, the Additional DSM charges will be
computed for Generators but the same will not be collected from
generators , unless required for payment of State DSM charges to
WRPC.
https://dsm.nldc.in/
Tabular representation of Deviation and Additional Deviation Charges for
Seller as per MERC DSM Regulations
CSTPS
-- For Additional DSM Rates in Table I of Annexure –II of MERC DSM Regulations (reproduced as
Annexure –II with this Procedure) shall be referred.
-- For Additional DSM Rates for under-injection by Gen. stations using Coal or Lignite or Gas supplied
under APM Table II of Annexure –II of MERC DSM Regulations
Energy Billing Procedure CSTPS
For Example :
SG = 1450MW, AG = 1460MW, Deviation = 10MW, Freq = 49.95 Hz,
Deviation price rate = 463.1 paisa/unit, MOD rate = 309.98 paisa/unit
For Example :
SG = 1450MW, AG = 1500MW, Deviation = 50MW, Freq = 49.95 Hz,
Deviation price rate = 463.1 paisa/unit, MOD rate = 309.98 paisa/unit
Case 2: SG = 1450 MW
AG = 1404 MW
Deviation = -46 MW
Freq = 49.99 Hz
Deviation price rate = 340.6 paisa/unit.
DSM Charge = Deviation X 250 X Deviation price rate
= 46 X 250 X 340.6 = 39169 Rs.
Additional DSM charge on deviation between > 30 to <= 40 MW
= 10 X 250 X 20% of deviation price rate
= 10 X 250 X 68.12 = 1703 Rs.
Additional DSM charge on deviation between > 40 to <= 50 MW
= 6 X 250 X 40% of deviation price rate
= 6 X 250 X 136.24 = 2044 Rs.
Total DSM charge = 39169 + 1703 + 2044 = 42916 Rs.
For Example :
SG = 1450MW, AG = 1460MW, Deviation = 10MW, Freq = 50.07 Hz,
Deviation price rate = 0 paisa/unit, MOD rate = 309.98 paisa/unit
For Example :
SG = 1470MW, AG = 1460MW, Deviation = -10MW, Freq = 49.84 Hz,
Deviation price rate = 394.30 paisa/unit, MOD rate = 309.98 paisa/unit
Under-Injection by Seller
•Additional Deviation Charges shall be applicable for Sellers crossing
volume limits subject to Cap limit of [394.3] Paisa/kWh or as further
determined by the Commission. Additional Charges for deviation in
excess of deviation charges, are applicable for under injection when
frequency is between ‘49.85 Hz and above and 50.05 Hz and below’,
when deviation of the State deviation at regional periphery crosses the
State volume limit.
Over-Injection by Seller
Total deviation for a station /unit over the day should not exceed 1% .
DECEMBER-
STAGE STAGE STAGE STAGE STATI
2020 (UPTO U-3 U-4 U-5 U-6 U-7 U-8 U-9
II III II & III IV ON
22/12/2020)
SG as per
MAHASLDC
DSM 117 130 247 336 276 198 809 1056 365 376 741 1798
Scheduling
Software
AG as per
MAHAGENCO 116 133 249 336 282 212 830 1079 371 382 753 1832
DSM Software
Difference
-1.37 3.18 1.82 0.62 6.16 13.9 20.67 22.49 5.56 5.81 11.33 33.82
(MW)
% Deviation -1.16 2.45 0.74 0.19 2.24 7.01 2.55 2.13 1.52 1.55 1.53 1.88
Normative Parameters as per MERC for FY 2020-21
(As per MERC Order 196 of 2019) CSTPS
Normative MERC Parameters UoM U-3 to 7 U-8 & 9
AVF (%) % 80.00 85.00
Sp. Oil Consumption (SOC) ml/kWh 1.00 0.50
Auxilliary Power Consumption (APC) % 7.80 6.00
Transit Loss (TL) % 0.80 0.80
Hear Rate (HR) kCal/kWh 2688 2375
Annual Fixed Cost (FC) Rs Crs 981.68 1147.06
Return on Equity (RoE) Rs Crs 114.82 160.34
Energy Charge Rate (ECR) Rs/kWh 2.539 2.453
Daily Fixed Cost Rs Crs 2.69 3.14
Particulars UoM U-3 to 7 U-8 & 9
Fixed Cost Loss if one 210 MW Unit is Under S/D
Rs Crs 0.29
for One Day
Fixed Cost Loss if one 500 MW Unit is Under S/D
Rs Crs 0.70 1.57
for One Day
Fixed Cost Loss by 1% Deviation in MERC AVF Rs Crs 12.27 13.49
Sp. Oil Consumption Loss by 0.1 ml/kwh Deviation
Rs Crs 5.98 3.33
in SOC
APC Loss by 1% Deviation in APC Rs Crs 34.16 18.27
HR Loss by 1 kcal/kwh in HR Rs Crs 1.15 0.72
TL Loss by 0.1% in TL Rs Crs 3.09 1.70
Return on Equity under MERC MYT Regulations, 2019
Base Return on Equity for the Generating Company, at the rate CST ofP14
S per
cent per annum.
In case of existing generating station, as and when any of the
requirements regarding FGMO /RGMO are found lacking based on the
report submitted by the SLDC, rate of Return on Equity shall be reduced
by 1.00% at the time of true-up, for the period for which the deficiency
continues.
An additional rate of Return on Equity of 0.25% shall be allowed for
every incremental ramp rate of 0.10% per minute achieved over and
above the ramp rate of 1% per minute, subject to ceiling of additional rate
of Return on Equity of 0.50%, for the year in which such ramp rate is
achieved.
An additional rate of Return on Equity of
0.50% for Unit for Mean Time Between Failure (MTBF) between 45
days to 89 days,
0.75% for Unit for Mean Time Between Failure (MTBF) between 90
days to 119 days,
1.00% for Unit for Mean Time Between Failure (MTBF) above 120 days.
Return on Equity under MERC MYT Regulations, 2019
CSTPS
Yes
Reduce RoE New
by 1% till unit &
No
compliance No FGMO/
Change
report from RGMO
SLDC ready ?
Add 0.25% RoE for
Additional each incremental
Max. 0.5%
RoE for 0.1% ramp-rate ,
additional
Ramp-rate subject to maximum
RoE
> 1% of 0.5% additional
RoE
Base Max 15.5%
Min. 13% rate (=14% +
(=14% -1%) 14% 0.5% + 1%)
T-Code : zpts_mtbf
OLC Deviation Charges till (NOVEMBER-2020)C S T P S
Month No. Of Revisions Financial Implications
Apr-20 193 434250
http://mwcstps.mahagenco.in/apps/dsm_web/ - For
Unitwise Deviation
http://mwcstps.mahagenco.in/apps/dsm_web/stage/ -
For Stagewise Deviation
ID – viewer@mahagenco.in
Password – M@h@genc0.1n
http://dsm-scheduling.mahasldc.in/Account/Login -
MAHASLDC DSM Scheduling Software
CSTPS
Thank You…