Performance Management

You might also like

Download as ppt, pdf, or txt
Download as ppt, pdf, or txt
You are on page 1of 30

BITS Pilani

Pilani Campus

PROGRESS & PERFORMANCE


MANAGEMENT AND EVALUATION
CHAPTER NO 13 TEXTBOOK T1
NEED

• Control holds people accountable

• Prevents small problems from mushrooming into large


problems

• Keeps focused

• Competitive edge

• Effective control through proper information system

BITS Pilani, Pilani Campus


PROJECT MONITORING
INFORMATION SYSTEM
• Determining what data to be collected

• How, when and who will collect the data

• Data analysis

• Reporting current progress

BITS Pilani, Pilani Campus


DATA COLLECTION AND
ANALYSIS
• Actual activity duration
• Resource usage and rates
• Actual costs

• Compare :
– Planned Vs. Actual
– Scheduled Vs. Actual

BITS Pilani, Pilani Campus


• Data To Be Collected By
– Project Team Members
– Individual Cost Engineers
– Project Manager

• Sources
– Cash Flow
– Machine Hours
– Labor Hours
– Materials In Place

BITS Pilani, Pilani Campus


Reports And Reporting
– Progress since last report
– Current status of project
• Schedule
• Cost
• Scope
– Cumulative trends
– Problems and issues since last report
• Action and resolution of earlier problems
• New variances and problems identified
• Corrective action planned

BITS Pilani, Pilani Campus


PROJECT CONTROL
PROCESS
• Setting the baseline plan

• Monitoring progress and performance

• Comparing Plan vs. Actual

• Taking actions

BITS Pilani, Pilani Campus


MONITORING TIME
PERFORMANCE
• Preparing Gantt Chart
– List the activities with duration
– Predecessor Relationship
– Critical Path
– Tracking Gantt Chart
• Progress
• Slippages
• Slack

BITS Pilani, Pilani Campus


EARNED VALUE
COST/SCHEDULE SYSTEM

Time Phased Budget Baseline


Comparisons With Actual And Planned Schedule And Cost
EV: Earned Value (BCWP)
PV: Planned Value (BCWS)
AC: Actual Cost (ACWP)
CV: Cost Variance SV: Schedule Variance
BAC: Budgeted Cost at Completion
ETC: Estimated Cost to Complete Remaining Work
EAC: Estimated Cost at Completion
VAC: Cost Variance at Completion

BITS Pilani, Pilani Campus


BITS Pilani, Pilani Campus
COST VARIANCE CV = EV – AC
SCHEDULE VARIANCE SV = EV – PV
TIME VARIANCE TV = ST – AT
VAC = BAC - EAC

CV : IF NEGATIVE : OVERRUN
SV : IF NEGATIVE : BEHIND SCHEDULE
TV: DELAY IS NEGATIVE

BITS Pilani, Pilani Campus


BITS Pilani, Pilani Campus
INTEGRATED COST
SCHEDULE SYSTEM
Define The Work Using WBS
– Scope
– Work Progress
– Deliverables
– Organization Units
– Resources
– Budgets For Each Work Package

BITS Pilani, Pilani Campus


• Develop work and resource schedule
– Schedule resources to activities
– Time-phase work packages into network

• Develop time phased budget using work packages and


determine planned budgeted cost of the work scheduled
• At work package level, collect actual costs for the work
performed.
• Collect percent completion and compute budgeted cost
of work performed : earned value

BITS Pilani, Pilani Campus


TIME PHASED BUDGET

• To measure overall performance by using aggregate


performance measure called earned value

• To compare the actual and scheduled cost with planned

• Earned value is calculated by multiplying the estimated


percent physical completion of work for each task by the
planned cost for those tasks

BITS Pilani, Pilani Campus


WAYS TO CALCULATE
PERCENT COMPLETION
• The 50-50 estimate: fifty percent completion is assumed
when the task is begun and remaining fifty percent when
the work is complete
• The 0-100 percent rule: this rule allows the credit of work
until the task is complete
• Critical input use: this rule assigns task progress
according to the amount of critical input that has been
used
• The proportionality rule: this rule divides actual task time
to date by total scheduled task time to calculate percent
complete

BITS Pilani, Pilani Campus


VARIANCE ANALYSIS

• Comparing earned value with the expected schedule


value

• Comparing Earned Value With The Actual Costs

• CV = EV- AC If Negative, Overrun


• SV = EV – PV If Negative Behind Schedule

BITS Pilani, Pilani Campus


DEVELOPING A STATUS
REPORT
• Baseline Development

• Development Of Status Report


– Not Yet Started
– Finished
– In Process Or Partially Complete

BITS Pilani, Pilani Campus


PERFORMANCE INDEX
• CPI = EV / AC

• SPI = EV / PV

INDEX CPI SPI


>1.00 UNDER RUN AHEAD OF
SCHEDULE
=1.00 ON COST ON SCHEDULE
<1.00 OVER RUN BEHIND SCHEDULE
PROJECT PERCENT
COMPLETE INDEX
• Percent complete index PCIB = EV / BAC

• PCIB represents the work accomplished as percent of


the total budgeted dollars to date

• Percent complete index PCIC = AC / EAC

• PCIC represents percent complete in terms of actual


dollars spent to accomplish work to date and the actual
expected dollars for the completed project

BITS Pilani, Pilani Campus


FORECASTING FINAL
PROJECT COST
EAC = AC + ETC

ETC = WORK REMAINING / CPI


= (BAC – EV) / EV/AC

TCPI : TO COMPLETE PERFORMANCE INDEX (TCPI)

TCPI = (BAC – EV) / (BAC – AC)


It measures the amount of value each remaining dollar in
the budget must earn to stay within budget

BITS Pilani, Pilani Campus


Problem no. 1

• A project to develop a country park has an actual cost in


month 17 of $350,000, A planned cost of $450,000, and
A value completed of $300,000. Find the cost and
schedule variances and the three indices.

• GIVEN : AC = 350,000 PV = 450,000


EV = 300,000
• COST VARIANCE = EV – AC

• CV = 300,000 – 350,000 = -50,000 OVERRUN

BITS Pilani, Pilani Campus


• SCHEDULE VARIANCE = EV – PV = 300,000 – 450,000
= -150,000 BEHIND SCHEDULE

• CPI = EV/ AC = 300,000/350,000 = 0.857

• SPI = EV / PV = 300,000 / 450,000 = 0.666

• CSI = CPI X SPI = 0.857 X 0.666 = 0.571

BITS Pilani, Pilani Campus


PROBLEM NO. 2

• A project to develop technology training seminars is 5


days behind schedule at day 65. It had a planned cost of
$735,000 for this point in time, but the actual cost is only
$550,000. Estimate the schedule and cost variances.

BITS Pilani, Pilani Campus


SOLUTION 2

GIVEN PV = 735,000 AC = 550,000 EV = 60/65 *


735,000 = 678,462

COST VARIANCE = EV – AC = 678,462 – 550,000 =


128,462 UNDERRUN

SCHEDULE VARIANCE = EV – PV = 678,462 – 735,000 =


- 56,538 BEHIND SCHEDULE

BITS Pilani, Pilani Campus


PROBLEM NO. 3
• For the following test marketing project at week 6,
calculate the cost schedule and time variances. Also
calculate the CPI, SPI, CSI, ETC AND EAC.

ACTIVITY PREDECE DURATI BUDGET ACTUAL %


SSOR ON COST COMPLE
TE
A - 2 300 400 100
B - 3 200 180 100
C A 2 250 300 100
D A 5 600 400 20
E B,C 4 400 200 20
SOLUTION 3
A PV 150 150
EV 150 150
B 100 100
100 100
C 125 125
125 125
D 300 300
300
E 200 200
200
TOTAL 250 150 525 125 200 0 300 200
: PV
CUM. 250 400 925 1050 1250 1250 1550 1750
AC 0 400 180 300 0 0
CUM. 0 400 580 880 880 880
EV 250 150 525 125 200 0
CUM. 250 400 925 1050 1250 1250
ON DAY 6

EV = 1250

PV = 1250

AC = 880

BITS Pilani, Pilani Campus


• COST VARIANCE : EV – AC = 1250 – 880 = 370
UNDERRUN
• SCHEDULE VARIANCE = EV – PV = 1250 – 1250 = 0
ON SCHEDULE

• CPI = EV/AC = 1250 / 880 = 1.42

• SPI = EV/PV = 1250 / 1250 = 1.00

• CSI = 1.42 X 1.00 = 1.42

BITS Pilani, Pilani Campus


• BAC = 1750 EV = 1250 CPI = 1.42

• ETC = (BAC – EV) / CPI = (1750 – 1250) / 1.42 = 352

• EAC = ETC + AC = 352 + 880 = 1232

BITS Pilani, Pilani Campus

You might also like