#3

COMMENCEMENT OF
GROUND FLOOR SLAB

CONSTRUCTION MILESTONE DESCRIPTION

A `Slab’ is a horizontal, moulded layer of reinforced concrete,


supported by beams, columns, walls, or other framework, to create
a floor or roof.

In Godrej Royale Woods the Ground floor slab is where the stilt
parking is planned with access at specific points to the central
landscaping. The Ground floor slab level in Godrej Royale Woods is
naturally ventilated and has predominantly covered parking with
few services like the electrical room, fire control room, maintenance
room, common toilets, association room, DG panel room etc.
CONSTRUCTION MILESTONE CERTIFICATE
1-PLUMERIA, 2-MAHOGANY, 3-RAINTREE, 4-PINE, 5-OAK, 6-BANYAN

MILESTONE ACHIEVEMENT DATE


This milestone was achieved Tower wise as follows:

Tower 3– RAINTREE – 23-Feb-21

MILESTONE PICTURES
Please note that the pictures shared as on above date indicates the commencement
of Ground floor slab work for the above mentioned Tower.

Tower 3

The above information is hereby certified as accurate by the Project Manager and
Project Architect for Godrej Royale Woods.

Raghuram S V (BE. Civil, PGP-ACM, MBA) Chriz Thomas (B.Arch. M.Arch)


Project Manager, Godrej Royale Woods Project Architect, Godrej Royale Woods
ANNEXURE 1:
LIST OF CONSTRUCTION MILESTONES
IN THE PROJECT - COMPLETED AND DUE NEXT
Milestones Tower 1 Tower 2 Tower 3 Tower 4 Tower 5 Tower 6

Completed: Completed: Completed: Completed: Completed: Completed:


Commencement of
excavation – Tower specific July-2020 July-2020 June-2020 June-2020 May-2020 May-2020

Expected: Expected: Completed: Completed: Completed: Completed:

Commencement of footings - December- December- December- December- December- December-


Tower specific 2020 2020 2020 2020 2020 2020

Completed: Completed: Completed: Completed: Completed: Completed:


Commencement of ground
floor slab - Tower specific January-2021 January-2021 February-2021 February-2021 January-2021 January-2021

Expected: Expected: Expected: Expected: Expected: Expected:


Commencement of first floor
slab - Tower specific March-2021 March-2021 April-2021 April-2021 March-2021 March-2021

Commencement of third
- - - - - -
floor slab - Tower specific

Commencement of fifth floor


- - - - - -
slab - Tower specific

Commencement of seventh
- - - - - -
floor slab - Tower specific

Commencement of ninth
- - - - - -
floor slab - Tower specific

Commencement of eleventh
- - - - - -
floor slab - Tower specific

Commencement of
fourteenth floor slab - Tower - - - - - -
specific

Commencement of terrace
- - - - - -
floor slab - Tower specific

Commencement of external
- - - - - -
painting – Tower specific

Commencement of flooring –
- - - - - -
Unit specific

Commencement of fixing of
windows and doors – Unit - - - - - -
specific
Commencement of fixing of
- - - - - -
CP Sanitary – Unit specific
ANNEXURE 2:
MASTERPLAN INDICATING EACH TOWER NUMBER AND NAME