OHS - Presentation 13 Jan 2023
OHS - Presentation 13 Jan 2023
Project
4th
13/01 /2022
There are only two existing river crossings. The first is CR9 steel bridge and second Khandia bridge . The 3 rd is Dugha
cable crane is in progress.
03 Fall arrest System ,rope grabs to implement Currently: A 2 meter hole drilled , After that a metal rod InProgress.
while working at mountain and rivers edges . installed into it . The rope is tied to it . The full body harness Record shared with the
fixed to it and rope is loosed as much as needed. Engineer via WhatsApp
In progress : We have already placed an order of rope grabs to
the vender, it has not been received from the Vender yet.
Minute of the Monthly OHS Progress Review Meeting (RAR-02) October 2022