4m Status Check
4m Status Check
Implementation
Process Short Pipe Connector Fitting 08/11/19
Date
Implementation
Process Final Fitment 15/11/19
Date
Implementation
Process Both Cup Fit 06/11/19
Date
Implementation
Process 2ND Bending 18/11/19
Date
straight (in radius form at bottom of U) – Roller Wear 2nd Bending machine roller has been replaced (unit;- hr.)
Out too quick and Pinching Part with double roller support instead of single roller 10%
Improvement Point at bottom
0.69
- single roller at bottom roller replaced 0.62
with double roller support
Jan ~Oct 19 Mar’20
Process Loss Improvement Sheet LGE Internal Use Only
Implementation
Process 1st Bending 15/11/19
Date
( Every Month due to continue friction) Threaded Bolt guided and pain in moving area
(unit;- hr.)
instead of Plain with easy movement against
friction of cylinder rotation. 5%
Improvement Point
1.2
- Improving machine Breakdown 1.12
Implementation
Process Short Pipe Bending 15/11/19
Date
Implementation
Process Air Compressor 25/11/19
Date
Implementation
Process Packing and inspection 08/11/19
Date
Separate Manpower for Visual inspection and packing - Merging of Manpower through Line balancing Manpower↓
in Bin - Combined Process time is less than Neck process
time ( 6.18 Sec) 50% ↓
Improvement Point unit - MP
Before After
(Jan~Sep’19) ( Nov’19)
Inspection Time : 5 Sec Packing Time : 2.20 Sec
Packing & Inspection Time : 6.03 Sec
Cycle Time ↓
Unit : Sec
7.20 6.03
2.20 6.03
Before After
(Jan~Dec’19) ( Jan’20)
Process Loss Improvement Sheet LGE Internal Use Only
Implementation
Process Ring Insertion 15/01/2020
Date
Long pipe Ring Insertion – 2 Manpower used Jig Kept in one hand and pushed by other Manpower↓
Cycle Time 1 st Stage - 3.96 Sec
50% ↓
Cycle Time 1 st Stage - 3.96 Sec
unit - MP
Improvement Point 2
1
Jig Used
Before After
(Jan~Sep’19) ( Jan’20)
Stage 2 Ring Stage 1Ring
Insertion : 7 Sec Insertion : 7 Sec
Cycle Time ↓
Unit : Sec
3.96 2.4
Stage After - Process Time
1.56
Pick Long Pipe 1.2
Ring Pick Long Pipe 1.2 Ring 1.2 1.20
Put Long pipe in Ring on
Insertion in
Insertion in
Pick Ring 1.2 long Pipe
Mat 1.2 1.2 1.20
long Pipe
Manual Fit both 1.56 Element
Before After
Removed
(Jan~Dec’19) ( Jan’20)
Process Loss Improvement Sheet LGE Internal Use Only
Implementation
Process Deburring 15/11/2020
Date
Improvement Point 2
1
- Cutting Machine ( Trob M/c modified & Deburring Process
added at time of cutting of pipe Before After
(Jan~Sep’19) ( Jan’20)
Cycle Time ↓
Unit : Sec
9.62 4.10
5.66 0
3.96 4.10
Cycle Time tube Cutting - 3.96 Sec Before After
Cycle Time Deburing - 5.66 Sec Cycle Time tube Cutting & Deburring - 4.10 (Jan~Dec’19) ( Jan’20)
Sec
Process Loss Improvement Sheet LGE Internal Use Only
Implementation
Process Deburring 15/11/2020
Date
Improvement Point 1
0
- Die modified and location defined by Jig 0
Before After
(Jan~Sep’19) ( Jan’20)
Cycle Time ↓
Unit : Sec
7.92 1.92
3.96 0
Stage Before - Process Time Stage After - Process Time
Manual Insertion of ring on Long 3.96 1.92
Ring Location defined by Jig
pipe ( No location defined for
Ring Setting Ring Setting
during ring insertion
1.92 Before After
Ring in Long Pipe ) 3.96 ( Jan’20)
No Ring Setting Reqd ( Die (Jan~Dec’19)
Ring Setting after Fittment 3.98
modified for Auto Ring Set ) 0
Process Loss Improvement Sheet LGE Internal Use Only
Implementation
Process Loading/Unloading 15/11/2020
Date
Before After
(Jan~Dec’19) ( Jan’20)
Man Power
Before
Reduction
(unit;- Nos)
Implementation
Process Dispatch and Production Planner 06/11/2019
Date
Before- After-
1.RM taken from the store 1.RM taken from machine
2.Dispatch Data From Mail 2.Dispatch Data From Scheduling Board
3. Planning with respect to Dispatch Schedule with 3. Self Planning according to customer wise
prod Supervisor schedule Man Power
Reduction
(unit;- Nos)
Before After
•Dispatch Planner Working •Prod. Supervisor Working (Jan~Dec’19) ( Jan’20)
with 45% load with 60% load