Professional Documents
Culture Documents
PMS-PMP-PDU-008 Cost (1)
PMS-PMP-PDU-008 Cost (1)
4. Integration 1 1 2 2 1 7
5. Scope 0 4 0 2 0 6
6. Schedule 0 5 0 1 0 6
7. Cost 0 3 0 1 0 4
8. Quality 0 1 1 1 0 3
9. Resource 0 2 3 1 0 6
10. Comm 0 1 1 1 0 3
11. Risk 0 5 1 1 0 7
12. 0 1 1 1 0 3
Procurement
13. 1 1 1 1 0 4
Stakeholder
Total 2
Prepared By: Hsaung Hnin Phyu,24
PMP 10 12 1 49
PMBOK GUIDE
SIXTH EDITION
Short Notes 95
Alternative analysis
PMBOK GUIDE
SIXTH EDITION
Short Notes 96
Short Notes 58
Short Notes 31
Reserves Analysis
- An approved change request is not required to access the contingency reserve
- Management reserve & contingency reserve are decided in estimate cost process
- Reserve analysis is used in Estimate activity duration, Estimate Cost, Determine budget,
Control cost & Monitor risk processes
- Reserve analysis is performed to determine if the remaining reserves are sufficient to
for the risk remaining in the project and to determine if adequate reserve have been set
aside to address identified risks as well as uncertainty in schedule duration, budget, funds
or estimated costs for the project.
- When opportunities are captured resulting in cost savings, fund may be added to the
contingency amount.
Presented By: Hsaung Hnin Phyu, PMP ®
PMBOK GUIDE
SIXTH EDITION
Short Notes 61
Cost of quality
- Cost of quality is what you get when you add up the costs of all the prevention &
inspection activities you are going to do on your project.
- It doesn’t just include the testing, it includes any time spent writing standards, reviewing
documents, meeting to analyze the root cause of defects, rework to fix the defects once
they are found by the team-absolutely everything you do to ensure quality on the project
This process is performed once or at predefined point in the project
Short Notes 56
Determine budget
- Cost baseline is main output
- The process of aggregating the estimated costs of individual activities or work packages
to establish an authorized cost baseline
- Any significant changes in a country’s economic policy would likely affect the currency
exchange rates. Project manager will need to account for these fluctuations in exchange
rates when determining project budget
PMBOK GUIDE
SIXTH EDITION
Short Notes 12
Short Notes 2
- Cost & staffing levels are low at the start of the project
- Risk & uncertainty are greatest at the start of the project
- The ability to influence the final characteristics of the project’s product is the highest
at the start of the project
- The project life cycle is the series of phases that a project passes through from its start
to its completion
Control cost => Cost Forecasts
Control schedule => Schedule Forecasts
Trend Analysis – examines project performance over time if performance is improving or
deterioration
S Curve
PMBOK GUIDE
SIXTH EDITION
Short Notes 63