METHOD OF STATEMENT

FOR REVETMENT AS
FLOOD CONTROL
Preparation prior to Installation of Revetment

1. All areas that will be installed with revetment wall must be free from any obstruction
2. Setting out. Establish the wall staking out plan. Use tansi as guide for installation of pile
cap.
Installation of Revetment

 1. Installation of Pile Cap

1. Installation of Pile Cap, first check the dimension ( 0.70 m X 0.50 )


2. Fabricate the formworks ( Phenolic Board )
3. Fabricate the exact Rebars ( 16 mm and 12 mm )
4. Prepare Dowel Rebars prior to Slope Installation ( 16 mm and 12 mm )vertical and
horizontal.
5. Concrete Pouring
 2. Installation of Slope

1. Check the width of slope ( 30 cm )


2. Installation of formworks
3. Fabricate the rebars continuous to pile cap and slab ( 16 mm and 12 mm )
4. Concrete pouring
 Installation of Stiffener Column

1. We put stiffener column for the purpose of no embankment due to impossible/lack of


resources.
2. Due to existing close-fitting houses we can’t do embankment with the use of backhoe that’s
way we put stiffener column as replacement of embankment
3. Check thickness ( 20 cm )
4. Installation of Formworks and rebars, from NGL to Slab
5. Concrete Pouring
 Installation of Slab
1. Check thickness (30 cm) width (1 m
2. Installation of formworks ( phenolic )
3. Fabricate Rebars, continuous from slope to retaining wall with U-pattern for stronger bond.
( 16 mm and 12 mm )
4. Prepare Dowel Rebars prior to Parapet wall installation ( 16 mm and 12 mm )vertical and
horizontal.
5. Concrete pouring
 Installation of Retaining Wall

1. As per inspection on area, retaining wall installed on houses wall.


2. Thickness of ( 30 cm ),
3. Fabricate of formworks ( phenolic )
4. Fabricate of Rebars ( 16 mm and 12 mm ), rebars must be continues from NGL to slab.
5. Concrete pouring
 Installation of Parapet Wall

1. Thickness (30 cm ) bottom , ( 20 cm ) up


2. Installation of formworks
3. Rebars fabrication ( 12 mm )
4. Concrete Pouring