Professional Documents
Culture Documents
EON_Antony Sheil_Case_Study_to_Baseline_Plan 2020 (1)
EON_Antony Sheil_Case_Study_to_Baseline_Plan 2020 (1)
Plan
Antony Sheil C77221283
Existing Property Proposed Property
• The matrix shows the risk to both the university for the project and the landlord at the early stage.
• The initial risks for the university far outweigh the ones of the landlord and therefore further discussions required to mitigate the risks and reduce.
Problem Definition V2
• Initially, Landlord is making money in the first month of purchase due to the cash injection incentive from the university however, will have to inject money into the project in month 2 due to the refurbishment and extension
works.
• Landlord will start to make profit in month 12 after the initial outlay of costs are absorbed.
• Landlord will be at risk between month 2-11 and may need to sort a private investor.
• Initial Draft Project
Programme shows a duration
of 64 days from 23/10/20 to
20/01/21.
• Provisional period for
planning added.
• Further programme to be
created showing base line,
critical path and resources
once project definition has
been discussed.
Project Definition V1
Business Value Case
• Highest risk for University is the loss of students – the reason for this case study due to the impact it would have on the income. The action addressed reduces the risk score down to a sustainable point and increases the chance
of the university to succeed.
• The joint highest risk for the university is the reputation – if the university has a bad reputation worldwide, it will have a negative impact on international students wishing to join. The action noted reduces the risk and upholds
the universities reputation. If the project is successful, the reputation of the university will increase.
• The risk for the university of the landlord unable to pay, links to the risk of the landlord and going bankrupt. However, it is to be noted that this risk is far more for the landlord than the university therefore the actions noted are
needed to safeguard both parties.
Risk Matrix V2 (continued)
• The rest of the risks are relatively small for the landlord but can still be substantial. The risks to changes of design are still high due to planning approval and costs associated with this can be crushing for the landlord on a tight
budget.
• Suitable actions for these redesigns have been noted and each in turn reduce the risk to the landlord.
Cashflow – Actual
• Landlord has managed to obtain a better mortgage rate of 2.20% in which has helped balance out and reduce the risks associated with the initial outlay.
• However, unforeseen problems have included additional costs but the increased mortgage lending has helped to reduce the risk to the landlord.
• Costs missed at planning stage of the cashflow have now been included.
• Overall risk to landlord has decreased and landlord benefits from the project in September rather than December as planned.
• Graph shows the difference between planned and actual – visual representation of the project working in favour to the landlord.
Programme of works
Duration estimates
for each process
have now been
added, giving a
base to start linking
the tasks together.
Each work package
has its only start
and finish
milestone.
Programme of works- Continued
Formatted to reveal
the critical path.
Section 278 notice
forms part of the
critical path due to
alterations to drive
crossing unable to
commence until
notice is received.
However, critical path
should run through
the full project
therefore, linking
section 278 notice to
the production of
drawings will be
required before
finalised programme.
Programme of works- Continued
Formatted to reveal
the float available
within the tasks
(slack) with critical
path still to be
amended.
Programme of works- Continued
Programme now
shows the project base
line in the tracking
gantt view with critical
path still to be
amended.
Programme of works- Continued
When attempting to
level the resources
within available slack
(smoothing), the
programme duration
has slipped from the
baseline as shown
however, it was not
possible to smooth all
resources therefore
some are unchanged
and a warning box
appeared in which
notes the tasks that
cannot be smoothed.
Over allocated report after smoothing
The finalised
programme showing
no conflicts and all
tasks and work
packages correctly
linked with critical
path now showing
throughout project.
Re-baselined for
construction use.
Split over two pages
for better viewing.
Programme of works- Finalised continued
Reflective Learning Notes
• The main reading document that I found useful was the Team Facilitation Through Visuals by Davis
et al 2020. This paper helped me to understands that a person can visualise something and engage in
planning much sooner if they are presented with pictorial representation of what they are required to
do. This can be used within the management of a project through the case study to business plan
document. This powerpoint presentation would be beneficial to a project manager and any person
involved as it would help visualise the project and highlight key factors surrounding the risks and
costs associated much quicker than with no pictoral viewing.
• After watching the Microsoft Projects video by John Heathcote, I have learned how to use Microsoft
Projects and successfully created a programme of works correctly in which provides vital information
for this case study.
• I have learned how to think “outside the box” when looking at different construction projects,
thinking about the project as a whole and not just technically. This relates to cost, time management,
site layout, health and safety, technicalities.
• Learned about risk matrices, cash flows and problem / project definitions and how these are vital
pieces of information when starting to think about a new project.