Project

Updates
Project Name :- DPS Santhoshnagar
Project Scope Status & Accomplishments
DPS SANTOSH NAGAR SCHOOL BUILDING Part-1: RO Plant is ready to use.
Portable washroom cabins fixed at Terrace for
students.
Part-2 & 3 : First Floor Slab shuttering and
reinforcement in progress and backfilling in Progress
behind Retaining wall.
Part-2 and 3 Temporary gates fixed.

Risks & Opportunities: Need help/Next steps


1.In time material Supply and PO’s
• Running late due to 6:00AM to 6PM Work permitted by 2.Vendor Payments are delayed and deducting
Colony Association.
the bill amount.(reason not known).Even after
finalizing the P.O./Work order
3.Request you to help in take the permission from
Colony Association for extra work time.(We
already Spoke to Association Members they
denied to give Permission)
Project Snap Shot
Previous Week Present Work
• RO PLANT FIXING AND PLANATION AT PART-1 IN PROGRESS Part-2 & 3FIRST FLOOR STAIRCASE AND MIDLANDING READY FOR CONCRETING
TODAY AND RAMP SHUTTERING WORK IN PROGRESS

PART-2 & 3 BLOCK WORK IN B-1 AND B-2. RO PLANT FIXED AND TEMPORARY WASH ROOMN CABINS FIXES AT TERRACE FOR
PART 2 & 3 G FLOOR & PEDESTRAIN RAMP SHUTTERING AND STUDENTS
REINFORCEMENT
TOP VIEW OF PART-2 & 3