Sec12 -Mom 18-Temerloh and Bentong Station Updated as on 10072024
Sec12 -Mom 18-Temerloh and Bentong Station Updated as on 10072024
Previous Legend:
Progress Unit Total % Done This week % Done To Date % Done
Week Piling completed
Previous Legend:
Progress Unit Total % Done This week % Done To Date % Done
Week Excavation
Photo 3 – Installation of rebar for pad footing. (11KV Photo 4 –Piling works in progress by S6. (Platform 1)
Substation)
11/07/2024
STATION 16 BENTONG
CURRENT PROGRESS BENTONG STATION BOX (CIVIL & STRUCTURE)
WORK PROGRESS - AS OF 10/07/2024
Previous Legend:
Progress Unit Total % Done This week % Done To Date % Done
Week Excavation
Spun Pile Nos 373 290 79.5% 46 12.33% 336 91.83% Lean con Completed
Cutting pile Nos 373 0 0% 0 0 0 0%
Rebar & F/work
Excavation Nos 68 0 0% 0 0 0 0%
Pile cap completed
Lean con Nos 68 0 0% 0 0 0 0%
Pile cap Nos 68 0 0% 0 0 0 0% Stump completed
CURRENT PROGRESS BENTONG 11KV SUBSTATION (CIVIL & STRUCTURE)
WORK PROGRESS - AS OF 10/07/2024
Previous Legend:
Progress Unit Total % Done This week % Done To Date % Done
Week Excavation
Spun pile Nos 78 78 100% 0 0 78 100% Lean con Completed
Cutting pile Nos 78 0 0 27 34.6% 27 34.6% Rebar & F/work Pile cap
Excavation Nos 26 26 100% 0 0 26 100%
Pile cap completed
Lean con Nos 26 0 0 6 23% 6 23%
Pile cap Nos 26 0 0 6 23% 6 23%
Supervision Photos (C&S)
STN 15 BENTONG STATION – 10 JULY 2024
Photo 1 – Driving spun piling works by Section 7. Photo 2 – Excavation works for lean con and cutting piles.
(STATION BOX) (11KV Substation)
Photo 3 – Casting works for pile cap GL (A-C,1-2). (11KV Photo 4 – MLT test pile no A6-B. (11KV Substation)
Substation)
11/07/2024