Cost Effective Cement Planning

Institute of Drilling Technology, Dehradun


Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

FIRST IT IS NECESSARY TO BE AWARE OF


THE COST IMPLICATION RELATED TO
CEMENTING OPERATION

Institute of Drilling Technology, Dehradun


Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

BRIEF CEMENTING REVIEW

3
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

Requirement For a Cementing Operation

1. CEMENTING EQUIPMENT

2. CEMENTING TOOLS / ACCESSORIES

3. CEMENT : Class G OWC

4. CEMENT CHEMICALS

5. PLANNING / DESIGNING

6. EVALUATION

4
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

Cementation Job for a WELL


• Planned Job :
 Primary Casing Cementation
 BOP Test / Hermetical Test

• Non-Planned Job :
 Secondary Cementations
 Plug job
 Squeeze job

 Allied Jobs
 Oil spot
 Pressure test
 Other Misc.

5
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

What is Cementing cost

6
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

PLANNED COST
Primary Casing Cementation

Fixed cost : Cementing Equipment Expenses


Cementing Service Cost

Variable cost : Cementing Accessories


 Cement & Additives
 Floating Equipment
 Cementing Plugs
 Stage collars
 Centralizers & scratchers
 Liner hangers etc.

7
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

8
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

How does the Cementing


Cost get escalated?

9
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

SINGLE MAJOR FACTOR:


POOR PRIMARY CEMENTATION

Unsuccessful Primary Cementation

Sick Well

1. Low production/Poor Reservoir


Evaluation

2. Repair and Work over Operation–


Recurring Expenditure

10
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

REASONS FOR POOR PRIMARY CEMENTATION


• HOLE IS NOT PROPERLY GAUGED, CLEANED OR
CONDITIONED

• LACK OF PROPER CENTRALISATION

• CEMENTATION IS NOT PLANNED & EXECUTED


PROPERLY.

• VITAL EQUIPMENT FAILED DURING


CEMENTATION.

• POOR QUALITY & POOR EVALUATION OF CEMENT


BOND

11
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

OTHER THAN POOR PRIMARY CEMENTATION

Non-planned Secondary jobs


1. Plug/Squeeze Jobs during drilling for
- Fishing – Side Track
- Mud loss
- Well head repair
- Cellar pit seepage
- Formation/ shoe integrity
- Temporary suspension

REMARK : NOT DESIRED BUT ESSENTIAL SOMETIMES

12
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

Non-planned Secondary jobs contd….


2. Cement repair as a consequence of
- Mud pump problem
- Inability to reciprocate casing
- Faulty pressure gauges.
- Inaccurate stroke counter
- Improper mud properties
- Inadequate centralizers
- Excessive caving
- Poor slurry design
- Unable to maintain designed slurry wt.

REMARK: NOT DESIRED & ALSO AVOIDABLE

13
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

Non-planned Secondary jobs contd….

3. Others
 Cement squeeze for casing pipe failure

 Squeeze job failure


- Improper design
- Non- availability of required
additives.
- Improper execution
- Inadequate WOC.

 Avoidable allied job


- Misc. pumping /pressure testing

REMARK: NOT DESIRED & ALSO AVOIDABLE

14
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

4. Improper evaluation of cement bond

A good bond or bad bond may be misleading if properly


not evaluated

Often it is found that there is no INJECTIVITY during


squeeze job

IMPORTANT to avoid unnecessary cement repair job


based on wrong evaluation as it leads to RIGTIME
WASTAGE AND DAMAGE OF CASING.

15
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

Who can Contribute to Cost Reduction?

16
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

CEMENTATION IS A SMALL BUT VERY


SIGNIFICANT PART TO ENSURE
LONG LIFE OF WELL FOR WHICH IT
IS NECESSARY FOR ALL
ASSOCIATED TO PLAY A ROLE FOR
COST REDUCTION

17
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

COST ESTIMATE :
A GENERAL QUANTIFICATION

18
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

Know the basic cost


Item UOM Approx. Cost
(Rs.)
Neat cement Per MT 8,000
Chemical slurry Per M3 41,000
Gas tight slurry Per M3 53,000
HPHT slurry Per M3 75,000
Deepwater slurry Per M3 130,000
Light weight slurry (< 1.5) Per M3 100,000
Cementing cost (onshore) Per job 5,00,000
Cementing cost (offshore) Per job 15,00,000
Onshore operating rate Per day 15,00,000
Offshore operating rate Per day 150,00,000

19
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

NOW WITH THE UNDERSTANDING OF


COST IMPLICATION

Next Logical Step is the Cost


Reduction in Cementing Operation

Institute of Drilling Technology, Dehradun


Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

Cost Reduction – Possibilities

PURPOSE OF COST AWARENESS IN


CEMENTING MOSTLY MEANS TO
AFFECT SAVINGS IN TERMS OF
RIGTIME THROUGH BETTER
PRIMARY CEMENTATION AS COST
OF CEMENTING OPERATION &
MATERIALS ARE PEANUTS
COMPARED TO RIG COST

21
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

Cost Reduction – Possibilities

1. SELECTION OF PROPER EQUIPMENT


2. SELECTION OF PROPER CEMENTING TOOLS &
MATERIALS
3. PROPER PLANNING AND DESIGNING
4. CO-ORDINATION TO ENSURE SMOOTH JOB
EXECUTION
5. A GOOD PRIMARY CEMENTATION
6. OPTIMISATION OF WOC
7. PROPER EVALUATION OF CEMENTATION
8. TO AVOID UNNECESSARY PRESSURE STRESS
ON CASING

22
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

SELECTION OF PROPER
CEMENTING EQUIPMENT

23
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

SELECTION OF PROPER CAPACITY EQUIPMENT

1. WHILE SELECTING, EQUIPMENT SYSTEM


SHOULD HAVE THE FOLLOWING
• INTEGRATED MIXING CUM PUMPING UNIT WITH
A PRECISION SLURRY MIXER OR RECIRCULATING
MIXER OR AUTOMATIC DENSITY CONTROL
UNIT
• ADEQUATE CEMENT BULK HANDLING
CAPACITY
• ADEQUATE ADDITIVE HANDLING CAPACITY

REMARK: THIS IS REQUIRED TO ACHIEVE APPROPRIATE


DESIGNED UNIFORM CEMENT SLURRY DENSITY AND
SLURRY QUANTITY AT LEAST POSSIBLE TIME.

24
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

SELECTION OF PROPER
CEMENTING TOOLS
& MATERIALS

25
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

SELECTION OF PROPER C/TOOLS

1. GUIDE SHOE WITH FLOAT FUNCTION

• ADDITIONAL FLOAT FUNCTION FOR A BACK


UP TO FLOAT COLLAR IN CASE F/C FAILS

SAVES CASING FROM ‘WOC UNDER


PRESSURE’ AND THEREBY THE QUALITY
OF CEMENT BOND IS NOT AFFECTED

26
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

SELECTION OF PROPER C/TOOLS

2. STAB-IN-SHOE FOR SURFACE CASING

• ENSURES POSITIVE CEMENT RISE


• ELIMINATION OF TOP UP JOB
• ENSURES ACTUAL CEMENT QUANTITY PUMPING
• SAVES DISPLACEMENT TIME
• OCCASIONAL CHANNELING INSIDE CASING IS
ELIMINATED
• ALL ABOVE SAVES RIGTIME
• ADDITIONAL COST IS INSIGNIFICANT

27
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

SELECTION OF PROPER C/TOOLS

3. LINER SHOE WITH SIDEPORTS

ENSURES CIRCULATION, CEMENT PUMPING


AND DISPLACEMENT EVEN WHEN HANGER
FAILS RESULTING IN RESTING OF SHOE AT
BOTTOM

• ELIMINATION OF FAILURE OF LINER


CEMENTATION & SAVES RIGTIME
• ADDITIONAL COST IS INSIGNIFICANT

28
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

SELECTION OF PROPER C/TOOLS

4. LINER HANGER WITH PACKER

ENSURES SEALING OF LINER HANGER AFTER


CEMENTATION AND ELIMINATES CHANCES OF
SQUEEZE JOB AGAINST HANGER TOP
LEAKAGE

• CONSIDERABLE SAVINGS IN RIGTIME


• ADDITIONAL COST IS INSIGNIFICANT

29
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

SELECTION OF PROPER C/TOOLS

5. EXPANDABLE LINER HANGER

ENSURES POSITIVE SEALING OF LINER


HANGER AFTER CEMENTATION AND
ELIMINATES NECESSITY TO DRILL CEMENT
WITH TWO BITS OF DIFFERENT SIZE

• CONSIDERABLE SAVINGS IN RIGTIME


• ADDITIONAL COST IS INSIGNIFICANT

30
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

SELECTION OF PROPER C/TOOLS

6. NON-ROTATING CEMENTING PLUGS


(WITH FLOAT COLLAR)

IMPROVES QUICK DRILLING OF CEMENTING


PLUGS WHEN OPERATION FOR NEXT PHASE
STARTS

• SAVINGS IN RIGTIME
• ADDITIONAL COST IS INSIGNIFICANT

31
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

SELECTION OF PROPER C/TOOLS

7. HYDRAULIC STAGE COLLAR

ENSURES OPENING OF STAGE COLLAR


HYDRAULICALLY ELIMINATING NEED FOR
TIME REQUIRED FOR OPENING PLUG
MOVEMENT.
FURTHER IT IS MUST FOR DEVIATED HOLE

• SAVINGS IN RIGTIME
• ADDITIONAL COST IS INSIGNIFICANT

32
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

SELECTION OF PROPER C/TOOLS

8. MECHANICAL AIDS (CENTRALISER)

 ENSURES CENTERING OF CASING AND


ALLOWS MAX STAND OFF
 WITH PROPER STAND 0FF, CEMENT SLURRY
COVERS ENTIRE CSG CIRCUMFERENTIALLY
 VERY IMPORTANT FOR DEVIATED WELL

• ELIMINATES REPAIR JOB


• SAVINGS IN RIGTIME

33
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

SELECTION OF PROPER C/TOOLS

9 MECHANICAL AIDS (TURBO/SPIROLISER)

 ENSURES ADDITIONAL LOCALISED


TURBULENCE
 EFFECTIVE FOR GOOD BOND THROUGH
LOCALISED ZONE ISOLATION WHEN
TURBULENCE CANNOT BE ACHIEVED DUE TO
PRESSURE LIMITATION

• ELIMINATES REPAIR JOB & THEREFORE SAVES RIGTIME


• ADDITIONAL COST IS INSIGNIFICANT

34
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

SELECTION OF PROPER C/MATERIALS

10.PREFLUSH / WASH / SPACER

 NEEDS TO BE USED FOR EFFECTIVE MUD


CAKE REMOVAL & MUD REPLACEMENT
BY
CEMENT SLURRY
 VERY EFFECTIVE WHEN TURBULENCE
CAN NOT BE ACHIEVED IN CEMENT SLURRY

• RESULTS IMPROVEMENT IN CEMENT BOND


• ADDITIONAL COST IS INSIGNIFICANT

35
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

PROPER DESIGNING OF
CEMENT SLURRY

36
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

Types of slurry –
Essential to meet WELL REQUIREMENT
Conventional slurry
Light weight slurry
Loss control slurry
Heavy weight slurry
Engineered cement slurry

37
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

PROPER JOB PLANNING

38
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

THERE IS NO SUBSTITUTION
FOR A GOOD PRIMARY
CEMENTATION JOB

FIRST TIME EVERYTIME

39
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

PLANNING OF A PRIMARY JOB

 IS CEMENT RISE SUFFICIENT?


 IS TURBULENCE ACHIEVABLE?
 IS CRITICAL CONTACT TIME ACHIEVABLE?
 DOES CEMENT RISE & DYNAMIC FORCE
CAUSE FORMATION FRACTURE?
o MULTISTAGE IS RQUIRED?
o LIGHTWEIGHT CEMENT IS
REQUIRED?
 IS SUFFICIENT STANDOFF MAINTAINED?
 SUFFICIENT STRENGTH DEVELOPED?
 IS SIMULATION RUN REQUIRED FOR
OPTIMISATION OF JOB PARAMETER?
40
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

HOW POOR PRIMARY JOB HAS MAJOR


CONSEQUENCES?
(STUDY OF MACONDO WELL BY DEEPWATER HORIZON)
 AT TD, CMTG SERVICE PROVIDER RECOMMENDED FOR 7”
LINER CEMENTATION FOLLOWED BY 7” TIE-BACK
CEMENTATION (FOR FOUR TIER SAFETY).
 OPERATOR LOWERED 7”X9 7/8” COMBINATION CASING
TO SAVE RIGTIME & EXPENSES
 CENTRALISER USED 6 Vs RECOMMENDED 21 NOS
 PRIOR TO CEMENTATION, MUD WAS NOT CIRCULATED &
CONDITIONED PROPERLY
 TOP OBJECT WAS NOT COVERED BY CEMENT
 DESPITE PRESSURE TEST PROBLEM DURING POSITIVE &
NEGATIVE TEST, OPERATOR PLACED 1ST A/PLUG.
 BEFORE 2ND A/PLUG, DURING RISER VOL DISPLACEMENT
WITH WATER, BLOWOUT OCCURRED
 ALL ABOVE WITHIN 20 HRS OF PRIMARY CEMENTATION
41
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

HOW POOR PLANNING & CMT SLURRY


DESIGN FOR A SECONDARY JOB HAS
MAJOR CONSEQUENCES?

(CASE STUDY OF A WELL IN INDIA)

WELL REQUIREMENT :

AFTER REACHING TD, OPEN HOLE WAS


REQUIRED TO BE ABANDONED BY
CEMENT PLUG AT 7” LINER SHOE TO
FACILITATE TESTING OF UPPER ZONES

42
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

HOW POOR PLANNING & CMT SLURRY DESIGN FOR A


SECONDARY JOB HAS MAJOR CONSEQUENCES?

 COMBINATION STRING OF 5” X 3 ½” DP WAS USED FOR PLUG


JOB IN THE WELL (5 7/8”OHX7”LX9 5/8“Csg)

 200M OF CEMENT PLUG WAS PLANNED

 AFTER P/O WELL COULD NOT BE CIRCULATED OUT AND


FINALLY CEMENT WAS FOUND TO BE SET AT 2 ½ HRS TIME
AGAINST DESIGNED 6 HRS THICKENING TIME

 EXCESS LENGTH OF C/PLUG COUPLED WITH RESTRICTED


ANNULUS RESULTED IN A STUCK UP OF THE STRING

 NUMBER OF DAYS WERE LOST IN FISHING OPERATION

 WELL WAS FINALLY ABANDONED W/O TESTING

43
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

OPTIMISATION OF WOC

44
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

WAITING ON CEMENTATION

ONCE CEMENTATION IS COMPLETE, WOC IS REQUIRED


FOR SUFFICIENT COMPRESSIVE STRENGTH
DEVELOPMENT IN CEMENT SLURRY TO START NEXT
OPERATION

WOC TIME IS REQUIRED TO BE GIVEN FOR


COMPRESSIVE STRENGTH DEVELOPMENT
•For Resuming drilling (500 PSI)
•For Recording CBL & VDL/PERFORATION
(2000 PSI)

45
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

WAITING ON CEMENTATION –cost reduction possibilities

In addition to all desired parameter, IDT


developed slurries have very early strength
development characteristics which can result in
considerable reduction of WOC.
Recently WOC has been reduced from 72 hrs to
48 hrs as proved in well PDEE in Cambay. Plan
is to reduce it further to 36 hrs

Institute of Drilling Technology, Dehradun


Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

OTHER FACTORS

47
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

WELL HEAD SELECTION


(TO SAVE WOC)

SELECTION OF TAILOR MADE


WELLHEAD LIKE SSMC (STANDARD
SNAP RING MODULAR COMPACT)
SAVES WELL TIME ON WOC

48
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

OTHER FACTORS

o DISPLACEMENT OF CEMENT SLURRY BY


WATER (IF FEASIBLE) TO PREVENT
MICROANNULUS

o COMBINING HERMATICAL TEST DURING


BUMPING OF TOP PLUG TO PREVENT DAMAGE
TO SET CEMENT

49
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

PROPER EVALUATION OF
CEMENT BOND

50
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

CEMENT JOB EVALUATION

QUALITY OF CEMENT BOND IS AFFECTED BY

•TOOL & CASING ECCENTRICITY

•CYCLE SKIPPING / TRAVEL TIME STRETCH

•WASH OUT OF FORMATION

•FAST FORMATION ARRIVAL

•DIFFERENCE IN SLURRY DENSITY

•DIFFERENCE IN CASING WEIGHT

•PRESENCE OF GAS / NON HOMOGENOUS FLUID


Institute of Drilling Technology, Dehradun 51
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

PROPER EVALUATION OF CEMENT QUALITY

•Understanding of strength and limitations of


cement bond log

•Basic principles of cement evaluation devices

TWO MAIN STEPS

•Recording of quality log

•Proper interpretation

Institute of Drilling Technology, Dehradun


Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

CEMENT JOB EVALUATION

LIMITATION OF CBL/VDL
Cement bond log measurement does not represent
3600 average of the sonic signals

Improper knowledge leads to wrong interpretation


Leads to unnecessary squeeze decisions

No CBL/VDL tool can identify a channel within a


cement sheath

Institute of Drilling Technology, Dehradun


Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

NEW TOOLS ARE AVAILABLE FOR


CEMENT BOND EVALUATION

CET : CEMENT EVALUATION TOOL


(THROUGH 6/8 SEGMENTS)

USIT : ULTRA SONIC IMAGING TOOL


(THROUGH 360D ROTATION)

HIGHER COST IS INSIGNIFICANT CONSIDERING


BENEFIT OF PROPER INTERPRETATION AND THERBY
REDUCING CHANCES OF UNWANTED REPAIR

54
Institute of Drilling Technology, Dehradun
Cost Effective Cement Planning
_________________________________________________________________________________________________________________________________________________________________________________________

THANK YOU

55